Florida has 16 data center sites, 0 buildings where disclosed on the record: 11 running and 5 proposed. The counties with the most are Miami-Dade County (5) and Duval County (2), and records are in 8 of 67 counties. The largest proposal is Treasure Coast Surf Park Data Center in St. Lucie County, 174 acres (third party estimate); it is reported, as reported August 28, 2026.

Florida decides case by case. From the state's own rule: Senate Bill 484 passed the Florida legislature and requires that minimum tariff and service requirements must reasonably ensure that each large load customer bears its own cost of service and that those costs are not shifted to the general body of ratepayers, August 28, 2026.

2 sites the EPA's registry shows and no record has verified are on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
AI Data Center near Mar-a-Lago Palm Beach CountyProposed
St. Lucie County Data Center (I-95) St. Lucie CountyProposed
Eatonville AI Data Center Eatonville, Orange CountyProposedHostDime data center originally slated for completion in 2020 but repeatedly delayed wftv.com (opens in a new tab) local outlet reported September 1, 2026
Treasure Coast Surf Park Data Center Fort Pierce, St. Lucie CountyProposedWillow Lakes LLCFlorida surf park plan scrapped tcpalm.com (opens in a new tab) local outlet reported August 28, 2026
Indiantown Data Center Indiantown, Martin CountyProposedVillage Attorney Wade Vose submitted resignation shortly after election results published tcpalm.com (opens in a new tab) local outlet reported August 27, 2026
QTS Miami Miami, Miami-Dade CountyRunningQTS Data Centers
Centersquare Tampa data center Tampa, Hillsborough CountyRunningCentersquare
Cologix Jacksonville Jacksonville, Duval CountyRunningCologix
Cologix LAK1 Lakeland, Polk CountyRunningCologix
DataBank Miami data center Miami, Miami-Dade CountyRunningDataBank
Digital Realty Miami Miami, Miami-Dade CountyRunningDigital Realty
Equinix MI3 Boca Raton, Palm Beach CountyRunningEquinix
Equinix MI6 Doral, Miami-Dade CountyRunningEquinix
Equinix Miami Miami, Miami-Dade CountyRunningEquinix
H5 Tampa Tampa, Hillsborough CountyRunningH5 Data Centers
TierPoint Jacksonville Data Center Jacksonville, Duval CountyRunningTierPoint

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 16 Florida projects.

Every Florida record 16 records, and 2 sites not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Ybor Data CenterTampa, HillsboroughNot yet verifiedEPA registry22026-10-20
QTS MiamiMiami, Miami-DadeRunningQTS Data Centerssite22026-10-04
Edgeconnex Tallahassee Holdings LLCTallahassee, LeonNot yet verifiedEdgeConneXEPA registry22026-10-03
AI Data Center near Mar-a-LagoPalm BeachProposedcentroid32026-09-17
Centersquare Tampa data centerTampa, HillsboroughRunningCentersquarecentroid22026-09-17
Cologix JacksonvilleJacksonville, DuvalRunningCologixcentroid22026-09-17
Cologix LAK1Lakeland, PolkRunningCologixcentroid22026-09-17
DataBank Miami data centerMiami, Miami-DadeRunningDataBankcentroid22026-09-17
Digital Realty MiamiMiami, Miami-DadeRunningDigital Realtycentroid22026-09-17
Equinix MI3Boca Raton, Palm BeachRunningEquinixcentroid22026-09-17
Equinix MI6Doral, Miami-DadeRunningEquinixcentroid22026-09-17
Equinix MiamiMiami, Miami-DadeRunningEquinixcentroid12026-09-17
H5 TampaTampa, HillsboroughRunningH5 Data Centerscentroid22026-09-17
St. Lucie County Data Center (I-95)St. LucieProposedcentroid42026-09-17
TierPoint Jacksonville Data CenterJacksonville, DuvalRunningTierPointcentroid22026-09-17
Eatonville AI Data CenterEatonville, OrangeProposedcentroid42026-09-17
Treasure Coast Surf Park Data CenterFort Pierce, St. LucieProposedWillow Lakes LLCcentroid42026-10-07
Indiantown Data CenterIndiantown, MartinProposedcentroid42026-09-17

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every Florida county (67)

8 of 67 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRulesHow it treats data centers
Miami-Dade County1208652
Duval County1203120
Hillsborough County1205720
Palm Beach County1209921restrictive
St. Lucie County1211121
Martin County1208511restrictive
Orange County1209511
Polk County1210512
DeSoto County1202701
Lake County1206901restrictive
Manatee County1208102
Marion County1208301
Okaloosa County1209102
Pinellas County1210301
Sarasota County1211501
Volusia County1212701

A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.

51 counties with no records yet
  • Alachua County
  • Baker County
  • Bay County
  • Bradford County
  • Brevard County
  • Broward County
  • Calhoun County
  • Charlotte County
  • Citrus County
  • Clay County
  • Collier County
  • Columbia County
  • Dixie County
  • Escambia County
  • Flagler County
  • Franklin County
  • Gadsden County
  • Gilchrist County
  • Glades County
  • Gulf County
  • Hamilton County
  • Hardee County
  • Hendry County
  • Hernando County
  • Highlands County
  • Holmes County
  • Indian River County
  • Jackson County
  • Jefferson County
  • Lafayette County
  • Lee County
  • Leon County
  • Levy County
  • Liberty County
  • Madison County
  • Monroe County
  • Nassau County
  • Okeechobee County
  • Osceola County
  • Pasco County
  • Putnam County
  • Santa Rosa County
  • Seminole County
  • St. Johns County
  • Sumter County
  • Suwannee County
  • Taylor County
  • Union County
  • Wakulla County
  • Walton County
  • Washington County

The rules in Florida 23 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
Floridastatecase by caseSenate Bill 484 passed the Florida legislature and requires that minimum tariff and service requirements must reasonably ensure that each large load customer bears its own cost of service and that those costs are not shifted to the general body of ratepayers. thecentersquare.com (opens in a new tab) national outlet Aug 28, 202623 acts on this row
Every act on the Florida row
  1. statement

    Florida Power & Light announced it would not propose new data center rate requirements and said its preexisting rules comply with a new state law requiring residents be protected from increases to electric bills from data centers.

