September 10, 2026
A permanent public ledger of 575 verified actions on the record. Each entry links directly to its underlying primary government document, council minutes, regulatory filing, or corroborated news report.
Opposition and Press Signals for September 10, 2026
National press investigations, local moratoriums, litigation, and community ratepayer pushbackIndiantown attorney drafting data center moratorium (opens in a new tab)
Indiantown Village Council voted unanimously to direct legal counsel to draft a data center moratorium and transparency ordinance as part of newly elected leadership efforts to pause data center applications.
-
S.B. 1179, Energy: other; reporting requirements for data centers; provide for. Creates new act.
S.B. 1179 was introduced in the Senate. September 10, 2026.
-
S.B. 1179, Energy: other; reporting requirements for data centers; provide for. Creates new act.
S.B. 1179 went to committee in the Senate. September 10, 2026.
-
A. 5396, Requires data centers to submit water supply emergency contingency plan to DEP.
A. 5396 was introduced in the General Assembly. September 10, 2026.
-
A. 5396, Requires data centers to submit water supply emergency contingency plan to DEP.
A. 5396 went to committee in the General Assembly. September 10, 2026.
-
A. 5397, Requires data centers to submit construction phase water usage plan to DEP.
A. 5397 was introduced in the General Assembly. September 10, 2026.
-
A. 5397, Requires data centers to submit construction phase water usage plan to DEP.
A. 5397 went to committee in the General Assembly. September 10, 2026.
-
A. 5373, Concerns noise abatement of data centers.
A. 5373 was introduced in the General Assembly. September 10, 2026.
-
A. 5373, Concerns noise abatement of data centers.
A. 5373 went to committee in the General Assembly. September 10, 2026.
-
Sioux County
Planning and Zoning Board voted to recommend the draft ordinance to the supervisors on September 10, 2026.
-
Troy
Troy Planning Commission voted 5-0 on September 10 to extend data center moratorium until March 2027.
-
Ionia
Ionia City Council and Planning Commission held joint informational meeting on September 10, 2026 to discuss data centers with MSU and Consumers Energy representatives.
-
Morton County
Morton County Commission approved data center ordinance on September 10, 2026.
-
Oregon
The Data Center Advisory Committee released preliminary findings on September 10, 2026.
-
Rapid City
Rapid City Planning Commission voted unanimously on September 10 to delay a vote on proposed data center ordinance amendments to the November 4 meeting.
-
United States (federal)
DOE identified 16 potential sites for AI data center infrastructure on DOE lands.
-
Jonathan Kreiss-Tomkins, Democratic candidate for Alaska governor
Plan requires local approval and ensures Alaskans do not shoulder electric rate increases or subsidize data center development. Said September 10, 2026.
-
Democratic candidate for Alaska governor
Jonathan Kreiss Tomkins, Democratic candidate for governor, proposed a moratorium on all new data centers in Alaska until the legislature passes comprehensive regulation. Said September 10, 2026.
-
Democratic gubernatorial candidate
Doug Jones accused Tuberville of ethical malpractice for accepting campaign funds from large tech companies currently building data centers in west Alabama. Said September 10, 2026.
-
Applied Digital Corporation donated $25,000 to Tommy Tuberville's gubernatorial campaign in August 2026. Said September 10, 2026.
-
Democratic gubernatorial candidate
Doug Jones proposed a one year moratorium on data centers and higher property tax brackets for data centers. Said September 10, 2026.
-
Applied Digital Corporation also donated $100,000 to Republican Forward, a conservative Alabama super PAC. Said September 10, 2026.
-
<UNKNOWN>
Arkansas lawmaker forms trade association focused on AI and data center policy. Said September 10, 2026.
-
environmental nonprofits
Colorado River flows have reduced by 20 percent since 2000. Said September 10, 2026.
-
environmental nonprofits
Colorado River flows have reduced by 30 percent since 2019. Said September 10, 2026.
-
assistant professor of agricultural and resource economics
Shinsuke Tanaka stated that downwind pollution from power plants led to higher COVID-19 mortality rates. Said September 10, 2026.
-
Republican gubernatorial candidate
Byron Donalds says data center industry donations do not influence his policy positions. Said September 10, 2026.
-
Republican gubernatorial candidate
Donalds says data centers are essential to commercial space race and national security. Said September 10, 2026.
-
Janet Smith, Interim Village Attorney, Indiantown Village
"I have statutory exceptions that the Council can use for trade secrets. If someone is bringing forward a proposal considered a trade secret and they're willing to indemnify the Village while they speak to us so we can protect their records, then we have that opportunity. So, an NDA should not be needed." Said September 10, 2026, Indiantown Village Council Meeting.
-
Janet Smith, Interim Village Attorney, Indiantown Village
"What we would like to proffer to the Council is two ordinances. They will both have to go through planning and zoning and come before you on two separate readings. You will have public comment at each of those meetings. The first one is the moratorium that we feel will be legally defensible. The second one is the transparency ordinance." Said September 10, 2026, Indiantown Village Council Meeting.
-
Republican gubernatorial candidate
Donalds advocates for local control on data centers. Said September 10, 2026.
-
Thor Equities states each direct data center job at Kingston Technology Hub would create an additional 4.5 ancillary jobs. Said September 10, 2026.
-
Google representative
Jen Ryan stated that Google worked with Columbia County leadership to exceed decibel standards and buffers for the data center. Said September 10, 2026.
-
Google representative Jen Ryan spoke at the Future Forward Summit about the Google data center coming to Columbia County, discussing standards for noise, lighting, and water usage. Said September 10, 2026.
-
Google representative
Jen Ryan said data centers employ many people, citing hundreds of employees at the Douglas County data center on any given day. Said September 10, 2026.
-
Columbia County Commissioner Doug Duncan stated that Google was an opponent during negotiations but understood the county's vision. Said September 10, 2026.
-
Google representative
Jen Ryan said the data center will follow certain standards when it comes to noise, lighting, and water usage. Said September 10, 2026.
-
Republican gubernatorial candidate
Republican candidate Zach Lahn calls for a statewide pause on data center construction. Said September 10, 2026.
-
Democratic gubernatorial candidate
Democratic candidate Rob Sand issued a standalone policy plan laying out his vision for data centers, calling for transparency, union jobs and setback requirements. Said September 10, 2026.
-
Democratic gubernatorial candidate
Sand stated Iowans have been getting a raw deal from data centers. Said September 10, 2026.
-
NO Data Center Concert organized by Robbie Bahr held in protest on September 13 from 2 to 10 p.m. at Clinton, Iowa Bandshell. Said September 10, 2026.
-
Illinois PIRG cites extreme energy demand and enormous water use as data center problems. Said September 10, 2026.
-
Chicago Tribune Editorial Board
Illinois experiencing higher electric bills directly translated from datacenter electricity consumption. Said September 10, 2026.
-
Illinois PIRG advocates for two year moratorium on large data centers. Said September 10, 2026.
-
Arnolt Center for Investigative Journalism
Companies are using non disclosure agreements to hide data center project details from the public in Indiana. Said September 10, 2026.
-
Shawnee County Commissioner Kevin Cook addressed data center debate at county level. Said September 10, 2026.
-
Coalition demands state and local policies prioritizing health, safety, welfare of Kansas communities with guardrails on water, energy, air, land, transportation, health. Said September 10, 2026.
-
International Brotherhood of Electrical Workers strongly supports data centers because they require large numbers of electricians. Said September 10, 2026.
-
Walter Mugdan, former EPA deputy regional administrator, said public involvement in pollution decision making matters and government should open doors not close them. Said September 10, 2026.
-
resident (Covington, LA)
Matt Hardey warns that electric bills could double if generating plants become stranded assets after 15 year data center contracts end. Said September 10, 2026.
-
Dr. Lynn Goldman, former EPA assistant administrator, said data center pollution poses health risks and EPA is weakening safeguards. Said September 10, 2026.
-
Louisiana state
Project must fully fund its own power generation and grid infrastructure costs. Said September 10, 2026.
-
Republican gubernatorial candidate
Republican Mike Minogue challenging Healey for governorship criticized her data center stance. Said September 10, 2026.
-
Louisa Conklin, Frederick County Council member, stated data center developers have legal avenues to protect themselves from council oversight and that water protection is a community priority. Said September 10, 2026.
-
2026 Democratic U.S. Senate candidate for Michigan
El Sayed calls for state and local moratorium on data centers until conditions are met. Said September 10, 2026.
-
U.S. Representative and Republican gubernatorial nominee
U.S. Rep. John James, Republican gubernatorial nominee, called for moratorium on new data centers until plan to protect people is in place, including environmental protections and ensuring electricity bills do not go up. Said September 10, 2026.
-
Jean Hardy, Michigan State University Associate Professor with the Department of Media and Information, said a data center proposal to Ionia, if it came, would be many years out and is unlikely. Said September 10, 2026.
-
Ypsilanti-area residents
Residents spoke against a proposed University of Michigan data and research center during a town hall meeting. Said September 10, 2026.
-
Consumers Energy representatives stated that data centers would not automatically increase electricity rates for nearby residents, as utility rates are subject to state regulatory approval. Said September 10, 2026.
-
Environmental Protection Network issued AI data center report detailing Trump administration actions that could increase pollution related health risks. Said September 10, 2026.
-
Michigan State University Associate Professor
Jean Hardy noted that Ionia has existing water capacity, including infrastructure from the former correctional facility, which could potentially be repurposed for a data center if one came to the area. Said September 10, 2026.
-
University of Michigan vice president for Government Relations
Chris Kolb, the U of M vice president for Government Relations, said the university is working with the local community. Said September 10, 2026.
-
University of Michigan interim vice president for Research and Innovation
Patricia Hurn, U of M interim vice president for Research and Innovation, spoke about the project. Said September 10, 2026.
-
2026 Democratic U.S. Senate candidate for Michigan
Abdul El Sayed states his conditions for University of Michigan data center: all union labor, no utility rate increases, no water use, revenue investment in reliability, and community benefits agreement. Said September 10, 2026.
-
Andrea Zupancich, Republican candidate for Minnesota state Senate
Grant Hauschild as part of Senate Tax Committee greenlit bills giving tax breaks to data centers. Said September 10, 2026.
-
U.S. Senator
Amy Klobuchar stated she would require any data center project to cover 100 percent of energy and grid costs. Said September 10, 2026.
-
Jobs for Minnesotans executive
Jobs for Minnesotans supports local data center development and trusts Minnesota's strict policies protecting environment, water quality, and energy generation. Said September 10, 2026.
-
Minnesota House Speaker
Lisa Demuth, House Speaker, negotiated bipartisan legislation that passed protecting Minnesotans' energy bills and putting data centers on the same playing field as other businesses for energy costs. Said September 10, 2026.
-
Republican candidate for Minnesota state Senate
Jobs for Minnesotans nonprofit board member Andrea Zupancich opposes tax breaks for data centers while running for state Senate against Grant Hauschild who supports them. Said September 10, 2026.
-
State Representative
Rep. Jeff Myers represents District 42, which includes Montgomery and Warren Counties, where a large data center is being built. Said September 10, 2026.
-
Nick Kasoff, Ferguson councilmember, said the plan would freeze the assessed value of the former Emerson campus at its 2024 assessment rate with a 75 percent tax abatement for the first 10 years. Said September 10, 2026.
-
Adrian Shropshire, Ferguson mayor, opposed the data center proposal and plans to vote against it. Said September 10, 2026.
-
NorthWestern Energy said it is in conversation with at least 11 data center developers. Said September 10, 2026.
-
NorthWestern Energy associate general counsel Mike Green stated that preventing any cost shifting is not realistic. Said September 10, 2026.
-
company officials
Applied Digital held a town hall meeting on its Harwood data center in August 2025 after construction plans were finished. Said September 10, 2026.
-
Councilor Phil Jones cited concerns about noise, energy and water use, diesel generators, property values and infrastructure for large scale commercial data center facilities. Said September 10, 2026.
-
RMI
The report outlined how data centers and other large electricity customers could help finance and scale distributed capacity. Said September 10, 2026.
-
RMI published a report in November 2025 making the case that off site demand flexibility, energy efficiency, and distributed generation can help meet rapidly growing data center electricity demand. Said September 10, 2026.
