Project Executive
Adam Kramer stated the project would generate $44 million a year of tax revenue from energy use going directly into infrastructure projects to support rural Martin County and Indiantown.
A data center debate in Indiantown, Florida resulted in the termination of the village manager, reflecting serious local conflict over the project. It is reported, as reported August 27, 2026.
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
Each figure as its source gave it. The number in brackets is its place in the source list.
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Not disclosed | |||
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | Not disclosed | |||
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
The record adds each the day a source gives it. Why these documents.
Acts of Martin County and Indiantown about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Martin County | Martin County Commission is expected to vote on a one year data center moratorium; first vote scheduled for October 13, 2026 and second vote for October 27, 2026. | yahoo.com | |
| Martin County | Limited industrial zoning allows construction of data centers; the rezoning was approved 3-2 with commissioners Edward Ciampi, Stacey Hetherington and Eileen Vargas voting for and Blake Capps and Commission Chair Sarah Heard voting against. | yahoo.com | |
| Martin County | Martin County Commission rezoned 108 acres in Hobe Sound from manufacturing and storage to limited industrial zoning on September 15, 2026. | yahoo.com | |
| Martin County | Martin County Commission agreed to move forward on one year moratorium on data centers | tcpalm.com | |
| Martin County | Any proposed moratorium ordinance would require two public hearings before implementation. | cbs12.com | |
| Martin County | County staff and attorney are expected to return with information about county authority to impose a moratorium, including potential legal questions involving state laws SB 180 and SB 484. | cbs12.com |
| Date | Who | Decision | Source |
|---|---|---|---|
| Martin County | Martin County commissioners voted to have staff return with a proposal for a possible one year moratorium on large scale hyperscale data center development. | cbs12.com |
· Status: rumored (source date; the content gives no date of its own)
Village Attorney Wade Vose submitted resignation shortly after election results published [1]
The full Indiantown Data Center timeline, in order
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
Every correction on the record is on the corrections page.
Project executive Adam Kramer stated the facility would not rely on Indiantown's water supply.
Every statement about data centers in Florida, by speaker
Project Executive
Adam Kramer stated the project would generate $44 million a year of tax revenue from energy use going directly into infrastructure projects to support rural Martin County and Indiantown.
Where in Martin County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.
Tap a pin for the data center, the parcel for its record
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is reported, as reported August 27, 2026. The newest entry, reported August 27, 2026: Village Attorney Wade Vose submitted resignation shortly after election results published [1].
Martin County: Martin County Commission is expected to vote on a one year data center moratorium; first vote scheduled for October 13, 2026 and second vote for October 27, 2026. (reported September 16, 2026, source); and Martin County: Limited industrial zoning allows construction of data centers; the rezoning was approved 3-2 with commissioners Edward Ciampi, Stacey Hetherington and Eileen Vargas voting for and Blake Capps and Commission Chair Sarah Heard voting against. (reported September 16, 2026, source). 7 events are on the county's rows; a rule about the area is not a decision about this record.
2 sources on file.
Data Center Record, "Indiantown Data Center", https://datacenterrecord.org/projects/indiantown-data-center-fl, last verified September 17, 2026.
Data Center Record, "Indiantown Data Center", https://datacenterrecord.org/projects/indiantown-data-center-fl. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.