    tampabay.com (opens in a new tab) local outlet

  2. rate rule

    Duke Energy submitted tariff to Florida Public Service Commission as first utility in Florida to present plan

    baynews9.com (opens in a new tab) local outlet

  3. rate rule

    Tampa Electric files tariff with Florida Public Service Commission requiring large load customers such as data centers to pay for electric infrastructure they need

    baynews9.com (opens in a new tab) local outlet

    Also reported by 1 source
  4. ordinance

    Manatee County Planning Commission directed staff to draft the ordinance following passage of Senate Bill 484, which took effect July 1 and established local government authority to set strict standards and deny data center projects.

    yourobserver.com (opens in a new tab) local outlet

  5. event

    Bryan Avila, former Florida state senator and Donalds' running mate, drafted data center legislation including SB 1118 public records exemption bill that failed Senate floor

    suaragarut.id (opens in a new tab) international outlet

  6. event

    Gov. Ron DeSantis signed SB 484 into law handing data center regulation authority to local governments

    wusf.org (opens in a new tab) local outlet

  7. event

    Duke Energy sought permission from Florida regulators to increase rates to cover costs from data centers

    floridapolitics.com (opens in a new tab) local outlet

  8. moratorium

    North Port enacted 18 month moratorium on large scale data centers

    palmbeachpost.com (opens in a new tab) local outlet

  9. moratorium

    Sarasota County commissioners unanimously directed staff to implement one year moratorium on new applications for large scale data centers

    palmbeachpost.com (opens in a new tab) local outlet

  10. event

    Duke Energy requested confidential treatment of cost figures for data centers in Florida

    tampabay.com (opens in a new tab) local outlet

  11. rate rule

    Florida Public Service Commission heard arguments over Duke Energy Florida's proposed tariff for exceptionally large customers, including data centers

    thecooldown.com (opens in a new tab) national outlet

  12. event

    Florida Governor Ron DeSantis signed legislation enforcing rights of local communities to reject data center proposals

    news.bgov.com (opens in a new tab) news outlet

  13. rate rule

    Senate Bill 484 passed the Florida legislature and requires that minimum tariff and service requirements must reasonably ensure that each large load customer bears its own cost of service and that those costs are not shifted to the general body of ratepayers.

    thecentersquare.com (opens in a new tab) national outlet

  14. hearing

    Florida Public Service Commission held a hearing on Duke Energy Florida's compliance with SB 484 data center law.

    utilitydive.com (opens in a new tab) trade press

    Also reported by 1 source
  15. rate rule

    Florida Public Service Commission heard testimony on Duke Energy proposal under Senate Bill 484 to protect ratepayers from data center costs

    floridatrib.org (opens in a new tab) local outlet

  16. filing

    Duke Energy filed paperwork with Florida Public Service Commission to exclude consumer group Florida Rising from data center hearings

    tampabay.com (opens in a new tab) local outlet

  17. event

    City staff reviewed similar ordinances adopted by other Florida Panhandle communities that exclude or restrict data centers.

    yahoo.com (opens in a new tab) national outlet

  18. moratorium

    Hillsborough County Commissioners voted unanimously last month to draft moratorium on data centers and develop land use rules prohibiting facilities from using drinking water for cooling.

    floridapolitics.com (opens in a new tab) local outlet

  19. event

    Gov. Ron DeSantis signed SB 484 on May 8, adding water use permitting requirements for large scale data centers

    tbbwmag.com (opens in a new tab) news outlet

  20. rate rule

    Gov. Ron DeSantis signed data centers law in May 2026 aimed at protecting consumers from costs of large load facilities

    baynews9.com (opens in a new tab) local outlet

  21. event

    Governor Ron DeSantis signed law in May codifying local governments' power to regulate data center developments through comprehensive plans.

    floridapolitics.com (opens in a new tab) local outlet

  22. rate rule

    Governor Ron DeSantis signed SB 484 in May, establishing requirements for large data centers including electricity rate structures, local planning authority preservation, and water permitting requirements.

    wtxl.com (opens in a new tab) local outlet

  23. event

    Governor Ron DeSantis signed SB 484 in May 2026, requiring data centers to cover their own utility and infrastructure costs.

    floridapolitics.com (opens in a new tab) local outlet

Last verified October 1, 2026.

232026-10-01
North Portcitynot ratedNorth Port City Commission approved an 18 month moratorium on data centers. yoursun.com (opens in a new tab) news outlet Sep 233 acts on this row
Every act on the North Port row
  1. moratorium adopted

    North Port City Commission approved an 18 month moratorium on data centers

    yoursun.com (opens in a new tab) news outlet

  2. hearing

    North Port held a workshop on a proposed data center

    mysuncoast.com (opens in a new tab) local outlet

  3. moratorium

    North Port city council advanced a pause on data center projects

    winknews.com (opens in a new tab) local outlet

Last verified September 23, 2026.

32026-09-23
Indiantowncitynot ratedJanet Hernandez and Anthony Dowling returned to council defeating incumbents. tcpalm.com (opens in a new tab) local outlet Reported Aug 275 acts on this row
Every act on the Indiantown row
  1. event

    Janet Hernandez and Anthony Dowling returned to council defeating incumbents

    tcpalm.com (opens in a new tab) local outlet

  2. event

    Christa Miley defeated former Mayor Carmine Dipaolo August eighteen

    tcpalm.com (opens in a new tab) local outlet

  3. event

    Three anti data center candidates elected August eighteen defeating incumbents

    tcpalm.com (opens in a new tab) local outlet

  4. moratorium

    Council agreed to possibly enact one year moratorium on data centers

    tcpalm.com (opens in a new tab) local outlet

  5. event

    Village Council approved Tesoro Groves on April 30, 2026

    tcpalm.com (opens in a new tab) local outlet

Last verified September 2, 2026.

52026-09-02
Eatonvillecitynot ratedEatonville town council rejected proposal to increase HostDime fines to 500 dollars per day. wftv.com (opens in a new tab) local outlet Reported Sep 12 acts on this row
Every act on the Eatonville row
  1. event

    Eatonville town council rejected proposal to increase HostDime fines to 500 dollars per day

    wftv.com (opens in a new tab) local outlet

  2. event

    Town fined HostDime 250 dollars per day after missed June 2025 deadline

    wftv.com (opens in a new tab) local outlet

Last verified September 1, 2026.