-
RMI
Since the report's publication, new laws, commission decisions, and utility proposals have begun creating pathways for large customers to fund distributed capacity. Said September 10, 2026.
-
Critics say the risk to local power bills isn't worth it. Said September 10, 2026.
-
Clark County Education Association
CCEA estimates their proposal could bring $2 billion in local schools support tax to the state pupil centered funding formula in four years. Said September 10, 2026.
-
Dina Neal is a Nevada state senator. Said September 10, 2026.
-
John Vellardita, Clark County Education Association Executive Director
Clark County Education Association proposes requiring data centers to pay Local School Support Tax, a 2.6 percent tax on retail sales. Said September 10, 2026.
-
Attorney General Aaron Ford said he supports a pause on data center tax abatements if elected. Said September 10, 2026.
-
Clark County Education Association
New or expanding data centers receive a 75 percent abatement on personal property tax and pay a reduced sales and use tax rate of 2 percent for 10 to 20 years. Said September 10, 2026.
-
Interior Board of Land Appeals judge
Judge David Gunter found appellants likely to prevail requiring Bureau of Land Management to provide new environmental studies and public input before project can proceed. Said September 10, 2026.
-
John Vellardita, Clark County Education Association Executive Director
Data centers receive property tax breaks up to 75 percent for 10 or 20 years, contingent on retaining 10 or 50 full time employees. Said September 10, 2026.
-
Gov. Joe Lombardo is supportive of data centers and says state has safeguards in place. Said September 10, 2026.
-
State Sen. Dina Neal requested drafting bill to end tax abatements and implement moratorium on data centers. Said September 10, 2026.
-
Geneva Zoltek, climate reporter
Nevada experiencing data center boom with massive power demand. Said September 10, 2026.
-
Clark County Education Association
CCEA proposes ending abatement of local schools support tax for data centers. Said September 10, 2026.
-
CCEA Executive Director
John Vellardita says there are seven to nine new data centers planned to open in Nevada. Said September 10, 2026.
-
James Rogan, former U.S. diplomat
Author states that electricity prices remain highest in states that mandated green transitions without adequate baseload power. Said September 10, 2026.
-
Microsoft executives
Microsoft temporarily paused select data center developments around early 2025 due to concerns about overbuilding. Said September 10, 2026.
-
U.S. Senator
Bernie Moreno plans to introduce federal legislation aimed at eliminating the financial benefit of state and local tax incentives for data centers. Said September 10, 2026.
-
U.S. Senator
Moreno proposes imposing a federal tax equal to 100% of any tax incentive provided to a data center by a state or local government. Said September 10, 2026.
-
State Rep.
Rader raised concern about private equity owning both data centers and power companies serving the same grid. Said September 10, 2026.
-
Ohio Democratic Party held rally in Bowling Green to denounce Jon Husted for bringing hundreds of data centers to Ohio. Said September 10, 2026.
-
U.S. Senator
Moreno criticized a 4.5 million dollar Ohio tax incentive connected to a data center expansion backed by the Carlyle Group in March 2026, arguing the project was expected to create only 10 new jobs. Said September 10, 2026.
-
U.S. Senator
Jon Husted introduced the Ratepayer Protection Act in July 2026, requiring states to consider standards for connecting large electricity users, including data centers, to the electric grid. Said September 10, 2026.
-
Ohio State Representative
Daniel Troy stated Ohio is a national leader in both operational data centers and tax breaks offered to these facilities. Said September 10, 2026.
-
Wood County auditor candidate
Mark Wongrowski said Meta data center north of Bowling Green in Middleton Township required 75 percent tax abatement for 15 years. Said September 10, 2026.
-
Cleveland Councilman Ward 15
Ward 15 Cleveland Councilman Charles Slife proposed updating the city's zoning code to prevent data center workarounds. Said September 10, 2026.
-
State Rep. Tristan Rader warned Ohioans about unrestricted data center growth and conflict of interest concerns. Said September 10, 2026.
-
Mark Wongrowski, Wood County auditor candidate
Ohio electricity bills have gone up double the national average. Said September 10, 2026.
-
Beth Cole, Middleton Township resident
Meta data center footprint is now 5 percent of Middleton Township. Said September 10, 2026.
-
Ohio State Representative
Democratic Rep. Tristan Rader proposes repealing the sales tax exemption and renegotiating past deals with Amazon, Meta and Google. Said September 10, 2026.
-
Courtney Lee, senior manager for state and local policy, Amazon Web Services
Amazon representative said Amazon data center uses less water than local agriculture industry. Said September 10, 2026.
-
Courtney Lee, senior manager for state and local policy, Amazon Web Services
Amazon representative said company runs diesel generators about 12 hours per year for testing and maintenance. Said September 10, 2026.
-
Jim Doherty, former Morrow County Commissioner, said opposition to data centers is a unifying moment between rural and urban Oregon. Said September 10, 2026.
-
Chair, Morrow County Board of Commissioners
David Sykes, chair of the Morrow County Board of Commissioners, said decisions over data centers on private property are up to local government. Said September 10, 2026.
-
Sean Trende, American Enterprise Institute
Republicans oppose data centers with a bare majority opposed and just 29 percent strongly opposed. Said September 10, 2026.
-
Sean Trende, American Enterprise Institute
By July 2026, support for data centers in or near community was down to 22 percent, opposition was up to 57 percent. Said September 10, 2026.
-
Sean Trende, American Enterprise Institute
In December 2025, 34 percent of Pennsylvanians supported data centers in or near their community, 42 percent opposed, and 24 percent had no strong opinion. Said September 10, 2026.
-
Sean Trende, American Enterprise Institute
Democrats oppose data centers more than other groups, with 71 percent opposed and more than half strongly opposed. Said September 10, 2026.
-
Democratic candidate
Bob Harvie called for a data center moratorium in his campaign. Said September 10, 2026.
-
Sean Trende, American Enterprise Institute
In Pennsylvania 7th Congressional District, opposition to data centers runs 74 percent to 14 percent support. Said September 10, 2026.
-
Harvie previously supported tax break for Amazon data center in Falls Township during Bucks County Commissioners vote in December 2020. Said September 10, 2026.
-
Southern Environmental Law Center advocated for a pause on data centers and raised concerns about a data center currently under construction on South Pine Street. Said September 10, 2026.
-
Sarah Knox, director of external affairs for NorthMark Strategies
NorthMark is complying with state laws and is still waiting on an air permit to operate and hopes to receive it by the end of the year. Said September 10, 2026.
-
Lee Zeldin, EPA director, said making the United States the artificial intelligence capital of the world is the agency's top priority. Said September 10, 2026.
-
Matt Krause, Tarrant County Commissioner
A planned data center in Westlake was discussed at the town hall. Said September 10, 2026.
-
Kate Franko, Fluidstack head of public affairs
Fluidstack will pay full local property taxes without requesting tax abatements or county incentives. Said September 10, 2026.
-
Kate Franko, Fluidstack head of public affairs
Fluidstack will pay for its own energy and infrastructure. Said September 10, 2026.
-
Tarrant County Commissioner
Krause said the state could develop a legislative agenda for data centers for the 2027 session. Said September 10, 2026.
-
Susanne DeHart, Pulaski County citizen
Tax rate for the data center facility is unknown but guaranteed not the same as citizens of Pulaski County who will have property reassessed in 2027. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
The Data Infrastructure Risk Reduction Act would require development of a strategy to protect communities near data centers from national security threats. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
Data Center Fair Share Act requires data centers and other large energy users to pay the full cost of grid and generation upgrades needed to serve them. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
The Data Center Fair Share Act would require states to establish utility rates to make data centers pay full incremental grid upgrade costs, with loss of federal highway funding as penalty for non compliance. Said September 10, 2026.
-
U.S. Representative (Virginia's 10th district)
U.S. Rep. Suhas Subramanyam announced a four bill National Data Center Plan to establish national standards for data center siting, utility rates, energy and water measurement, and infrastructure security. Said September 10, 2026.
-
David Aldrich and Chris Miller
Each transmission line corridor has a minimum 300 foot wide right of way affecting rural and suburban communities. Said September 10, 2026.
-
David Aldrich and Chris Miller
Data centers require thousands of miles of new transmission lines, hundreds of new substations, and dozens of new power plants. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
The Data Infrastructure Energy Measurement and Standards Act would direct NIST to develop standards for measuring data center energy and water consumption. Said September 10, 2026.
-
David Aldrich and Chris Miller
Virginia needs to immediately pause all data center contracts for interconnections to the power grid until a plan addresses six critical issues. Said September 10, 2026.
-
David Aldrich and Chris Miller
If 85 GW of data center capacity were built out, Virginia's current power grid would quadruple in size. Said September 10, 2026.
-
U.S. Representative
Rep. Subramanyam introduced bills directing government agencies to create official standards for measuring data center energy and water use. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
Residents report utility bills doubling due to data center infrastructure demands. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
The Responsible Data Center Siting Act would direct the U.S. Department of Energy to establish best practices for data center siting considering electricity, water, environment, noise, security, workforce and tax revenue. Said September 10, 2026.
-
Suhas Subramanyam, U.S. Representative
Four bills include Responsible Data Center Siting Act, Data Center Fair Share Act, Data Infrastructure Energy Measurement and Standards Act, and Data Infrastructure Risk Reduction Act. Said September 10, 2026.
-
Anirban Basu, chief economist at Associated Builders and Contractors
Data center related construction activity was byproduct of nonresidential specialty trade employment growth. Said September 10, 2026.
-
Alliant Energy President of Wisconsin operations
Becky Valcq, President of Alliant Energy's Wisconsin electric company and Vice President of Energy Delivery, spoke at an educational session about data centers. Said September 10, 2026.
-
Governor
Gov. Patrick Morrisey highlights economic development with hyperscale data centers. Said September 10, 2026.
-
Eric Schlidt, Prometheus Build Wyoming director
Prometheus is asking commissioners to bypass the state industrial siting review to speed up build time. Said September 10, 2026.
-
vice president of policy, Rewiring America
Kristin Eberhard, vice president of policy with Rewiring America, said the concern is not just knee jerk resistance to growth but opposition to communities absorbing costs while others get benefits. Said September 10, 2026.
-
San Francisco
San Francisco considering moratorium on new data centers.
-
Florida
Hillsborough County Commissioners voted unanimously last month to draft moratorium on data centers and develop land use rules prohibiting facilities from using drinking water for cooling.
-
Palm Beach County
Palm Beach County Commissioners rejected planned hyperscale data center campus in July by 5-1 vote.
-
Florida
More than a dozen Florida counties have adopted or advanced moratoriums or bans by late June, including Clay, Lake and Nassau counties.
-
Florida
Governor Ron DeSantis signed law in May codifying local governments' power to regulate data center developments through comprehensive plans.
-
Miami Lakes
Miami Lakes Town Council set to consider item by Steven Herzberg to trigger development of ordinance defining and prohibiting dedicated data centers as principal use.
-
Salix
Salix, IA city leaders discussed a data center ordinance and future conversations with Google.
-
Salix
Salix city leaders discussed data center ordinance and future conversations with Google.
-
Hancock County
Three dozen people spoke at public hearing, majority opposing the data center.
-
Hancock County
MCNI requested rezoning of 724 acres in Concord Township from agricultural to industrial for data center development.
-
Hancock County
Hancock County Planning and Zoning Commission voted unanimously to deny zoning change request for data center near Garner.
-
Illinois
Gov. Pritzker in June suspended state tax breaks for datacenters in effect since 2020.
-
Kentucky
A Kentucky think tank identified potential loopholes in data center tax incentive policy.
-
Kentucky
Kentucky schools and local governments may receive tax benefits from data center projects.
-
Kentucky
Kentucky state law exempts manufacturing facilities using significant energy from sales tax on energy expenses exceeding 3 percent of gross production costs.
-
Kentucky
Power service agreement subject to approval by Kentucky Public Service Commission.
-
Calcasieu Parish
Project requires Calcasieu Parish Planning and Zoning Board approval.
-
Louisiana
The Lightning Amendment speeds data center approval process with little or no public oversight.
-
Louisiana
The Public Service Commission is negotiating contract terms for data centers to cover power generation costs for 15 years.
-
Massachusetts
Massachusetts paused data center sales tax exemption.
-
Massachusetts
Governor Maura Healey issued executive order requiring data centers over 25 megawatts to supply 100 percent of electricity through clean energy or contribute to ratepayer protection fund.
-
Massachusetts
Governor Maura Healey issued Executive Order 658 establishing framework for data center development.
-
Massachusetts
Framework required data centers to bring or fund clean energy generation sufficient to meet 100 percent of demand released June 2026.
-
Massachusetts
Data centers must demonstrate clean energy compliance before state permits; community approval required.
-
Massachusetts
Payments go into Ratepayer Protection Fund to mitigate electricity supply costs.
-
Massachusetts
MassDEP must establish alternative compliance payment mechanism by December 31 2026 for projects not meeting clean energy requirement.
-
Massachusetts
Massachusetts previously stopped offering sales tax incentives for data centers.
-
Massachusetts
Developers must arrange and finance own clean energy and related infrastructure or chip into ratepayer protection fund.
-
Massachusetts
Order outlaws nondisclosure deals between state agencies and data center developers.
-
Massachusetts
Governor Healey signed executive order requiring data center projects to need local buy in via community benefits agreements before state will sign off.
-
Michigan
Michigan utility regulator will decide whether to approve DTE Energy contracts for Google's 1 gigawatt data center project in Van Buren Township.
-
Ypsilanti Township
Community town hall scheduled for October 1, 2026 at 5:30 PM at Ann Arbor Marriott Ypsilanti at Eagle Crest.
-
Ypsilanti Township
University of Michigan Board of Regents meeting scheduled for September 17, 2026.
-
Ypsilanti Township
Ypsilanti Township Board of Trustees meeting scheduled for September 15, 2026 at 6:00 PM.
-
Ypsilanti Township
Township utility provider enacted moratorium on supplying data centers with water.
-
Ypsilanti Township
Ypsilanti Township passed resolutions opposing the project.
-
Ypsilanti Township
A town hall was held on a proposed high performance research computing center.
-
Ypsilanti Township
University of Michigan leaders held town hall discussion about high performance research computing center in Ypsilanti Township.
-
Minnesota
Minnesota legislature successfully passed a standalone data center bill in 2025 that included environmental regulation, a repeal of a sales tax exemption on electricity, and a later expiration of sales exemptions on software and hardware.
-
Minnesota
Minnesota legislature in 2026 had bipartisan effort to ban non disclosure agreements for data centers, but the bill died.
-
Minnesota
Data center moratoriums create delays increasing legal, engineering, environmental, utility and financing costs.
-
Minnesota
Development moratorium can pause rezoning, conditional use permits, site plan approvals, subdivision approvals.
-
Minnesota
Minnesota municipalities have generally imposed initial data center moratoriums of up to one year.
-
Desloge
Public comments called for a planning moratorium on data centers.
-
Desloge
Several hundred regional residents attended and public comments largely opposed the idea.
-
St. Louis
The proposed Board of Aldermen Bill 24 is scheduled for a final board vote Friday.
-
St. Louis
Board of Aldermen Bill 24 recently advanced to establish a zoning framework for where data centers can operate and how the city addresses energy use, noise, lighting and compatibility with surrounding neighborhoods.
-
Ferguson
The proposal requires the developer to pay Ferguson Neighborhood Improvement Program $7.5 million over 10 years.
-
Ferguson
Ferguson councilmembers reintroduced legislation Wednesday for $1.5 billion in tax incentives and up to $22 billion in industrial revenue bonds for the Emerson campus data center redevelopment.
-
Ferguson
Ferguson City Council voted 3-3 with one abstention on a data center tax break proposal in May 2026.
-
Missoula County
Missoula County is preparing study on data center impacts and mitigation strategies, with draft presentations planned for November 4 and 12, 2026.
-
Missoula County
Missoula County implemented one year moratorium on new or expanded data centers effective July 9, 2026.
-
Harwood
Charter amendment to require transparency in industrial negotiations is set for Harwood ballot in November.
-
Spotswood
Spotswood city council sent a data center zoning proposal to the planning board.
-
New Jersey
New Jersey and Virginia are considering regulations to prevent data centers from shifting increased power usage costs to customers.
-
Nevada
CCEA proposal includes mandatory transparency and audits for data center environmental compliance.
-
Nevada
CCEA proposal requires data center water to be returned to Nevada if drawn from state.
-
Nevada
CCEA proposal requires communities to have local control over whether data center is built and location.
-
Nevada
CCEA proposal requires data centers to build their own power and cannot draw on state power grid.
-
Nevada
Clark County Education Association proposes eliminating Local School Support Tax abatement for data centers.
-
Nevada
Senate Bill 170 provided sales and property tax abatements to attract data centers to Nevada.
-
Nevada
The proposed moratorium could be taken up during the 2027 legislative session.
-
Nevada
Nevada lawmakers moved to draft legislation for a potential moratorium on new data center development during a legislative revenue committee meeting in late August.
-
Nevada
Tax abatements last for 10 or 20 years depending on capital expenditures and jobs created.
-
Nevada
Data centers pay reduced sales and use tax rate of 2%.
-
Nevada
New or expanding data centers receive 75% abatement on personal property tax.
-
Nevada
Clark County Education Association unveiled plan to end abatement of local schools support tax for data centers.
-
Nevada
NV Energy will need to more than double its current electricity load by 2046 to meet data center demand.
-
Nevada
Interim revenue committee of lawmakers voted to draft a bill to pause data centers across Nevada and repeal tax abatements.
-
Ohio
Ohio Data Center Tax Exemption established in 2013 as 100 percent sales tax exemption.
-
Ohio
House Bill 999 introduced to ban property tax exemptions for data centers and examine termination of existing abatements.
-
Ohio
Lawmakers expect data center reform proposals may be consolidated into House Bill 646.
-
Ohio
House Bill 646 attempted and failed to pass before June 2026 General Assembly recess.
-
Ohio
Rep. Daniel Troy introduced proposal for eliminating property tax abatements for data centers.
-
Ohio
Rep. David Thomas drafting language to eliminate property tax abatements for data centers.
-
Ohio
Governor Mike DeWine paused data center sales tax exemptions via executive order earlier in 2026.
-
Ohio
Rep. Tristan Rader introduced bill to prohibit data center companies from receiving any new state sales tax exemptions.
-
Ohio
Some Ohio legislators want to repeal the data center tax exemption outright and reopen long term agreements.
-
Ohio
Ohio Governor Mike DeWine froze new applications for data center tax exemptions.
-
Ohio
In May 2026, Gov. Mike DeWine paused new applications for the data center sales tax exemption after public backlash over the scale of the tax break.
-
Ohio
Gov. Mike DeWine paused new data center incentives earlier in 2026 after reporting indicated the cost of existing incentives in 2025 was substantially higher than previously projected.
-
Ohio
Ohio law provides tax exemptions for certain computer data center equipment and investments under a program that took effect in 2025.
-
Oregon
Kotek issued an executive order pausing any new developments on state owned land.
-
Oregon
Oregon Gov. Tina Kotek announced support for a statewide moratorium on the construction of new data centers.
-
Salem
Salem Data Center Task Force is crafting a policy proposal for city council approval.
-
Salem
Salem city scheduled third town hall on data center policies on October 20.
-
Salem
Salem city scheduled second town hall on data center policies on October 6.
-
Salem
Salem city scheduled first town hall on data center policies on September 15 at 5-7 p.m.
-
Wyoming County
Wyoming County commissioners voted to formally adopt an amendment to the county's Subdivision and Land Development Ordinance for data center development.
-
Indiana County
Tabling decision triggers 90 day investigation period for Planning Commission review.
-
Indiana County
Indiana County Planning Commission voted to table Amazon Web Services application for data centers in Center and Black Lick Townships.
-
South Carolina
South Carolina passed ruling that power plants for data centers can be constructed without review or approval from state's regulatory commission.
-
South Carolina
South Carolina Public Service Commission ruled that private technology company generating power for its own use not subject to Utility Siting Act.
-
South Carolina
A third and final vote on the one year moratorium is expected later this month, on September 21.
-
South Carolina
The meeting followed a delayed vote last month on a proposed one year moratorium on data centers.
-
South Carolina
Spartanburg County Council held a special called meeting on data centers.
-
Spartanburg County
Residents stormed out during data center debate in Spartanburg County.
-
Texas
Texas Gov. Abbott imposed a moratorium on data center development in the state.
-
United States (federal)
EPA proposed change would let developers start building data centers before permits are approved.
-
United States (federal)
EPA plans to scrap federal requirement that states tell the public and allow public comment before approving air pollution permits for industrial facilities including data centers and power plants.
-
United States (federal)
More than 10 states are reconsidering or pausing tax breaks for data centers.
-
Virginia
New Jersey and Virginia are considering regulations to prevent data centers from shifting increased power usage costs to customers.
-
Pulaski County
Survey of NRV Commerce Park website showed 102 responses; 95 percent opposed data centers in Pulaski County.
-
West Virginia
Communities from Putnam County to Tucker County formed Data Center Accountability Project to demand state and local leaders prioritize communities over computers.
-
West Virginia
Multiple data center projects have been proposed across West Virginia.
-
Bisnow
Kingston Technology Hub estimated cost is $1 billion. Cartersville, Bartow County, GA, 2026.
Key Figure 1,000,000,000 USD -
yahoo.com
Texas planned gas generation grew 50 percent. Texas, statewide, 2026.
Key Figure 50 percent -
ktnv.com
Data centers consumed 22 percent of Nevada electricity generation capacity in 2024 according to Desert Research Institute. Nevada, statewide, 2026.
Key Figure 22 percent -
Wyoming Public Media
74% of survey respondents said they would be more supportive of data centers if developers helped offset their home electricity costs. United States, statewide, 2026.
Key Figure 74 percent -
Pittsburgh Post-Gazette
Project Phoenix is a 2 gigawatt data center project. Beaver County, PA, 2026.
Key Figure 2 GW -
Nevada Current
Nevada abated $90 million in sales tax for data centers in 2021 and 2022. Nevada, statewide, 2026.
Key Figure 90,000,000 USD -
kolotv.com
State could capture minimum 500 million dollars annually for K-12 education if abatements eliminated. Clark County, Nevada, NV, 2026.
Key Figure 500,000,000 dollars a year -
Louisiana Illuminator
University of California Riverside and California Institute of Technology 2026 study estimated data center pollution could cause roughly 600,000 asthma cases and 1,300 premature deaths under rapid development scenario by 2028. LA, 2026.
Key Figure 600,000 asthma cases -
yahoo.com
Texas already has 81.7 gigawatts of gas power in operation. Texas, statewide, 2026.
Key Figure 81.7 GW -
Colorado Public Radio
At 50 megawatts, Project Taurus would consume about a quarter of the monthly power used by all households in Colorado Springs. Colorado Springs, El Paso County, CO, 2026.
Key Figure 50 MW -
mountain-topmedia.com
International Brotherhood of Electrical Workers donated $206,000 to In This Together, Kentucky Gov. Beshear's PAC, making the union the fourth largest donor since 2023. Kentucky, statewide, 2026.
Key Figure 206,000 USD -
arkansasonline.com
Initial power demand of 150 megawatts with potential growth to one gigawatt. Pulaski County, AR, 2026.
Key Figure 150 MW -
cbsnews.com
The facility is a $1.2 billion research computing facility. Ypsilanti Township, Michigan, 2026.
Key Figure 1,200,000,000 USD -
Stocktwits
Amazon paid almost 11 million dollars in Ohio state property taxes and fees last year. Ohio, statewide, 2026.
Key Figure 11,000,000 dollars -
Stocktwits
Meta paid over 40 million dollars in Ohio property taxes and fees during the 2018 to 2026 period. Ohio, statewide, 2026.
Key Figure 40,000,000 dollars -
Deseret News
Project Oasis at Delta Gigasite aims to generate approximately 4,000 acre feet of water per year. Delta, Millard County, UT, 2026.
Key Figure 4,000 acre feet per year -
Wyoming Public Media
The project is expected to create approximately 150 jobs. Natrona County, WY, 2026.
Key Figure 150 jobs -
ktnv.com
NV Energy proposes 1,223 megawatts of natural gas combustion turbines. Nevada, statewide, 2026.