22026-09-01
Alachuacitynot ratedAlachua City Commission cancelled a second meeting on data centers due to three members being absent, including Mayor Walter Welch. alligator.org (opens in a new tab) news outlet Sep 301 act on this row
Every act on the Alachua row
  1. hearing

    Alachua City Commission cancelled a second meeting on data centers due to three members being absent, including Mayor Walter Welch.

    alligator.org (opens in a new tab) news outlet

Last verified September 30, 2026.

12026-09-30
Crestviewcitynot ratedCrestview city council passed a 4-0 motion instructing the city manager to draft a data center ordinance prohibiting new data center development within city limits. yahoo.com (opens in a new tab) national outlet Reported Aug 171 act on this row
Every act on the Crestview row
  1. moratorium

    Crestview city council passed a 4-0 motion instructing the city manager to draft a data center ordinance prohibiting new data center development within city limits.

    yahoo.com (opens in a new tab) national outlet

Last verified August 17, 2026.

12026-08-17
DeSoto Countycountynot ratedDeSoto County commissioners proposed one year data center moratorium. winknews.com (opens in a new tab) local outlet Reported Aug 212 acts on this row
Every act on the DeSoto County row
  1. moratorium

    DeSoto County commissioners proposed one year data center moratorium

    winknews.com (opens in a new tab) local outlet

  2. moratorium adopted

    DeSoto County approved 35000 square foot data center in March 2026, then received two much larger proposals, then imposed one year moratorium four months later

    wtxl.com (opens in a new tab) local outlet

Last verified August 21, 2026.

22026-08-21
Fort Meadecitycase by caseFort Meade data center project was approved by city commission in April. tampabay28.com (opens in a new tab) news outlet Sep 22, 20261 act on this row
Every act on the Fort Meade row
  1. approval

    Fort Meade data center project was approved by city commission in April

    tampabay28.com (opens in a new tab) news outlet

Last verified September 22, 2026.

12026-09-22
Fort Piercecitynot ratedOrganized opposition to the data center included dozens of protesters at the Planning Board meeting and a picket line formed before the meeting. tcpalm.com (opens in a new tab) local outlet Reported Sep 173 acts on this row
Every act on the Fort Pierce row
  1. event

    Organized opposition to the data center included dozens of protesters at the Planning Board meeting and a picket line formed before the meeting.

    tcpalm.com (opens in a new tab) local outlet

  2. event

    Developers tabled their rezoning application for Project Neptune on September 17 during a Planning Board meeting.

    tcpalm.com (opens in a new tab) local outlet

  3. event

    Fort Pierce planning board requested further research on proposed rezoning of 200 acres near I-95 and Midway Road for data center and commercial development on September 17, 2026

    wpbf.com (opens in a new tab) local outlet

Last verified September 18, 2026.

32026-09-18
Lake CountycountyrestrictiveLake County in Central Florida has paused or outright banned permits for new data centers. orlandosentinel.com (opens in a new tab) local outlet Sep 11, 20261 act on this row
Every act on the Lake County row
  1. moratorium

    Lake County in Central Florida has paused or outright banned permits for new data centers

    orlandosentinel.com (opens in a new tab) local outlet

Last verified September 11, 2026.

12026-09-11
Lakelandcitynot ratedCity commissioners voted 4-3 to approve the pause on data centers. baynews9.com (opens in a new tab) local outlet Aug 32 acts on this row
Every act on the Lakeland row
  1. moratorium

    City commissioners voted 4-3 to approve the pause on data centers.

    baynews9.com (opens in a new tab) local outlet

  2. moratorium adopted

    Lakeland city commissioners voted Monday to approve a one year moratorium on any data center development.

    baynews9.com (opens in a new tab) local outlet

Last verified August 3, 2026.

22026-08-03
Manatee Countycountynot ratedManatee County Planning Commission approved an ordinance imposing a 12 month moratorium on data centers in unincorporated Manatee County, effective September 22 2026. yourobserver.com (opens in a new tab) local outlet Reported Sep 221 act on this row
Every act on the Manatee County row
  1. moratorium adopted

    Manatee County Planning Commission approved an ordinance imposing a 12 month moratorium on data centers in unincorporated Manatee County, effective September 22 2026.

    yourobserver.com (opens in a new tab) local outlet

Last verified September 22, 2026.

12026-09-22
Marion Countycountynot ratedMarion County commissioners directed staff to draft a 12 month permitting moratorium on data centers. 352today.com (opens in a new tab) local outlet Reported Aug 182 acts on this row
Every act on the Marion County row
  1. moratorium

    Marion County commissioners directed staff to draft a 12 month permitting moratorium on data centers

    352today.com (opens in a new tab) local outlet

  2. event

    Marion County commissioners voted July 21 to schedule a workshop for Sept. 1 to establish guidelines for data center developments

    ocalagazette.com (opens in a new tab) news outlet

Last verified August 18, 2026.

22026-08-18
Martin Countycountyrestrictive until August 26, 20272027-08-26Martin County commissioners voted to have staff return with a proposal for a possible one year moratorium on large scale hyperscale data center development. cbs12.com (opens in a new tab) local outlet Aug 26, 20265 acts on this row
Every act on the Martin County row
  1. moratorium

    Martin County Commission took its first of two required votes on October 13 for a one year moratorium on data centers.

    tcpalm.com (opens in a new tab) local outlet

  2. approval

    Martin County Commission rezoned 108 acres in Hobe Sound from manufacturing and storage to limited industrial zoning on September 15, 2026.

    yahoo.com (opens in a new tab) national outlet

  3. moratorium

    Martin County Commission agreed to move forward on one year moratorium on data centers

    tcpalm.com (opens in a new tab) local outlet

  4. moratorium

    Martin County commissioners voted to have staff return with a proposal for a possible one year moratorium on large scale hyperscale data center development.

    cbs12.com (opens in a new tab) local outlet

  5. litigation

    Greater Indiantown Community Alliance sued Indiantown and Florida Power & Light over Tesoro Groves planned unit development approval (alleged in the filing, not a finding)

    tcpalm.com (opens in a new tab) local outlet

Last verified October 13, 2026.

52026-10-13
Miami Lakescitynot ratedNo dated act on this row yet.2026-09-10
Miami-Dade Countycountynot ratedNo dated act on this row yet.2026-09-22
Okaloosa Countycountynot ratedStaff directed to explore data center location possibilities, power and water demand, noise, lighting, buffers and other development standards. weartv.com (opens in a new tab) local outlet Reported Sep 31 act on this row
Every act on the Okaloosa County row
  1. event

    Staff directed to explore data center location possibilities, power and water demand, noise, lighting, buffers and other development standards

    weartv.com (opens in a new tab) local outlet

Last verified September 3, 2026.

12026-09-03
Orange Countycountynot ratedOrange County commissioners voted in support of temporary moratorium on large data centers used for AI. wusf.org (opens in a new tab) local outlet Reported Sep 161 act on this row
Every act on the Orange County row
  1. moratorium

    Orange County commissioners voted in support of temporary moratorium on large data centers used for AI

    wusf.org (opens in a new tab) local outlet

Last verified September 16, 2026.

12026-09-16
Palm Beach Countycountyrestrictive until August 27, 20272027-08-27Palm Beach County commissioners unanimously approved language for the proposed moratorium ordinance on a one year ban on large scale data centers. sun-sentinel.com (opens in a new tab) local outlet Aug 27, 202612 acts on this row
Every act on the Palm Beach County row
  1. moratorium adopted

    Palm Beach County passed a data center moratorium

    commondreams.org (opens in a new tab) national outlet

  2. moratorium adopted

    Palm Beach County commissioners unanimously approved one year moratorium on large scale data centers (50+ megawatt peak load); moratorium expires September 24, 2027 or when code updates are complete, whichever comes first.

    sun-sentinel.com (opens in a new tab) local outlet

  3. event

    The county discussed the possibility of hiring a consultant, which could cost the county a couple hundred thousand dollars

    yahoo.com (opens in a new tab) national outlet

  4. moratorium adopted

    Palm Beach County commissioners gave unanimous final approval for a yearlong moratorium that prohibits the county from accepting, processing or approving any large scale data center applications

    yahoo.com (opens in a new tab) national outlet

  5. event

    Palm Beach County commissioners voted 5-1 to reject Project Tango, PBA Holdings' hyperscale AI data center plan in Loxahatchee.

    facebook.com (opens in a new tab) social media

  6. moratorium

    Palm Beach County advanced a plan to temporarily ban data centers

    sun-sentinel.com (opens in a new tab) local outlet

  7. moratorium

    Palm Beach County commissioners voted unanimously to pursue a yearlong pause on large scale data center applications

    therealdeal.com (opens in a new tab) news outlet

  8. moratorium adopted

    Palm Beach County commissioners unanimously approved language for the proposed moratorium ordinance on a one year ban on large scale data centers

    sun-sentinel.com (opens in a new tab) local outlet

  9. moratorium adopted

    Palm Beach County approved one year moratorium on large scale data centers last month

    palmbeachpost.com (opens in a new tab) local outlet

  10. denial

    Palm Beach County Board of County Commissioners voted to reject Project Tango following months of organized opposition from local residents.

    businessinsider.com (opens in a new tab) national outlet

  11. denial

    Palm Beach County Commissioners rejected planned hyperscale data center campus in July by 5-1 vote.

    floridapolitics.com (opens in a new tab) local outlet

  12. denial

    Palm Beach County commission voted 5 to-1 against Project Tango data center in July

    palmbeachpost.com (opens in a new tab) local outlet

Last verified September 28, 2026.

122026-09-28
Palmettocitynot ratedCommissioners directed attorneys Aug. 3 to draft temporary halt to data center development. tbbwmag.com (opens in a new tab) news outlet Aug 31 act on this row
Every act on the Palmetto row
  1. moratorium

    Commissioners directed attorneys Aug. 3 to draft temporary halt to data center development

    tbbwmag.com (opens in a new tab) news outlet

Last verified September 14, 2026.

12026-09-14
Pinellas Parkcityrestrictive until August 29, 20272027-08-29Pinellas Park approved data center moratorium. thegazette.com (opens in a new tab) local outlet Aug 16, 20262 acts on this row
Every act on the Pinellas Park row
  1. moratorium adopted

    Pinellas Park adopted a one year moratorium on data center applications.

    businessobserverfl.com (opens in a new tab) news outlet

  2. moratorium adopted

    Pinellas Park approved data center moratorium

    thegazette.com (opens in a new tab) local outlet

Last verified September 23, 2026.

22026-09-23
Sarasota Countycountynot ratedSarasota County Commission unanimously directed staff July 8 to implement a one year moratorium on applications for large scale data centers while updating county codes to prohibit such developments. heraldtribune.com (opens in a new tab) news outlet Jul 81 act on this row
Every act on the Sarasota County row
  1. moratorium

    Sarasota County Commission unanimously directed staff July 8 to implement a one year moratorium on applications for large scale data centers while updating county codes to prohibit such developments

    heraldtribune.com (opens in a new tab) news outlet

Last verified July 9, 2026.

12026-07-09
Volusia Countycountynot ratedVolusia County council voted to move forward with a permanent ban on large scale data center development. orlandoweekly.com (opens in a new tab) local outlet Reported Aug 251 act on this row
Every act on the Volusia County row
  1. moratorium

    Volusia County council voted to move forward with a permanent ban on large scale data center development

    orlandoweekly.com (opens in a new tab) local outlet

Last verified August 25, 2026.

12026-08-25

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

Florida laws and the full scorecard

Bills and laws in Florida

5 signed into law, 8 bills tracked

8 bills tracked in the Florida legislature, 5 of them signed into law, grouped by where each stands. A row opens its own page; the Florida laws page has what each law requires.

Signed into law 5

  • Data Centers

    SB 484 Signed

    What it says and where it is from

    Specifying that local governments maintain authority to exercise power and responsibility over comprehensive planning and land development regulations relating to large load customers; requiring public utilities to provide certain minimum tariff and service requirements for large load customers; prohibiting the governing board of a water management district or the Department of Environmental Protection from issuing a permit for the consumptive use of water to a large scale data center under certain circumstances; requiring the Office of Program Policy Analysis and Government Accountability to contract for a study relating to the construction and operation of large scale data centers, etc. As published by the legislature, found through LegiScan.