Key Figure 1,223 MW -
capitalbnews.org
In communities surrounding Meta's data center, median home and rental prices rose 80 percent in one year. SC, 2026.
Key Figure 80 percent -
Stocktwits
Meta has invested more than 2.3 billion dollars in Ohio data centers since 2018. Ohio, statewide, 2026.
Key Figure 2,300,000,000 dollars -
yahoo.com
Texas has 99.4 gigawatts of gas power in development. Texas, statewide, 2026.
Key Figure 99.4 GW -
KRGV
The project is expected to create more than 2,500 construction jobs. Cameron County, TX, 2026.
Key Figure 2,500 jobs -
ktnv.com
NV Energy proposes 5,405 megawatts of battery energy storage systems. Nevada, statewide, 2026.
Key Figure 5,405 MW -
The Clinton Chronicle
Valara facility permitted for 24 natural gas generators at 2000 kilowatts each. Spartanburg County, SC, 2026.
Key Figure 2,000 kW -
Texas Border Business
First phase expected to create more than 2,500 construction jobs. Rio Hondo, Cameron County, TX, 2026.
Key Figure 2,500 jobs -
Planet Detroit
Project will create 30 to 50 technical support jobs, 200 higher level research jobs, and 300 temporary construction jobs. Ypsilanti Township, Washtenaw County, MI, 2026.
Key Figure 30 to 50 jobs -
linkedin.com
Quincy Washington water system saving 138 million gallons a year through data center water reuse. Quincy, WA, 2026.
Key Figure 138,000,000 gallons a year -
ktnv.com
Desert Research Institute estimates data center electricity consumption will grow to more than 35 percent by 2030 with estimated cost of more than 2.8 billion dollars each year. Nevada, statewide, 2026.
Key Figure 2,800,000,000 dollars -
Nevada Public Radio KNPR
The tax abatement proposal could generate as much as 500 million dollars a year for schools statewide. Nevada, statewide, 2026.
Key Figure 500,000,000 dollars a year -
dailyreporter.com
Nonresidential building lost 1,800 jobs in August. United States, statewide, 2026.
Key Figure 1,800 jobs -
wowo.com
Google, Meta and Amazon each have agreements valued at roughly 600 million dollars over 40 years. Columbus, Ohio, 2026.
Key Figure 600,000,000 dollars -
kolotv.com
Over 16 years Nevada has given away over 350 million dollars in tax abatements to data centers. Clark County, Nevada, NV, 2026.
Key Figure 350,000,000 dollars -
Yahoo Finance
Alpha Compute secured 47 million dollars in seller financing. Tioga County, PA, 2026.
Key Figure 47,000,000 dollars -
OPB
Data centers took up 15.7 million square feet in the region east of the Cascades, equivalent to 270 football fields. Morrow County, OR; Umatilla County, OR; Eastern Oregon, statewide, 2026.
Key Figure 15,700,000 square feet -
nbc4i.com
Sales tax exemptions for data centers cost Ohio at least $1.5 billion in 2025. OH, 2026.
Key Figure 1,500,000,000 USD -
Yahoo Finance
Marcellus resource could supply 200 MW of continuous generation for ten years at approximately 0.0585 dollars per kilowatt hour. Tioga County, PA, 2026.
Key Figure 0.06 dollars per kilowatt hour -
wowo.com
Ohio has committed at least 2.3 billion dollars in sales tax exemptions for data centers. Columbus, Ohio, 2026.
Key Figure 2,300,000,000 dollars -
Planet Detroit
Computing center has capacity of 100 megawatts. Ypsilanti Township, Washtenaw County, MI, 2026.
Key Figure 100 MW -
PA Environment Digest Blog
PJM Interconnection identified system wide reliability shortfall of 6,831 megawatts for 2028-29 delivery year in July 2026 capacity auction. Pennsylvania, PA, 2026.
Key Figure 6,831 MW -
KDHL Radio
Duluth has 6 data centers. Minnesota, statewide, 2026.
Key Figure 6 count -
ktnv.com
Data centers projected to account for 64 percent of NV Energy power sales by 2046. Nevada, statewide, 2026.
Key Figure 64 percent -
The Clinton Chronicle
Valara applied for additional 5 natural gas combustion turbines at 17 megawatts each and 6 turbines at 54 megawatts each. Spartanburg County, SC, 2026.
Key Figure 17 MW -
NBC4 Washington
Up to 200 more data centers are planned for Northern Virginia in coming years. Northern Virginia, VA, 2026.
Key Figure 200 data centers -
dailyreporter.com
Construction employment expanded by 120,000 jobs, or 1.5 percent year over year. United States, statewide, 2026.
Key Figure 120,000 jobs -
Morning Journal
Data Center Tax Exemption cost the state 1.6 billion dollars as of 2025. Ohio, statewide, 2026.
Key Figure 1,600,000,000 dollars -
TradingView
Microsoft aims to scale AI dedicated capacity to roughly one third of the total 38 gigawatt capacity by 2032, from about 2 gigawatts currently. NY, 2026.
Key Figure 2 GW -
linkedin.com
Quincy Washington achieved 72 percent lower property taxes through data center development. Quincy, WA, 2026.
Key Figure 72 percent -
News From The States
Nevada abated $240 million in sales tax for data centers in 2023 and 2024. Clark County, NV, 2026.
Key Figure 240,000,000 USD -
Bisnow
Kingston Technology Hub expected to use 50,000 gallons of water daily. Cartersville, Bartow County, GA, 2026.
Key Figure 50,000 gallons a day -
linkedin.com
Quincy Washington data centers generated 6 billion plus in new tax base. Quincy, WA, 2026.
Key Figure 6,000,000,000 dollars -
Construction Review
The project is expected to drive approximately $10 billion in regional investment. Shippingport, Beaver County, PA, 2026.
Key Figure 10,000,000,000 USD -
yahoo.com
Oregon data center tax breaks total more than $450 million annually. Oregon, statewide, 2026.
Key Figure 450,000,000 USD -
Las Vegas Review-Journal
Data centers would have generated an additional $357 million for schools since 2015 had they been required to pay Local School Support Tax. Las Vegas, Clark County, NV, 2026.
Key Figure 357,000,000 USD -
dailyreporter.com
Construction industry added 22,000 jobs in August 2026. United States, statewide, 2026.
Key Figure 22,000 jobs -
Chicago Tribune
Polls show 70% or more of Americans oppose datacenters in their communities. United States, national, 2026.
Key Figure 70 percent -
Construction Review
The project is estimated to support about 3,000 construction jobs during development. Shippingport, Beaver County, PA, 2026.
Key Figure 3,000 jobs -
yahoo.com
The gas power tied to Nexus Data Center Hubbard is projected to emit 22 million tons annually. Texas, statewide, 2026.
Key Figure 22,000,000 tons per year -
Ahwatukee Foothills News
Department of Interior cut Arizona's Colorado River water supplies by almost 30%. Phoenix, Arizona, 2026.
Key Figure 30 percent -
News-Herald
State revenue loss from Ohio Data Center Tax Exemption was estimated at approximately 136 million dollars in 2013. Ohio, statewide, 2026.
Key Figure 136,000,000 dollars -
dailyreporter.com
Heavy and civil engineering added 4,400 jobs in August. United States, statewide, 2026.
Key Figure 4,400 jobs -
NBC4 Washington
Democratic U.S. Rep. Suhas Subramanyam represents 10th Congressional District with more than 300 data centers. Northern Virginia, VA, 2026.
Key Figure 300 data centers -
kolotv.com
Nevada per pupil funding is about 4000 dollars below the national average. Clark County, Nevada, NV, 2026.
Key Figure 4,000 dollars -
Patriot Publishing LLC
Survey results: 90 percent of respondents said data centers would not benefit Pulaski County and the New River Valley. Pulaski County, VA, 2026.
Key Figure 90 percent -
Cryptopolitan
Lowell residents saw electric bills climb more than 50 percent due to data center activity. Massachusetts, statewide, 2026.
Key Figure 50 percent -
Louisiana Illuminator
Environmental Protection Network report estimated data center related air pollution could impose 11.7 billion to 20.9 billion dollars in annual public health costs by 2028. LA, 2026.
Key Figure 11,700,000,000 to 20,900,000,000 dollars per year -
Richmond Times-Dispatch
Virginia is the largest data center market in the world with nearly 85 gigawatts of contracted electric power requests in the pipeline. Virginia, statewide, 2026.
Key Figure 85 GW -
Bisnow
Kingston Technology Hub has $2 million annual impact on local tax revenues. Cartersville, Bartow County, GA, 2026.
Key Figure 2,000,000 USD -
dailyreporter.com
Average monthly gain for specialty trade contractors over last 12 months was 6,000 employees. United States, statewide, 2026.
Key Figure 6,000 employees -
Ahwatukee Foothills News
Arizona State University study found data centers can raise temperatures in surrounding neighborhoods by as much as 4 degrees Fahrenheit. Phoenix, Arizona, 2026.
Key Figure 4 degrees Fahrenheit -
yahoo.com
Fermi America's Project Matador in the Panhandle is projected at 24 million tons of emissions annually. Texas, statewide, 2026.
Key Figure 24,000,000 tons per year -
Nevada Current
Nevada abated $240 million in sales tax for data centers in 2023 and 2024. Nevada, statewide, 2026.
Key Figure 240,000,000 USD -
KRGV
The project is valued at 4 billion dollars. Cameron County, TX, 2026.
Key Figure 4,000,000,000 dollars -
Planet Detroit
University of Michigan and Los Alamos computing center project costs 1.2 billion dollars. Ypsilanti Township, Washtenaw County, MI, 2026.
Key Figure 1,200,000,000 dollars -
yahoo.com
GW Ranch Energy Center near Fort Stockton is expected to emit 33 million tons of greenhouse gases a year. Texas, statewide, 2026.
Key Figure 33,000,000 tons per year -
KDHL Radio
Minnesota has 81 data centers operating, under construction, or in planning phase. Minnesota, statewide, 2026.
Key Figure 81 count -
ktnv.com
NV Energy 2026 Integrated Resource Plan shows data centers accounted for 5 percent of total power sales in 2025. Nevada, statewide, 2026.
Key Figure 5 percent -
Construction Review
The completed campus is expected to create about 640 full time positions for ongoing operations. Shippingport, Beaver County, PA, 2026.
Key Figure 640 jobs -
yahoo.com
Texas has 22.4 gigawatts of gas power announced. Texas, statewide, 2026.
Key Figure 22.4 GW -
Washington Examiner
Quincy funded a $100 million high school complex without raising taxes on residents due to data center tax base expansion. NY, 2026.
Key Figure 100,000,000 USD -
ktnv.com
NV Energy proposes 180 megawatts of geothermal generation. Nevada, statewide, 2026.
Key Figure 180 MW -
sent-trib.com
Bowling Green area resident utility bill increased from 29 dollars last July to 130 dollars this year. Bowling Green, Ohio, 2026.
Key Figure 29 dollars -
KVAL
Data centers expected to receive about $450 million in Oregon tax breaks this year. Eugene, OR, 2026.
Key Figure 450,000,000 USD -
Muscatine Journal
A Gallup survey conducted in March 2026 found 60 percent of Americans opposed the construction of data centers in their communities, including 63 percent who said they were strongly opposed. United States, national, 2026.
Key Figure 60 percent -
News-Herald
As of 2025, the Ohio Data Center Tax Exemption cost the state 1.6 billion dollars. Ohio, statewide, 2026.
Key Figure 1,600,000,000 dollars -
Bisnow
Kingston Technology Hub requires 150 megawatts of power per day from the Municipal Electric Authority of Georgia. Cartersville, Bartow County, GA, 2026.
Key Figure 150 MW -
dailyreporter.com
Unemployment for all industries remained at 4.1 percent in August. United States, statewide, 2026.
Key Figure 4.1 percent -
Yahoo Finance
Property purchase price is 55 million dollars. Tioga County, PA, 2026.
Key Figure 55,000,000 dollars -
Morning Journal
State revenue loss from Ohio Data Center Tax Exemption estimated at 136 million dollars in 2013. Ohio, statewide, 2026.
Key Figure 136,000,000 dollars -
98.1 - Minnesota's New Country
Minnesota has 81 data centers operating or in the planning phase across the state, according to Data Center Map. Minnesota, statewide, 2026.
Key Figure 81 data centers -
WyomingNews.com
The facility will use between 20 and 30 million gallons of water annually for domestic and safety purposes. Laramie County, WY, 2026.
Key Figure 20,000,000 to 30,000,000 gallons a year -
TradingView
Microsoft plans to expand total compute capacity from approximately 12 gigawatts to more than 38 gigawatts by 2032. NY, 2026.
Key Figure 12 GW -
The Clinton Chronicle
Valara initially approved for 50 megawatts but amended application to 450 megawatts. Spartanburg County, SC, 2026.
Key Figure 50 MW -
Colorado Public Radio
One megawatt can power about 1,000 homes. Colorado Springs, El Paso County, CO, 2026.
Key Figure 1,000 homes -
TradingView
Microsoft spent 145 billion dollars in capital expenditures during its most recent fiscal year. NY, 2026.
Key Figure 145,000,000,000 dollars -
Washington Examiner
Data centers in Quincy, Washington generate 55 to 60 percent of local property tax revenue. Quincy, Grant County, WA, 2026.
Key Figure 55 to 60 percent of property tax revenue -
The Arkansas Democrat-Gazette
The transmission upgrades will cost about $19 million. Pulaski County, AR (near Wrightsville), 2026.
Key Figure 19,000,000 USD -
Radio Iowa
National data centers use 18 billion gallons of water across 4,929 total centers. Hancock County, IA, 2026.
Key Figure 18,000,000,000 gallons -
KRGV
The project sits on more than 1,100 acres. Cameron County, TX, 2026.
Key Figure 1,100 acres -
dailyreporter.com
Nonresidential construction employment overall grew by 10,400 jobs in August. United States, statewide, 2026.
Key Figure 10,400 jobs -
yahoo.com
Oregon currently occupies more than 2,100 acres with data centers and has 9,000 more acres planned. Oregon, statewide, 2026.
Key Figure 2,100 acres -
dailyreporter.com
Nonresidential specialty trade contractors added 8,000 jobs since July 2026. United States, statewide, 2026.
Key Figure 8,000 jobs -
mountain-topmedia.com
American Edge Project estimated data centers will create nearly 5 million temporary construction jobs and nearly 700,000 permanent jobs. Kentucky, statewide, 2026.
Key Figure 5,000,000 jobs -
American Enterprise Institute - AEI
58 percent of PA-7 residents call the 2021 tax exemption a bad deal. Pennsylvania, PA, 2026.
Key Figure 58 percent -
The Arkansas Democrat-Gazette
The data center developer is working with Entergy to supply an initial 150 megawatts of power. Pulaski County, AR (near Wrightsville), 2026.
Key Figure 150 MW -
Muscatine Journal
In Dallas and Polk counties, 5,363 construction workers were added between 2014 and 2022. Salix, Woodbury County, IA, 2026.
Key Figure 5,363 jobs -
98.1 - Minnesota's New Country
Duluth is the next biggest market for data centers in Minnesota with 6 data centers. Minnesota, statewide, 2026.
Key Figure 6 data centers -
ktnv.com
NV Energy proposes 4,370 megawatts of solar photovoltaic generation. Nevada, statewide, 2026.
Key Figure 4,370 MW -
Construction Review
The campus is designed for 2 gigawatt capacity. Shippingport, Beaver County, PA, 2026.
Key Figure 2 GW -
Patriot Publishing LLC
Performance agreement includes 50 million dollar data center investment requirement at the end of the fourth year of operation. Pulaski County, VA, 2026.
Key Figure 50,000,000 dollars -
Bisnow
Kingston Technology Hub expected to employ 50 people full time. Cartersville, Bartow County, GA, 2026.
Key Figure 50 jobs -
The Advocate
To qualify for state tax incentives project must commit to minimum $200 million capital investment. Moss Bluff, Calcasieu Parish, LA, 2026.
Key Figure 200,000,000 USD -
today.uconn.edu
Cornell University study projects data centers will put an additional 24 to 44 million metric tons of carbon dioxide into the atmosphere by 2030. CT, 2026.
Key Figure 24,000,000 to 44,000,000 metric tons of CO2 -
OPB
Amazon Web Services has more than 50 data centers in Morrow County and Umatilla County, with growth largely fueled by Amazon. Morrow County, OR; Umatilla County, OR; Eastern Oregon, statewide, 2026.
Key Figure 50 facilities -
American Enterprise Institute - AEI
49 percent of Pennsylvanians call the 2021 tax exemption for data center equipment a bad thing for the state, versus 17 percent who call it good. Pennsylvania, PA, 2026.
Key Figure 49 percent -
Stocktwits
Ohio data center sales tax exemption topped 1.5 billion dollars in 2025, more than 10 times the state's original estimate. Ohio, statewide, 2026.
Key Figure 1,500,000,000 dollars -
WyomingNews.com
Peak construction workforce is estimated at around 2,500 workers. Laramie County, WY, 2026.
Key Figure 2,500 workers -
WyomingNews.com
The project will have initially 250 operational jobs. Laramie County, WY, 2026.
Key Figure 250 jobs -
malaysia.news.yahoo.com
Data centers in Southern Nevada accounted for about 773 million gallons of water in 2025, which is 0.52 percent of Southern Nevada's total water use. Nevada, statewide, 2026.
Key Figure 773,000,000 gallons -
Concord Monitor
Potential data center in Bow could draw up to 200 megawatts of power. Bow, Merrimack, NH, 2026.
Key Figure 200 MW -
Stocktwits
Amazon has invested nearly 40 billion dollars in Ohio data centers since 2015. Ohio, statewide, 2026.
Key Figure 40,000,000,000 dollars -
The Advocate
To qualify for state tax incentives project must create at least 50 new permanent jobs. Moss Bluff, Calcasieu Parish, LA, 2026.
Key Figure 50 jobs -
Newser
Ohio's data center equipment sales tax exemption costs more than 1.5 billion dollars annually. Ohio, OH, 2026.
Key Figure 1,500,000,000 dollars a year -
News From The States
Nevada abated $90 million in sales tax for data centers in 2021 and 2022. Clark County, NV, 2026.
Key Figure 90,000,000 USD -
Chicago Tribune
27 datacenters built in Illinois since 2020 collectively saved nearly $1 billion in taxes via incentives. Illinois, statewide, 2026.
Key Figure 1,000,000,000 USD -
Bucks County Beacon
Brian Fitzpatrick voted for $20 billion in data center subsidies. Bucks County, PA, 2026.
Key Figure 20,000,000,000 USD -
dailyreporter.com
Construction unemployment rate fell to 3.1 percent in August 2026. United States, statewide, 2026.
Key Figure 3.1 percent -
Muscatine Journal
Google's Council Bluffs data center has reportedly invested more than $5 billion since 2007. Salix, O'Brien County, IA, 2026.
Key Figure 5,000,000,000 USD -
Patriot Publishing LLC
Virginia's First would pay 150,000 dollars in project development fees to the company within 30 days of Phase I completion. Pulaski County, VA, 2026.
Key Figure 150,000 dollars -
Patriot Publishing LLC
Proposed data center property purchase price was 1.6 million dollars or roughly 3,370 dollars per acre. Pulaski County, VA, 2026.
Key Figure 1,600,000 dollars per acre -
WCCS AM1160 & 101.1FM
AWS stated proposed data centers would generate between 1500 and 2000 jobs. Indiana County, PA, 2026.
Key Figure 1,500 to 2,000 jobs -
Google Blackstone's TPU neocloud named Crux AI, hires Meta's data center engineering head Alan Duong
Alan Duong, formerly Meta's VP of data center engineering, joined Crux AI as chief development officer with plans to deliver multiple gigawatts of capacity.
-
Kreiss-Tomkins unveils platform to institute moratorium on data centers and regulate AI - Delta Discovery
Democratic candidate for Alaska governor Jonathan Kreiss Tomkins proposes moratorium on new data centers pending regulation and local approval requirements.
-
Brookwood data center developer donates $25k to Tuberville campaign - WVUA 23
Applied Digital Corporation donated $25,000 to Alabama gubernatorial candidate Tommy Tuberville; Democratic rival Doug Jones criticized Tuberville's financial ties to AI and data center companies.
-
Arkansas lawmaker forms trade association focused on AI, data center policy - KATV
Arkansas lawmaker forms trade association to shape AI and data center policy amid debate over economic benefits versus ratepayer and environmental costs.
-
Entergy re-submits AVAIO power agreement to Arkansas Public Service Commission - arkansasonline.com
Entergy re submitted power agreement to Arkansas PSC for AVAIO's 150 megawatt data center in Pulaski County with service to begin June 2027.
-
A Guide to Better Data Center Policy for Local Governments - Federation of American Scientists
Federation of American Scientists releases guide on data center policy for local governments, analyzing ordinances, property values, and community benefits agreements.
-
Corporation Commission debate came with intense sparring over data centers
Arizona Corporation Commission candidates debate data center impacts, with Democrats proposing a moratorium and Republicans defending current regulation.
-
California's Data Center Challenge: Rebuilding Community Trust - smdp.com
Opinion piece argues California tech industry must rebuild community trust in data centers through transparency, equitable economic benefits and clean energy deployment.
-
California judge halts state's largest data center - Courthouse News
California judge halts Imperial Valley Data Center, California's largest, requiring full environmental review under CEQA before project can proceed.
-
San Francisco, heartland of AI, to weigh moratorium on new data centers - San Francisco Chronicle
San Francisco considers a moratorium on new data center construction.
-
Court overturns approval of Imperial County data center, orders environmental review - KPBS
Imperial County Superior Court judge overturns county approval of data center complex, orders environmental review under California Environmental Quality Act.
-
Weld County commissioners approve permit for Global AI data center - Colorado Newsline
Weld County commissioners voted unanimously to approve a zoning permit for Global AI's 41 acre data center near Windsor, expected to reach 1 gigawatt by 2029.
-
Climate change, not data centers, behind Colorado River drought - malaysia.news.yahoo.com
Water experts debunk social media claims that data centers caused 2026 Colorado River drought, attributing crisis to climate change, low snowpack, and high evaporation.
-
Global AI Wins Colorado Data Center Permit Amid Power, Water Disputes - TheEnergyMag
Weld County commissioners unanimously approved Global AI's 41 acre data center project despite concerns over power, water and noise.
-
If approved, Project Taurus will use substantially more electricity than Colorado Springs' current top power customer - Colorado Public Radio
Colorado Springs Utilities confirms Project Taurus data center would consume 50 MW continuously, making it the city's largest customer by substantial margin.
-
Weld County commissioners approve proposed 41-acre data center - denver7.com
Weld County commissioners voted 5-0 to approve a 41 acre data center project that could become Colorado's largest, despite community concerns about water, noise, and grid strain.
-
How Are Data Centers Impacting Health? - today.uconn.edu
University of Connecticut researcher discusses environmental and health impacts of data center construction including air pollution, water use and noise pollution.
-
U.S. Rep. Kathy Castor Opposes Data Centers in Hillsborough County - U.S. Representative Kathy Castor (.gov)
U.S. Representative Kathy Castor expressed strong opposition to data centers in Hillsborough County, citing impacts on utility bills, water supplies, and costs to residents.
-
Indiantown attorney drafting data center moratorium
Indiantown Village Council voted unanimously to direct legal counsel to draft a data center moratorium and transparency ordinance following a recent leadership change aimed at pausing data center applications.
moratorium legislation zoning -
Byron Donalds says data center dollars don’t influence his policy positions - Florida Politics
Byron Donalds, Republican gubernatorial candidate, says data center industry donations do not influence his policy positions on the facilities.
-
Miami Lakes to consider data center ban - floridapolitics.com
Miami Lakes Town Council considers ordinance to prohibit dedicated AI data centers as principal use within municipality.
-
Google representative speaks at Columbia County Chamber event - AOL.com
Google representative Jen Ryan spoke at Columbia County Chamber event about the coming Google data center, discussing standards for noise, lighting, and water usage.
-
Another large data center proposed in Georgia - The Augusta Press
A large data center is proposed for a small community in northwest Georgia, state under consideration for next major project.
-
Thor Equities Plans $1B Data Center In North Georgia: The Atlanta Deal Sheet - Bisnow
Thor Equities proposes Kingston Technology Hub, a 350,000 square foot data center on 560 acres north of Cartersville, Georgia, estimated to cost $1 billion and open in 2030.