    What it requires, on the Florida laws page.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology

    S. 2518 Signed

    What it says and where it is from

    Providing that all functions, records, personnel, contracts, interagency agreements, and assets of the Department of Management Services State Data Center are transferred to the Northwest Regional Data Center; deleting the operational management and oversight of the state data center from the powers, duties, and functions of the department, acting through Florida Digital Service; requiring the department to assist customer entities transitioning from other cloud computing services to the Northwest Regional Data Center or a cloud computing service procured by the state data center; designating the Northwest Regional Data Center as the state data center, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Taxation

    H. 7061 Signed

    What it says and where it is from

    Specifying that portions of property not used for certain purposes are not exempt from ad valorem taxation; specifying that exemptions for certain portions of property from ad valorem taxation are not affected so long as such portions of property are used for specified purposes; exempting certain multifamily projects from ad valorem taxation; requiring, rather than authorizing, tax collectors to accept late payments of prepaid property taxes within a certain timeframe; extending the expiration date of the sales tax exemption for data center property; exempting specified items that assist in independent living from the sales tax, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology Governance

    H. 7073 Signed

    What it says and where it is from

    Creates Agency for State Technology (AST); provides for appointment of executive director of AST, who shall serve as chief information officer; transfers certain assets and authority of Agency for Enterprise Information Technology, Northwood Shared Resource Center, & Southwood Shared Resource Center to AST; establishes single state data center; revises schedules for consolidation of state agency data centers & computing facilities into state data center; provides additional duties of FDLE Cybercrime Office; repeals provisions for statewide e mail service; provides appropriations. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology [WPSC]

    S. 2020 Signed

    What it says and where it is from

    Revises the duties and responsibilities of the Agency for Enterprise Information Technology. Requires that the agency develop standards for information technology services. Specifies the contents of financial statements that must be provided by primary data centers. Requires that each data center submit to its board of trustees cost reduction proposals and organizational plans, etc. APPROPRIATION: $300,000. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

In committee 2

  • Data Centers

    H. 1007 In committee

    What it says and where it is from

    Prohibits agency from entering into nondisclosure agreement or other contract that restricts agency from disclosing certain information to public; specifies that local governments maintain authority to exercise power & responsibility over comprehensive planning & land development regulations related to large load customers; prohibits large load customer from being considered electric substation; requires applicants for construction permits for certain new data center in specified areas to demonstrate that operation of data center will comply with certain provisions & submit specified study in support of such application; requires PSC to develop minimum tariff & service requirements for large load customers; prohibits governing board of water management district or DEP from issuing permit for consumptive use of water to large scale data center; requires governing board or DEP to require use of reclaimed water for large scale data center applicant's allocation when certain requirements are met. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Public Records/Data Centers

    S. 1118 In committee

    What it says and where it is from

    Providing an exemption from public records requirements for information relating to the plans, intentions, or interest of a person to locate a data center; providing for future legislative review and repeal of the exemption; providing a statement of public necessity, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

Failed or died 1

  • Approval of Data Center Facilities

    H. 1517 Died at adjournment

    What it says and where it is from

    Requires applications for approval of data center facilities to include specified disclosures; requires existing data centers to disclose specified information; requires DEP to make such information publicly available on its website; provides penalty; prohibits certain tax credits, exemptions, protections, & restrictions for such information; requires DEP to adopt rules. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

8 bills tracked, 5 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
SB 484 2026 Regular Session Signed 2026-05-08 Data Centers
H. 1517 2026 Regular Session Died at adjournment 2026-03-13 Approval of Data Center Facilities
H. 1007 2026 Regular Session In committee 2026-03-02 Data Centers
S. 1118 2026 Regular Session In committee 2026-01-12 Public Records/Data Centers
S. 2518 2022 Regular Session Signed 2022-06-03 Information Technology
H. 7061 2021 Regular Session Signed 2021-05-24 Taxation
H. 7073 2014 Regular Session Signed 2014-06-20 Information Technology Governance
S. 2020 2010 Regular Session Signed 2010-05-28 Information Technology [WPSC]

8 bills tracked in Florida; 2026 Sixth Special Session, legislature adjourned; last checked October 26, 2026. The last check found: 4 bills matched the watch terms as of October 26, 2026. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. Florida's members: 23 yea, 0 nay, 4 present or not voting. How each member voted

MemberPartyPosition
Bean (FL)RYea
BilirakisRYea
BuchananRNot Voting
CammackRYea
Castor (FL)DYea
Diaz-BalartRYea
DonaldsRYea
Dunn (FL)RNot Voting
FineRYea
Frankel, LoisDYea
Franklin, ScottRYea
FrostDYea
GimenezRYea
HaridopolosRYea
Lee (FL)RYea
LunaRYea
MastRYea
MillsRNot Voting
MoskowitzDYea
PatronisRYea
RutherfordRYea
SalazarRNot Voting
SotoDYea
SteubeRYea
Wasserman SchultzDYea
Webster (FL)RYea
Wilson (FL)DYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. Florida's members: 2 yea, 0 nay. How each member voted

MemberPartyPosition
Moody (R-FL)RYea
Scott (R-FL)RYea

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What was said

Governor Ron DeSantis considers SB 484 watered down but a pretty strong first step in protecting consumers from potential harms of artificial intelligence
Ron DeSantis, Governor of Florida · October 4, 2026 · paraphrased · WUSF Public Media (opens in a new tab) local outlet
Duke Energy Florida does not currently have any large load data center customers within its service territory but has developed a proposal with safeguards requiring new data center customers to sign long term agreements, provide significant collateral, meet minimum payment requirements, and pay penalties for early termination
Melissa Seixas, Duke Energy Florida president · October 2, 2026 · paraphrased · Florida Politics (opens in a new tab) local outlet

Every Florida statement, by speaker (137)

127 more on this page, one per speaker and claim; 137 statements in all

Google announced a $1 million investment in the Home Builders Institute to address skilled trade worker shortages for data center construction

Ed Brady, President & CEO of the Home Builders Institute floridadaily.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: floridadaily.com (opens in a new tab).