-
No Data Center Concert Rocking Clinton, Iowa This Weekend - quadcities.com
Clinton, Iowa residents organized protest concert against a proposed data center.
-
Salix, IA city leaders discuss data center ordinance, future conversations with Google - Hawaii News Now
Salix, Iowa city council discusses data center ordinance and Google project; votes against moratorium three weeks prior.
-
Iowa data center debate looms in governor race. Where Sand, Lahn stand - The Quad-City Times
Iowa gubernatorial candidates Zach Lahn and Rob Sand take opposing stances on data centers, with Lahn calling for a statewide pause and Sand proposing transparency and union requirements.
-
Iowa data center debate looms in governor race. Where Sand, Lahn stand - Muscatine Journal
Iowa gubernatorial candidates Rob Sand and Zach Lahn outline different approaches to data center regulation, with Sand favoring transparency and job protections while Lahn calls for a statewide construction pause.
-
Salix, IA city leaders discuss data center ordinance, future conversations with Google - KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE
Salix, Iowa city leaders discuss data center ordinance and future conversations with Google.
-
Northern Iowa county panel becomes latest to reject call for data center - Radio Iowa
Hancock County Planning and Zoning Commission unanimously denies zoning change for potential data center development near Garner, Iowa, after three hour hearing with three dozen speakers, majority opposed.
-
Iowa county enacts moratorium on new data center projects - KCCI
Boone County, Iowa adopted a one year moratorium on new data center projects while the board studies and creates a new zoning ordinance.
-
AI Infrastructure on DOE Lands Request for Information - Department of Energy (.gov)
Department of Energy released a Request for Information for AI infrastructure on DOE lands, identifying 16 sites for data center development with target operation by end of 2027.
-
Tell your governor: Data center moratorium now - PIRG
Illinois PIRG advocates for two year moratorium on large data centers, citing concerns about energy demand and water use.
-
Lake County Approves 8-Month Data Center Moratorium - Patch
Lake County, Illinois approves eight month moratorium on data center development in unincorporated areas while studying potential regulations.
-
Editorial: R-E-S-P-E-C-T is the only way for AI advocates to deal with data center haters - Chicago Tribune
Chicago Tribune editorial criticizes tech industry executives for dismissing datacenter opposition as ignorance, noting legitimate concerns about electricity costs, employment, and AI risks.
-
Columbus adds oversight to data center proposals - ipm.org
Columbus, Indiana adds oversight ordinance requiring data center proposals to obtain board of zoning appeals approval.
-
Ford challenges Spartz on data centers after her call for federal review - LarryInFishers
Representative Victoria Spartz requested federal review of Indiana data center projects including LEAP and others for energy and water impacts; rival congressional candidate J.D. Ford called for federal legislation requiring local control and disclosure.
-
Rep. Spartz seeks independent federal review of Indiana data centers & LEAP - The Hamilton County Reporter
Rep. Victoria Spartz requested federal review of LEAP and other Indiana datacenters, raising concerns about energy, grid reliability, transmission costs, water resources and cost allocation.
-
ARNOLT CENTER: Companies Seek to Hide Indiana Data Center Details with NDAs - the indiana citizen
Investigation: companies seek to hide Indiana data center project details using non disclosure agreements; residents express concerns about transparency.
-
Shawnee Co. Commissioner updates budget talks, data center debate - WIBW
Shawnee County, Kansas Commissioner Kevin Cook discussed data center debate and county budget during media appearance; specific actions not detailed in excerpt provided.
-
Judge dismisses City of Edgerton's lawsuit against two residents over data center petition - Johnson County Post
Kansas judge dismisses Edgerton's lawsuit against residents and rules citizen petition seeking ballot vote on data center is protected speech.
-
The Kansas WEALTH Coalition Calls for a Data Center Moratorium Until Significant Guardrails Are Put in Place - sentineltimes.com
Kansas WEALTH Coalition calls for statewide data center moratorium with guardrails protecting water, energy, and labor standards.
-
Energy Secretary Announces New American Energy Hub at Paducah Site - Department of Energy (.gov)
Energy Secretary announces $100 billion Paducah, Kentucky AI data center campus with 1.8 GW capacity, 2 GW natural gas generation, 2.6 GW battery storage, completion by 2031.
-
Sphere 3D (NASDAQ: ANY) Soars as AI Data Center Expansion Accelerates
Sphere 3D advances a proposed 50 MW AI and HPC data center in Hopkinsville, Kentucky with a 65 MW substation as part of a strategic pivot to the TVA region.
-
A Kentucky county becomes first in state to permanently ban data center construction - kentuckylantern.com
Woodford County, Kentucky passed a permanent ban on data center construction, the first county in the state to take such a strict stance.
-
Some Ky Schools and Local Governments Eye a Data Center Tax Windfall. A Think Tank Sees Loopholes. - The Lexington Times
Kentucky think tank raised concerns about loopholes in data center tax incentives available to schools and local governments.
-
Data center planned for north of Lake Charles, developer confirms. Here’s what we know. - The Advocate
Azimuth Renewables president confirms plans for data center at Moss Bluff Louisiana on 1,200 acres, early evaluation stage, details pending.
-
Proposed data center north of Moss Bluff still in exploration stage, company says - KPLC 7 News
Azimuth Renewables is exploring a data center north of Moss Bluff in Calcasieu Parish, but faces zoning barriers and community opposition.
-
Ascension Zoning Commission recommends first data center regulations. See what they are.
Ascension Parish Zoning Commission recommends first data center ordinance; parishes council will vote on adoption.
-
Former EPA officials warn of health risks from data center pollution - Louisiana Illuminator
Former EPA officials warn that data center pollution could cause 600,000 asthma cases and 1,300 premature deaths by 2028.
-
Letters: As data center discussed for Livingston Parish, questions remain - NOLA.com
A Louisiana resident warns that data center power contracts may burden ratepayers if technology becomes obsolete or power costs decline during 15 year utility terms.
-
Massachusetts lets towns veto data centers before the state weighs in - Cryptopolitan
Massachusetts Governor Maura Healey signed an executive order requiring data centers over 25 megawatts to win local approval and meet 100 percent clean energy demands.
-
Massachusetts Mandates Clean Energy for Large Data Centers as Backlash Grows - AI Insider
Massachusetts Governor Maura Healey issued Executive Order 658 requiring large data centers over 25 megawatts to procure clean power or contribute to ratepayer protection fund.
-
Massachusetts Establishes New Framework for Data Center Development | Mintz - ML Strategies - JD Supra
Massachusetts Governor Maura Healey's Executive Order 658 establishes framework for data center development requiring clean energy and community benefits agreements.
-
Massachusetts Tightens Data Center Environmental Permitting - Environment+Energy Leader
Massachusetts Governor signed Executive Order 658 requiring data centers over 25 MW to meet clean energy, water, environmental and community benefit requirements before permitting.
-
Massachusetts Requires Local Approval for Data Centers Under New Executive Order - Boston's ROCK 92.9
Massachusetts Governor Healey signs executive order requiring data centers to secure local approval, fund clean energy, meet environmental standards, and pay ratepayer protection fee.
-
Massachusetts Sets Clean Energy Rules For Data Centers - taiyangnews.info
Massachusetts issues clean energy mandate: data centers above 25 MW must procure new clean power or pay into ratepayer fund; local approval required.
-
Massachusetts tightens the rules on data centers as energy angst grows - Briefs Finance
Massachusetts Governor Healey ordered community benefits agreements for data centers, banned NDAs, and forced developers to fund clean power or contribute to ratepayer protection fund.
-
Data center developers have one more avenue to protect themselves from a Council that wants to protect you- but it's not over yet. #frederickcountymd #frederick #peopleoverprofit #waterislife
Frederick County Council member advocates for protections against data center development, citing water concerns and community interests.
-
UM town hall panel faces angry, jeering crowd over plan for joint computing center with Los Alamos - Michigan Public
University of Michigan held hostile town hall in Ypsilanti Township on proposed advanced research computing center with Los Alamos National Laboratory; residents oppose project.
national -
As voters sour on data centers, governor candidates embrace moratorium - Detroit Free Press
Michigan governor candidates embrace data center moratorium as voters sour on facilities; both major party nominees call for halting new construction pending regulatory protections.
-
Nearly two thirds of Michigan voters are against construction of data centers, poll finds - ClickOnDetroit | WDIV Local 4
Poll shows nearly two thirds of Michigan voters oppose data center construction in the state.
-
Trump EPA Accused of Endangering Public as Study Highlights 'Hidden Health Costs' of Data Centers - commondreams.org
Environmental Protection Network report accuses Trump EPA of actions that could increase pollution and health risks from data centers.
-
University of Michigan's Ypsilanti Township computing center plans meet with anger at town hall: 'Enormous distrust' - Planet Detroit
University of Michigan and Los Alamos $1.2 billion 100 megawatt computing center faces community backlash; township board and utility enact opposition resolutions and moratorium.
-
Ionia has no data center proposal, but leaders are starting the conversation - fox17online.com
Ionia Michigan city leaders and residents discuss data center possibility with MSU professor and utility; no current proposal exists.
-
El-Sayed on U-M data center, university enrollment and affordability - The Eastern Echo
Democratic U.S. Senate candidate Abdul El Sayed outlines five conditions for University of Michigan data center in Ypsilanti: union labor, no rate increases, water protection, revenue investment, and community benefits agreement.
-
University of Michigan holds town hall over proposed data center - cbsnews.com
University of Michigan held town hall on proposed high performance research computing center in Ypsilanti Township.
-
Minnesota Already Has Over 80 Data Centers In These Cities - 98.1 - Minnesota's New Country
Data Center Map reports Minnesota has 81 data centers operating or in planning phase, with majority in Minneapolis market and six in Duluth.
-
Where do Minnesota statewide office candidates stand on data centers? - Alexandria Echo Press
Minnesota statewide office candidates Demuth, Klobuchar, Tafoya, and Flanagan state positions on data center transparency, local authority, environmental regulation, and cost allocation.
-
Minnesota Already Has Over 80 Data Centers In These Cities - KDHL Radio
Minnesota has 81 operating, under construction, or planned data centers with majority in Minneapolis market and six in Duluth.
-
Data center moratoriums create developer, landowner risks - Minnesota Lawyer
Data center moratoriums in Minnesota municipalities create delays and costs for developers and landowners; municipalities generally imposing up to one year initial moratoriums.
-
Inside the state’s miserable task of re-vetting Medicaid providers. Plus: meet the pro-data center group Iron Range DFLers and Republicans support. - MinnPost
Minnesota Iron Range political figures diverge on data center support; Jobs for Minnesotans nonprofit advocates for local data center development.
-
Desloge town hall draws regional opposition to potential data center - Park Hills Daily Journal
Desloge, Missouri held a town hall where several hundred regional residents largely opposed a potential data center and called for a planning moratorium.
-
Property marketed in Oregon County for Data Center - E Communications
Nations Media Partners markets 226 acre property in Oregon County, Missouri for mid scale data center development.
-
Opinion: Data-center rules will test our community health decisions
St. Louis author Angela Mott outlines framework for regulating data centers, emphasizing community health assessment and evidence based governance.
-
Rejected once, tax break plan returns for Ferguson data center and Emerson redevelopment
Ferguson reintroduces legislation for $1.5 billion tax incentives for a data center and Emerson campus redevelopment after a 3-3 council vote rejected it in May.
-
Lawmakers don’t want ratepayers saddled with data center costs - Missoula Current
Montana legislature's Energy and Technology Committee advanced a draft bill to prevent utility ratepayers from funding data center infrastructure costs.
-
Missoula County to prepare data center study after passing one-year moratorium - Nonstop Local News Montana
Missoula County passed one year moratorium on new or expanded data centers and is preparing study on their impacts.
-
Butte commissioners discuss possibility of data center moratorium - montanarightnow.com
Butte Silver Bow commissioners consider six month moratorium on new data center construction, citing need for community input and regulatory clarity.
-
McDowell joins NC data center pause - Carolina Journal
McDowell County, North Carolina approved six month moratorium on data center development, joining at least 30 other NC counties and towns amid concerns over energy, water, and infrastructure costs.
-
North Carolina governments hit pause on data centers as AI backlash grows - Substack
North Carolina local governments are imposing moratoriums or temporary restrictions on data centers amid public concerns about electricity, water, property rights, and tax revenue.
-
Proposed Harwood charter amendment looking to make industrial negotiations more transparent - The Mighty 790 KFGO
Harwood, North Dakota voters will decide in November on a charter amendment to require more transparency in negotiations for large industrial projects, following criticism of the Applied Digital data center approval process.
-
Winnebago Tribe of Nebraska offers information on proposed data center project - AZ Family
The Winnebago Tribe of Nebraska is offering information on a proposed data center project.
-
Keene Committee Advances Data Center Moratorium, Dog Restrictions; Delays Kratom Action - My Keene Now
Keene, New Hampshire planning committee voted to refer data center moratorium proposal to planning board; moratorium would last no more than one year.
-
Rates and Rights: Don’t panic about that data center in Bow
Eversource officials reveal plans for potential 200 megawatt data center in Bow, NH, next to Merrimack Station power plant.
-
States Are Opening the Door to Data Center Investment in Virtual Power Plants - RMI
RMI reports states are opening pathways for data centers to fund distributed capacity through virtual power plants and new compensation mechanisms.
-
Spotswood Sends Data Center Zoning Proposal to Planning Board Amid Council Debate - TAPinto
Spotswood, New Jersey sent data center zoning proposal to planning board after council debate on economic benefits and environmental concerns.
-
Oracle Plans Public Environmental Dashboard for Project Jupiter - eponline.com
Oracle plans a public dashboard on air, noise, heat, light and water use at Project Jupiter in Doña Ana County, New Mexico, with an independent expert assessing that information twice a year.
-
Oracle’s 2-GW Renewable RFP Aims to Offset AI Data Center Emissions in New Mexico - energytech.com
Oracle issues 2 GW renewable energy RFP to support Project Jupiter's 100% carbon free energy goal by 2031 in New Mexico.
-
‘This industry is the future:’ Clark County teachers union wants state to bargain with data centers - News From The States
Clark County teachers union calls for data center tax abatement reforms to fund education.
-
Nevada is reviewing its data center tax breaks , but counties are out of the loop - Northern Nevada Business Weekly
Nevada state government is reviewing its data center tax break program, but counties are not being consulted despite bearing fiscal costs.
-
First of its kind public Nevada data center halted over review concerns - Trending Now Infrastructure
Federal appeals board halted approval of 167 MW data center near Boulder City, Nevada, citing environmental review concerns.
-
Teachers’ union proposes plan to make Nevada data centers pay more for public education - kolotv.com
Clark County Education Association proposes eight point plan to eliminate data center tax breaks and redirect revenues to education, water, power, and environmental controls.
-
Nevada data center debate reaches classroom as teachers union pushes against moratorium - news3lv.com
Nevada lawmakers draft legislation for a potential data center moratorium as teachers union opposes and Senator Neal defends the industry amid AI expansion concerns.
-
TPS concerns, Las Vegas airfare costs and data center tax incentives
Nevada teachers union proposes ending data center tax abatements to fund schools, potentially raising $500 million annually for K-12 education.
-
‘This industry is the future:’ Clark County teachers union wants state to deal with data centers - Nevada Current
Clark County Education Association calls for ending data center tax abatements to fund schools, citing $240 million in abated sales tax in 2023-2024.
-
DATA VS. DESERT PART 4: The massive power demand of Nevada's data center boom - ktnv.com
Data center growth in Nevada comes with large power demand, and critics say the risk to local power bills is not worth it.
-
Nevada’s 'unprecedented' data center boom comes with a massive power bill - ktnv.com
NV Energy 2026 Integrated Resource Plan shows data centers driving unprecedented electricity demand, projected to grow from 5 percent to 64 percent of sales by 2046.
-
Teachers union says Nevada wants data centers to help fund schools - Las Vegas Review-Journal
Nevada teachers union proposes eight point plan requiring data centers to pay Local School Support Tax and address environmental concerns.
-
Microsoft Eyes Massive Data Center Push To Triple Computing Power And Solve Capacity Bottlenecks, Says Report - TradingView
Microsoft plans to expand global data center capacity to 38 gigawatts by 2032, tripling from 12 gigawatts now, with one third AI dedicated.
-
Why the AI hyperscalers are winning the data center debate - Washington Examiner
Analyst argues AI hyperscaler companies are winning the data center debate by emphasizing economic and tax benefits, citing Quincy, Washington as a success case and community benefit agreements as commitments.
-
BG rallies against Husted and his role in bringing data centers to Ohio - sent-trib.com
Ohio Democratic Party rally denounces Lieutenant Governor Jon Husted for promoting data centers; speakers cite environmental and tax concerns.
-
Vivek Ramaswamy could turn Ohio into America’s data center capital, all while holding investments across the industry - TiffinOhio.net
Ohio gubernatorial candidate Vivek Ramaswamy, who holds data center industry investments, previously praised Ohio's data center boom but now proposes conditional approval framework requiring community benefits.
-
Rep. Tristan Rader, Councilman Charles Slife Warn Ohioans of Unrestricted Data Center Growth - Cleveland Scene
Ohio State Rep. Tristan Rader and Cleveland Councilman Charles Slife warn voters about unrestricted data center growth and potential conflicts of interest by gubernatorial candidates.
-
Amazon, Meta and Google Confront Data Center Backlash - TradingView
More than a dozen states are reducing data center tax subsidies as lawmakers question whether job creation and investment justify lost revenue and grid costs.
-
Legislation to ban tax abatements for data centers introduced in Ohio - News-Herald
Ohio state representative introduces bill to ban property tax abatements for data centers and examine termination of existing exemptions.
-
Ohio lawmakers mull pulling data center tax break - nbc4i.com
Ohio lawmakers propose eliminating or limiting data center tax breaks including sales and property tax exemptions in response to public backlash.
-
Legislation to ban tax abatements for data centers introduced in Ohio - Morning Journal
Ohio state rep introduces House Bill 999 to ban property tax exemptions for data centers and examine terminating existing abatements.
-
States Want to Pull Back Data Center Tax Breaks - Newser
Ohio Governor Mike DeWine froze new data center tax exemption applications after costs ballooned to 1.5 billion dollars annually, prompting lawmakers to consider repealing the break.
-
AMZN, META, GOOGL Might Lose Billions As Ohio State Reconsiders Data Center Tax Breaks, Says Report - Stocktwits
Ohio is reconsidering data center tax incentives worth billions as states weigh costs of data center growth and rising power and water demand.
-
Ohio Sen. Bernie Moreno Calls for End to Data Center Tax Subsidies - wowo.com
Ohio Sen. Bernie Moreno proposes federal legislation to eliminate financial benefit of state and local data center tax incentives through a 100% federal tax offset.
-
Tomorrow, September 8, the Grady County Commissioners are holding a special meeting regarding the proposed data center. I have one concern with the way the meeting is currently structured: The commissioners may discuss and possibly take action on the
Citizens call for public comment to precede commission action on Grady County data center proposal at September 8 special meeting.
-
Representing sovereignty, traditions - ocolly.com
Oklahoma State University students protested Google data center project, citing threats to Indigenous sovereignty and communities.
-
Eugene rejects data center at former Hynix site - KVAL
Eugene rejected a data center proposal at the former Hynix site under employment zoning rules; the decision may be appealed to state board.
-
Kotek, Drazan Each Call for Oregon Data Center Moratorium - yahoo.com
Oregon Governor Tina Kotek and Republican challenger Christine Drazan both called for a statewide moratorium on new data center construction, citing impacts on water, energy, and farmland.
-
Oregon Governor Tina Kotek orders statewide pause on new data center construction - AppleValleyNewsNow.com
Oregon Governor Tina Kotek ordered a statewide pause on state agency approvals for new data center projects through July 1, 2027, citing concerns about water, energy, and environmental impacts.
-
Kotek’s push against data centers unlikely to slow expansion in Eastern Oregon, local officials say
Oregon Gov. Kotek announced support for a statewide moratorium on data centers and issued an executive order pausing developments on state owned land.
-
Salem will host three town halls on data center policies
Salem established a Data Center Task Force and scheduled three town halls to develop data center policies for city council approval.
-
Wyoming County Passes Data Center Regulations - The Rocket-Courier
Wyoming County commissioners formally adopted regulations for data centre development in an amendment to the county's subdivision and land development ordinance.
-
Alpha Compute Secures $47 Million in Seller Financing for Planned 200MW Pennsylvania AI Data Center Campus - Yahoo Finance
Alpha Compute secures 47 million dollars in seller financing for planned 200 MW Pennsylvania AI data center campus in Tioga County.
-
Aligned Data Centers and Shippingport Community Mark Revitalization of Legacy Energy Site with Groundbreaking of 2 GW Project Phoenix Campus
Aligned Data Centers holds groundbreaking ceremony for Project Phoenix, a 2 GW data center campus in Shippingport, Pennsylvania, on September 10, 2026, with expected regional economic investment of $10 billion.
-
Polling Pennsylvania: Data Center Discourse - aei.org
Pennsylvania poll shows data center support dropped from 34% to 22% in seven months, opposition surged from 42% to 57%, with Democrats opposing more than Republicans.
-
Potential data center development the topic of community event in Shippingport - WPXI
Aligned Data Centers held a community meeting about plans to build a nearly 2 million square foot data center campus on the former Bruce Mansfield Power Plant site in Shippingport, Pennsylvania.
-
A massive data center breaks ground near former coal plant campus in Beaver County - Pittsburgh Post-Gazette
Texas developer breaks ground on Project Phoenix, a 2 gigawatt data center near a defunct coal plant in Beaver County.
-
PUC to examine grid reliability, customer costs related to data center growth - wfmz.com
Pennsylvania PUC ordered staff to develop grid reliability regulations and scheduled technical conference on cost allocation as data center load grows.
-
Alpha Compute Corp. Announces $47 Million Seller Financing Amendment for Pennsylvania Data Center Campus Project - quiverquant.com
Alpha Compute amended financing for a 200 MW natural gas data center campus in Pennsylvania, reducing cash at closing to $8 million with $47 million seller financing.
-
Pennsylvania Democrat’s new data center ad - Punchbowl News
Democrat Bob Harvie airs first general election TV ad calling for data center moratorium against Rep. Brian Fitzpatrick in Pennsylvania.
-
PUC Moves To Address A.I. Data Center Impacts On Emergency Load Control Procedures, Allocation Of Costs Associated With Large Loads; Technical Conference On Cost Responsibility To Be Held - PA Environment Digest Blog
Pennsylvania Public Utility Commission votes 5-0 to update emergency load control procedures and examine cost allocation for data centers.
-
Crucial House Race Becomes Data Center Battle - HuffPost
Pennsylvania Democratic candidate Bob Harvie calls for data center moratorium in congressional race, reversing prior support.
-
2 GW Project Phoenix Data Center Campus Breaks Ground in Pennsylvania - Construction Review
Aligned Data Centers broke ground on Project Phoenix, a 2 GW three facility data center campus in Shippingport, Pennsylvania, with $10 billion regional investment and 3,000 construction jobs.
-
Democrat Bob Harvie’s First Campaign TV Ad Calls for Data Center Moratorium, Criticizes Congressman Brian Fitzpatrick for Being in Big Tech's Pocket - Bucks County Beacon
Democratic candidate Bob Harvie calls for data center moratorium and criticizes Congressman Fitzpatrick over data center subsidies.
-
Federal Government Moves to Limit Public Input on Data Center Projects - capitalbnews.org
Federal EPA proposes to eliminate public comment requirement for air pollution permits for data centers and power plants.
-
DATA 2: Spartanburg data center not subject to public power plant rules, SC regulators rule - The Clinton Chronicle
South Carolina Public Service Commission ruled data center generating its own power not subject to utility regulation; environmental groups contest decision.
-
Spartanburg County Council, speakers clash at data center meeting - FOX Carolina News
Spartanburg County Council held special meeting on data center moratorium vote; final vote on one year moratorium expected September 21.
-
Residents storm out during data center debate in Spartanburg County - FOX Carolina News
Residents walked out of a debate over a data center in Spartanburg County, South Carolina.