Byron Donalds stated Florida state law will keep utility rates in check and prevent utility bills from increasing due to data centers

Republican gubernatorial candidate Yahoo (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yahoo (opens in a new tab).

Angie Nixon proposed that communities affected by data centers receive dividend payments similar to Alaska's natural resource distribution system.

Florida Democratic Senate candidate newsweek.com (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: newsweek.com (opens in a new tab).

Loudoun County supervisor Mike Turner graded Loudoun a failure on five of six data center tests (noise, power, emissions, setback, appearance), with water as the only pass.

Loudoun County Vice Chair and Ashburn District Supervisor 352today (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: 352today (opens in a new tab).

Loudoun County supervisor Mike Turner stated that Loudoun treated data centers as office parks in 2000, making them by right, and now has four hyperscale data centers that cannot be voted down, with by right ending on March 18, 2025.

Loudoun County Vice Chair and Ashburn District Supervisor 352today (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: 352today (opens in a new tab).

Heidi Cramer, business consultant for the Florida Small Business Development Center at FGCU, said the data center issue is the most talked about and misunderstood issue.

Florida Weekly (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Weekly (opens in a new tab).

Imran Siddiqui, executive director of the Florida Digital Infrastructure and Security Alliance, said a data center brings in tax revenue and creates more than 100 six figure jobs.

Florida Weekly (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Weekly (opens in a new tab).

Jolly suggested Byron Donalds' acceptance of donations from data center developers would lead to more data centers in Florida

Florida gubernatorial candidate Bay News 9 (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Bay News 9 (opens in a new tab).

Sherry Ambrose, director of economic development for Florida Power and Light, said if a new generator is needed for power, the data center pays 100 percent of that cost.

Florida Weekly (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Weekly (opens in a new tab).

Jay Stearman, county planner, stated large scale data centers require substantial water and electrical resources comparable to small municipalities and do not support many long term employment opportunities, often emitting low frequency nuisance noise.

county planner, Manatee County yourobserver.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: yourobserver.com (opens in a new tab).

Commissioner Amanda Ballard stated the moratorium would give staff time to fill gaps in Manatee County regulations regarding data centers, which are not adequately addressed in land development code or comprehensive plan.

Manatee County Commissioner yourobserver.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: yourobserver.com (opens in a new tab).

Democratic U.S. Senate candidate Angie Nixon headlined a town hall in Fort Meade on Monday to outline federal safeguards she says should include transparency, environmental review and community input

Tampa Bay 28 (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Tampa Bay 28 (opens in a new tab).

Nikki Fried, chair of Florida Democratic Party, said Westview community was not informed about data center construction until too late due to hidden negotiations and backroom deals.

NBC 6 South Florida (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NBC 6 South Florida (opens in a new tab).

Adam Kramer stated the project would generate $44 million a year of tax revenue from energy use going directly into infrastructure projects to support rural Martin County and Indiantown.

Project Executive cbs12.com (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: cbs12.com (opens in a new tab).

Jimmy Patronis, Florida District 1 representative, voted to advance H.R. 9430, the Ratepayer Protection Act, which would protect ratepayers from paying costs of AI data center power and grid infrastructure.

Yahoo (opens in a new tab) national outlet

Confirmed by the record: Patronis voted Yea on H.R. 9340, U.S. House of Representatives roll call 312, September 16, 2026. Read from the statement's words: Jimmy Patronis voted for H.R. 9430. The statement gives the number as H.R. 9430; the record's Ratepayer Protection Act is H.R. 9340. Checked against the roll call the record holds on the bill, as the clerk printed it.

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yahoo (opens in a new tab).

Donalds now says he no longer agrees with the national moratorium and was not the biggest fan of that provision

Naples Republican gubernatorial candidate Florida Phoenix (opens in a new tab) local outlet · [Archived Copy] (opens in a new tab)
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Phoenix (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Also reported by: WUSF Public Media (opens in a new tab) local outlet , Creative Loafing Tampa (opens in a new tab) news outlet .

Byron Donalds voted in May 2025 for the U.S. House's version of the One Big Beautiful Bill Act, which included a 10 year moratorium on enforcement of state or local regulations for artificial intelligence models

Naples Republican gubernatorial candidate Florida Phoenix (opens in a new tab) local outlet · [Archived Copy] (opens in a new tab)

Not on the record: the record holds no bill called the One Big Beautiful Bill Act. Read from the statement's words: Byron Donalds voted for the One Big Beautiful Bill Act (2025). Checked against the bills and roll calls the record holds.

Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Phoenix (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Also reported by: WUSF Public Media (opens in a new tab) local outlet , Creative Loafing Tampa (opens in a new tab) news outlet .

Grassroots opposition to AI infrastructure because of its huge demand on local water supplies and the electrical grid has been growing since early 2026

unnamed grassroots opponents Florida Phoenix (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Phoenix (opens in a new tab).

Florida Democratic Party made visit to Pinellas County to criticize Rep. Byron Donalds over campaign donations from tech executives and AI developers.

WFLA (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WFLA (opens in a new tab).

David Jolly has promised that if elected governor, he will declare a year long statewide moratorium on construction of data centers in Florida

Florida Democratic gubernatorial candidate Florida Phoenix (opens in a new tab) local outlet · [Archived Copy] (opens in a new tab)
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Florida Phoenix (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Also reported by: Creative Loafing Tampa (opens in a new tab) news outlet .

Byron Donalds supports keeping data centers away from homes and using cooling technology that conserves water, including systems that recirculate water or use air cooling.

Republican candidate for Florida governor Tampa Bay 28 (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Tampa Bay 28 (opens in a new tab).

Kelly Martinez Semrad said the county needs more time to evaluate the short, medium and long term effects of large AI data centers, citing concerns about water consumption, increased utility costs for nearby residents and noise

Orange County Commissioner District 5 FOX 35 Orlando (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: FOX 35 Orlando (opens in a new tab).

Russo's Florida Data Center Community Responsibility Act includes five principles: Community Responsibility Tax, Host Community Fund, Five Year Modernization Deadline, Energy Self Sufficiency, and End Taxpayer Subsidies

Florida gubernatorial candidate Morningstar (opens in a new tab) press release · [Archived Copy] (opens in a new tab)
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Morningstar (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Jolly said data centers destabilize communities, devalue real estate, carry environmental impacts, pose public health concerns, and lack a long term economic benefit

Democratic nominee for Florida governor Hoodline (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Hoodline (opens in a new tab).