-
Bilateral Energy answers handful of Project Patriot questions
Bilateral Energy, developer of Project Patriot data center in Granbury, disclosed power, water and noise details after months of limited public information.
-
Company launches data center’s $4B first phase near Harlingen - MyRGV.com
Fluidstack launches $4 billion first phase of 1,100 acre hyperscale data center east of Harlingen, Texas, creating hundreds of permanent and 2,500 construction jobs.
-
Boling residents meet Amazon leaders over massive data center project - click2houston.com
Amazon held a community meeting with Boling residents to address questions and concerns about a massive data center project in Wharton County, Texas.
-
Data centers are driving some conservative Texas voters away from the GOP - Houston Public Media
Conservative Texas voters in Hood County oppose data center expansion and are shifting political allegiance away from Republican candidates who support development.
-
Behind the meter: Private power fuels AI data center growth - Fierce Network
Industry analysts and power suppliers report behind the meter power solutions are expanding for data centers as grid wait times stretch to years nationwide.
-
Texas chose a ‘soft approach’ with data center survey. It was so soft it flopped. - San Antonio Current
Texas data centers largely ignored mandatory water survey from state regulators; Governor Abbott criticized lack of transparency as compliance fell short.
-
Texas needs greater transparency on data centers’ water and air impacts
The Environmental Defense Fund called on Texas regulators to require greater public disclosure of water consumption and air emissions from data center facilities.
-
Data Center Water Use in Texas Impossible to Quantify,Lawmakers Aren't Always Sure How to Reach The Operators - deceleration.news
Texas regulators report low survey response from data centers on water usage; 81 facilities reported 1.3 billion gallons total water intake.
-
Texas Republicans Rolled Out the Welcome Mat for Data Centers. Their Voters Are Tearing It Up. - Gadget Review
Rural Texas voters oppose data centers over noise pollution and property value losses, reshaping the 2026 gubernatorial race.
-
NUAI Stock Stumbles As Texas Data Center Claims Face Probe - timothysykes.com
New Era Energy & Digital Inc. faces regulatory investigation into alleged overstated permitting progress on its flagship Texas data center project.
-
Data centers are driving some conservative Texas voters away from the GOP - KERA News
Conservative Texas voters in Hood County say data center opposition is pushing them toward Democrats or away from voting as Governor Abbott faces criticism over data center incentives.
-
Key facts: AMZN 10 yr Qualcomm deal; $1.6B Texas plant; bonds premium - TradingView
Amazon expands Texas data center hardware plant to $1.6 billion with Wiwynn, creating 1,000 advanced manufacturing jobs by 2027 toward 4,000 total.
-
Google Invests $15 Billion on Data Center Buildout in ‘Texas of Europe’ - The Daily Upside
Google announces $15 billion AI data center investment in Finland over two years, including three new facilities powered partly by nuclear electricity.
-
Texas' 12 largest planned gas projects all aim to power data centers as buildout jumps 50% - yahoo.com
Texas plans 12 new gas plants to power data centers as proposed gas generation grows 50 percent, raising concerns about emissions and energy supply constraints.
-
Tarrant County Commissioner Holds Town Hall on Data Center Concerns - thetexan.news
Tarrant County Commissioner Matt Krause holds town hall on data center concerns, hearing resident complaints about a Westlake project and plans to raise issue with state legislators.
-
Fluidstack breaks ground on $4 billion data center project in Cameron County - KRGV
Fluidstack broke ground near Rio Hondo in Cameron County, Texas, on a data center campus valued at 4 billion dollars and expected to create more than 2,500 construction jobs.
-
Fluidstack Begins $4 Billion AI Data Center Project in Cameron County - Texas Border Business
Fluidstack begins $4 billion AI data center campus in Cameron County, Texas near Rio Hondo; first phase expected to create 2,500 construction jobs.
-
Tarrant commissioner: Data center debate ‘transcends partisan sides’
Tarrant County Commissioner Matt Krause calls for regulatory guardrails on data centers after hosting a town hall, suggesting state and local regulatory frameworks.
-
ABC4 Utah. . Data center backlash in Mona, Lori Meers has been sentenced and more.
ABC4 Utah reports on data center opposition in Mona, Utah.
-
Can you make water from natural gas? We’re about to find out - Deseret News
Creekstone Energy announced patent pending Gigawater technology to convert natural gas to water at Delta Gigasite data center in Millard County, Utah.
-
Representative Suhas Subramanyam introduces H.R. 10322: Data Center Fair Share Act - Quiver Quantitative
Representative Suhas Subramanyam introduced H.R. 10322, the Data Center Fair Share Act, to require utilities to assign full infrastructure costs to large load customers of 100 megawatts or more, with states having two years to comply or risk losing federal highway funds.
-
VA Rep. Suhas Subramanyam Unveils National Data Center Legislation - Patch
U.S. Rep. Suhas Subramanyam proposed four federal bills to regulate data center siting, energy standards, and infrastructure impacts nationally.
-
What to know about Amazon's data center proposal - Loudoun Times-Mirror
Amazon submits site plan for four data center buildings on purchased George Washington University campus in Loudoun County; complex zoning and regulatory process begins.
-
Vantage turns to institutional investors for data center financing as lenders face opposition - report - TradingView
Vantage Data Centers seeks up to 2 billion dollars from institutional investors for data center build outs as lenders face political and community opposition.
-
Citizens Continue to Oppose Data Centers - Patriot Publishing LLC
Pulaski County, Virginia citizens and officials debate proposed data center; survey shows 95 percent opposition to development in county.
-
Virginia needs a data center moratorium now | Guest column - Richmond Times-Dispatch
Virginia guest column calls for statewide moratorium on data center contracts until grid reliability, energy, water, and air quality impacts are addressed.
-
Virginia’s data center backlash spills into midterms and more state headlines - cbs19news.com
Virginia data center opposition is becoming a political issue in midterm elections, with community backlash spilling into 2027 state races.
-
Virginia is doing data centers backwards | Guest column - Richmond Times-Dispatch
Virginia opinion piece argues counties should establish data center standards and community benefit terms before accepting developer proposals, citing Hanover rejection and Lancaster approval.
-
Subramanyam introduces package of bills related to data centers - NBC4 Washington
U.S. Rep. Suhas Subramanyam introduces package of bills to regulate data center energy and water use; his Virginia district has over 300 data centers with 200 more planned.
-
Rep. Subramanyam announces national data center plan - Rappahannock News
U.S. Rep. Suhas Subramanyam unveiled four bills to reform data center siting and require data centers to pay for grid upgrades and infrastructure.
-
What Quincy, Washington Can Teach America About Building AI Infrastructure Communities Actually Want - linkedin.com
Quincy Washington data centers achieved 72 percent lower property taxes, 6 billion plus new tax base, and water system savings of 138 million gallons yearly.
-
Port Washington residents look for answers from Vantage, Oracle and OpenAI on massive data center project - TMJ4 News
Oracle, OpenAI and Vantage held public forum in Port Washington, Wisconsin on data center project; 1000 jobs promised by 2028 opening.
-
Guest opinion: What Wisconsin’s Democratic primary reveals about data center politics - Wisconsin Watch
Wisconsin Democratic primary revealed data center politics more nuanced than moratorium debate; Black voters showed more favorable view than other groups surveyed.
-
Construction employment grows modestly with data center activity - dailyreporter.com
Construction employment grew 22,000 jobs in August with specialty trade contractors up 8,000 due to data center megaproject activity.
-
Alliant executive speaks on data centers at Uptown Social - The Sheboygan Press
Becky Valcq, President of Alliant Energy's Wisconsin electric company, spoke at an educational session about data centers in Sheboygan.
-
Homeowner’s yard floods again near Nscale data center site - WSAZ
A homeowner near NScale's Monarch Compute Campus data center in Mason County, West Virginia reports the second flooding of their property from site runoff since construction began.
-
Stakeholders statewide unite to form WV Data Center Accountability Project - The Real WV
West Virginia stakeholders form Data Center Accountability Project opposing unchecked buildout, demanding local control, environmental protection, and community consent.
-
Communities from Putnam to Tucker unite over data center concerns - WCHS
Multiple West Virginia communities formed Data Center Accountability Project to demand holistic assessment and local control over data center projects.
-
Natural gas leads race to fuel Wyoming’s spiking data center driven electrical demand - Powell Tribune
Wyoming state officials report natural gas power projects are rising to meet data center electricity demand, with seven projects in planning totaling 8,700 MW.
-
America's reddest state chases billion dollar boom as others sour on massive emerging industry - Fox News
Wyoming positions itself as alternative to other states imposing restrictions on data centers, citing advantages in land, energy and favorable regulatory environment for AI infrastructure.
-
Natrona County residents split on a potential multi-million-dollar A.I. data center - Wyoming Public Media
Natrona County commissioners heard residents debate Prometheus Hyperscale's $500 million, 940 acre AI data center on Falls Ranch between Casper and Glenrock.
-
A new study shows public opposition to data centers could change if people felt they were benefitting, too
Yale researchers find public opposition to data centers could shift if developers offset community electricity costs through incentives.
-
Google Salix Data Center
Death threats sidelined a planned city council meeting in Salix where local leaders were set to discuss a proposed Google data center. The record reads reported, reported September 10, 2026.
-
Google Salix Data Center
Local leaders in Norwalk approved a development agreement for a $12 billion data center project. The record reads reported, reported September 10, 2026.
-
ValorC3 Boise Data Center
ValorC3 Boise data center built in 2020 using hybrid cooling. The record reads reported, reported September 10, 2026.
-
Meta Louisiana data center
Work continues on the Meta Richland Parish Data Center near Rayville as of August 3, 2026. The record reads running, reported September 10, 2026.
-
Meta plus Moss Bluff
Azimuth Renewables signed option to purchase about 1,200 acres in Moss Bluff in April 2026. The record reads reported, reported September 10, 2026.
-
Meta plus Moss Bluff
Azimuth Renewables has three years to purchase property with optional one year extension. The record reads reported, reported September 10, 2026.
-
Meta plus Moss Bluff
Data center would occupy fraction of 1,168 acres in wooded rural portion of Moss Bluff. The record reads reported, reported September 10, 2026.
-
Ypsilanti Township / University of Michigan & Los Alamos Data Center
University of Michigan initially proposed 20 acre project before purchasing 124 additional acres. The record reads reported, reported September 10, 2026.
-
U-M / Los Alamos Data Center (Van Buren Township)
The facility is proposed to be built on a 144 acre site. The record reads reported, reported September 10, 2026.
-
U-M / Los Alamos Data Center (Van Buren Township)
The facility is proposed to be built along the Huron River. The record reads reported, reported September 10, 2026.
-
U-M / Los Alamos Data Center (Van Buren Township)
A next town hall is scheduled for October 1. The record reads reported, reported September 10, 2026.
-
Applied Digital Polaris Forge 2 (Harwood)
Harwood city council approved the Applied Digital data center and signed a three billion dollar deal within 21 days of initial announcement. The record reads reported, reported September 10, 2026.
-
Bow Data Center
Eversource has been in communication with a developer interested in building a data center in Bow. The record reads reported, reported September 10, 2026.
-
Bow Data Center
Data center would be located next to Merrimack Station power plant. The record reads reported, reported September 10, 2026.
-
Amazon Eastern Oregon Data Centers
Amazon data center project is proceeding in the Boardman area with Oregon Department of Environmental Quality opening public comment period for air quality permit. The record reads reported, reported September 10, 2026.
-
NorthMark Spartanburg County Data Center
Valara project became public in March 2025 when Spartanburg County began negotiating tax incentives for project creating 27 jobs. The record reads reported, reported September 10, 2026.
-
NorthMark Spartanburg County Data Center
NorthMark Strategies converting Kohler kitchen and bath manufacturing plant into $2.8 billion computing center on 300 acres. The record reads reported, reported September 10, 2026.
-
Prometheus Hyperscale Natrona County Data Center
Commissioners said a formal vote on the Prometheus project remains months away. The record reads waiting on permits, reported September 10, 2026.
-
Prometheus Hyperscale Natrona County Data Center
Prometheus Hyperscale is proposing a $500 million AI data center on 940 acres south of I-25 on Falls Ranch property between Casper and Glenrock. The record reads waiting on permits, reported September 10, 2026.
-
Fremont County Data Center