Byron Donalds introduced federal legislation called the Protecting Ratepayers Act requiring commercial data centers consuming five megawatts or more to generate their own off grid power

Republican nominee for Florida governor Hoodline (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Hoodline (opens in a new tab).

Leon County Commissioner Nick Maddox stated there is time and place for data centers but county needs twelve months to figure out if permitting them is appropriate

WTXL ABC 27 (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WTXL ABC 27 (opens in a new tab).

Dianne Triplett, Duke Energy deputy general counsel, said the company's proposal includes a 20 year minimum commitment, significant financial assurances, early termination obligations, monthly minimum bills, and two years' notice before termination

The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

Walt Trierweiler, Office of Public Counsel, said Duke's tariff proposal does not set out a distinct rate schedule for large load customers

The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

Bradley Marshall, Florida Rising, stated that data centers must pay their full cost of service and Duke's proposal does not come close

The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

"I have statutory exceptions that the Council can use for trade secrets. If someone is bringing forward a proposal considered a trade secret and they're willing to indemnify the Village while they speak to us so we can protect their records, then we have that opportunity. So, an NDA should not be needed."
Janet Smith, Interim Village Attorney, Indiantown Village Indiantown Village Council Meeting Hometown News Treasure Coast (opens in a new tab) news outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Indiantown Village Council Meeting.

Primary source: Hometown News Treasure Coast (opens in a new tab).

"What we would like to proffer to the Council is two ordinances. They will both have to go through planning and zoning and come before you on two separate readings. You will have public comment at each of those meetings. The first one is the moratorium that we feel will be legally defensible. The second one is the transparency ordinance."
Janet Smith, Interim Village Attorney, Indiantown Village Indiantown Village Council Meeting Hometown News Treasure Coast (opens in a new tab) news outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Indiantown Village Council Meeting.

Primary source: Hometown News Treasure Coast (opens in a new tab).

Commission Chairman Jamie English said a moratorium would send the wrong message and that the county lacks rules for issuing data center permits

Taylor County Commission Chairman WCTV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WCTV (opens in a new tab).

Commissioner Pam Feagle proposed a 12 month moratorium on data centers to allow time for land development revisions

Taylor County Commissioner WCTV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WCTV (opens in a new tab).

Byron Flagg stated that Florida Senate Bill 484 requires data centers to obtain consumptive use permits and preserves local government oversight through comprehensive planning and land development codes

environmental attorney, Gray Robinson Mid Florida Newspapers (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Mid Florida Newspapers (opens in a new tab).

Aaron Blyeu, chief development officer of Cloverleaf Infrastructure, stated typical data center projects request 75,000 gallons of water, mostly for initial system build, with ongoing use limited to offices, toilets, break rooms, and kitchens

chief development officer, Cloverleaf Infrastructure Mid Florida Newspapers (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Mid Florida Newspapers (opens in a new tab).

Imran Siddiqui, executive director of Florida Digital Infrastructure and Security Alliance Board, told Florida League of Cities Annual Conference attendees that data centers are essential infrastructure and Florida should compete for data center investment

executive director, Florida Digital Infrastructure and Security Alliance Board Mid Florida Newspapers (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Mid Florida Newspapers (opens in a new tab).

David Jolly vows to enact a one year moratorium on Florida data center construction if elected

gubernatorial nominee Central Florida Public Media (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Central Florida Public Media (opens in a new tab).

Also reported by: Yahoo (opens in a new tab) national outlet , Tampa Bay 28 (opens in a new tab) local outlet , SuaraGarut.ID (opens in a new tab) international outlet , islandernews.com (opens in a new tab) news outlet , Bay News 9 (opens in a new tab) local outlet .

Said again: September 7, 2026 ( Yahoo (opens in a new tab) national outlet ), September 16, 2026 ( Tampa Bay 28 (opens in a new tab) local outlet ), September 17, 2026 ( SuaraGarut.ID (opens in a new tab) international outlet ), September 20, 2026 ( islandernews.com (opens in a new tab) news outlet ), September 23, 2026 ( Bay News 9 (opens in a new tab) local outlet ).

Okaloosa County Commissioner Trey Goodwin stated I know a lot of jurisdictions have taken the position that they either need to ban or put on moratoriums for these things, I'm concerned that is taking the wrong approach

Okaloosa County Chairman WEAR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WEAR-TV (opens in a new tab).

Duke Energy proposes minimum 20 year contract term and minimum monthly bill provisions for large load data center customers

Dianne Triplett, attorney for Duke Energy The Florida Trib (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Florida Trib (opens in a new tab).

Also reported by: Utility Dive (opens in a new tab) trade press .

Said again: August 27, 2026 ( Utility Dive (opens in a new tab) trade press ).

Volusia County is highly susceptible to sinkholes, with approximately 10 percent of Florida being most susceptible and Volusia in the heart of one of those areas

Don Dempsey, Volusia County council member Orlando Weekly (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Orlando Weekly (opens in a new tab).

Carol McFarlane, planning and development services director, said data center water and electricity impacts are huge and noise and low frequency sound pose public health concerns

Volusia County planning and development services director Orlando Weekly (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Orlando Weekly (opens in a new tab).

Mayor Pro Tem Doug Capps referenced approximately 1,400 acres of undeveloped land near the bypass that could require city water and sewer service and possible annexation if developed.

The Cool Down (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Cool Down (opens in a new tab).

Mark McNees, Florida State University professor, stated: 'Saying rates will not go up because of the law claims an outcome the statute does not deliver'

Yahoo (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yahoo (opens in a new tab).

Hyperscale data centers use millions of gallons of water per day and their electric demand often requires governments to build new power infrastructure.

Michele Norton, assistant director Sarasota County Planning & Development Services ABC7 WWSB (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ABC7 WWSB (opens in a new tab).

Donalds filed message legislation called the Protecting Ratepayers Act in summer 2026 to require data centers to draw on alternative sources for power and water.

Republican gubernatorial candidate Florida Politics (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Florida Politics (opens in a new tab).

"We've tried to flip this and say we know we have to build new generation to serve these (large) customers, and they should be the ones to pay for it."
Tiffany Cohen, Vice President of Rate and Regulatory Strategy, Florida Power & Light House panel FlaglerLive (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: House panel.

Primary source: FlaglerLive (opens in a new tab).

"If we don't do this, others are going to get ahead of us."
Jason Brodeur, State Senator, Florida State Senate Florida State Senate Regulated Industries Committee FlaglerLive (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Florida State Senate Regulated Industries Committee.

Primary source: FlaglerLive (opens in a new tab).

On the November 3, 2026 ballot in Florida: Governor (8), U.S. Senate (3), U.S. House, District 1 (3), U.S. House, District 2 (2), U.S. House, District 3 (3), U.S. House, District 4 (4), U.S. House, District 5 (2), U.S. House, District 6 (3), U.S. House, District 7 (3), U.S. House, District 8 (2), U.S. House, District 9 (2), U.S. House, District 10 (1), U.S. House, District 11 (3), U.S. House, District 12 (3), U.S. House, District 13 (3), U.S. House, District 14 (3), U.S. House, District 15 (2), U.S. House, District 16 (3), U.S. House, District 17 (3), U.S. House, District 18 (3), U.S. House, District 19 (3), U.S. House, District 20 (3), U.S. House, District 21 (3), U.S. House, District 22 (2), U.S. House, District 23 (2), U.S. House, District 24 (2), U.S. House, District 25 (3), U.S. House, District 26 (3), U.S. House, District 27 (2), U.S. House, District 28 (3); 9 of 85 candidates with a statement on data centers on the record. Every candidate.

What your members of Congress said

On federal matters, filed on the federal page; not counted among Florida's statements.

  • Kathy Castor, U.S. Representative (D-FL): Rep. Kathy Castor, D Florida, is a Democratic co sponsor of the Ratepayer Protection Act. (September 16, 2026)

Already running in Florida

11 sites are serving load, 5 of them in Miami-Dade County.

See the 11 running sites
  1. Centersquare Tampa data center Tampa, Hillsborough County Running
  2. Cologix Jacksonville Jacksonville, Duval County Running · Operational since 2017 (9 years)
  3. Cologix LAK1 Lakeland, Polk County Running
  4. DataBank Miami data center Miami, Miami-Dade County Running
  5. Digital Realty Miami Miami, Miami-Dade County Running · Operational since 2008 (18 years)
  6. Equinix MI3 Boca Raton, Palm Beach County Running · Operational since 2014 (12 years)
  7. Equinix MI6 Doral, Miami-Dade County Running · Operational since 2021 (5 years)
  8. Equinix Miami Miami, Miami-Dade County Running · Operational since 2004 (22 years)
  9. H5 Tampa Tampa, Hillsborough County Running
  10. QTS Miami Miami, Miami-Dade County Running · Operational since 2013 (13 years)
  11. TierPoint Jacksonville Data Center Jacksonville, Duval County Running

Questions about Florida data centers

How many data center projects are on the record in Florida?

16 projects are on the record in Florida: 5 reported, 11 running and 2 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in Florida are they?

Records are in 8 counties: Miami-Dade County (5), Duval County (2), Hillsborough County (2), Palm Beach County (2), St. Lucie County (2), Martin County (1), Orange County (1) and Polk County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in Florida?

Not disclosed. None of the 16 records on file for Florida states a power figure. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in Florida say they will use?

Not disclosed. None of the 16 records on file for Florida states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in Florida?

10 developers are named on the record: Equinix (3 records), Cologix (2 records), Centersquare, DataBank, Digital Realty, EdgeConneX, H5 Data Centers, QTS Data Centers, TierPoint and Willow Lakes LLC. 3 records name no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in Florida have rules about data centers?

22 county and city rows are on the record, 5 of them rated: Fort Meade is rated case by case: Fort Meade data center project was approved by city commission in April, September 22, 2026, source (opens in a new tab), Lake County is rated restrictive: Lake County in Central Florida has paused or outright banned permits for new data centers, September 11, 2026, source (opens in a new tab) and Martin County is rated restrictive: Martin County commissioners voted to have staff return with a proposal for a possible one year moratorium on large scale hyperscale data center development, August 26, 2026, source (opens in a new tab). The state's own row is rated case by case, with 23 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in Florida, by county?

5 records are not yet running. St. Lucie County: Treasure Coast Surf Park Data Center (reported) and St. Lucie County Data Center (I-95) (reported); Martin County: Indiantown Data Center (reported); Orange County: Eatonville AI Data Center (reported); and Palm Beach County: AI Data Center near Mar-a-Lago (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of Florida itself decided?

5 state laws are on the record: SB 484 (signed, May 8, 2026, source (opens in a new tab)), S. 2518 (signed, June 3, 2022, source (opens in a new tab)) and H. 7061 (signed, May 24, 2021, source (opens in a new tab)) and 2 more under Laws. The state's own scorecard row carries 23 dated acts, the newest October 1, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

nothing disclosed by 16 records

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power016
Water, stated per day016
Water, stated per year016
Permanent jobs016
Tax each year016

A blank cell means no record in Florida disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power016
Water, stated per day016
Water, stated per year016
Permanent jobs016
Tax each year016

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 16 tracked facilities in Florida are for. 2 sites not yet verified are named apart and are not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use16

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

No source on file states how any of the 16 tracked facilities in Florida are cooled. 2 sites not yet verified are named apart and are not in that number.

Sources read for Florida

26 sources

26 sources are read for Florida:

Newspapers
Orlando Sentinel, Tampa Bay Times
Public broadcaster
WUSF Public Media
Search feeds
23 news searches
Every feed, with its kind and tier

What the monitor reads for Florida: feeds every four hours, pages daily.

Public broadcaster

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Florida", https://datacenterrecord.org/states/fl, updated October 24, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in Florida", https://datacenterrecord.org/states/fl. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
FL
Rating of the state's own row
Case by case
Count by status
reported 5, running 11, not yet verified 2
Located records
1 located, 15 at a centroid, 0 without coordinates

Researcher view · Florida · 16 data center sites, 0 buildings where disclosed, 23 rule rows, 8 bills · basis and source tier on every row · verified October 24, 2026