● Running First recorded September 14, 2026 · 2 Buildings

Cologix Jacksonville Data Center Campus (JAX1 and JAX2)

Street address 421 West Church Street and 4800 Spring Park Road, Jacksonville, FL 32202, Duval County verified address Exact, at the address cologix.com (opens in a new tab)

Overview, regulatory gates and specifications

Cologix operates two network neutral colocation facilities in Jacksonville, JAX1 inside the JaxNAP carrier hotel at 421 West Church Street and JAX2 at 4800 Spring Park Road in Duval County, Florida. [1] Filings on the record specify disclosed capacity of 9 MW (the developer's figure), 2 planned or operational buildings. [1] Cologix lists Cologix JAX1, Cologix JAX2 at Jacksonville, Florida on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
9 MW
the developer's figure

Equivalent to ~7,470 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.4% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
2 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 421 West Church Street and 4800 Spring Park Road, Jacksonville, FL 32202.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
9 MW developer figure Equivalent to the continuous electricity demand of about 7,470 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.088 percent) of New York City's summer peak demand in 2024.
cologix.com (opens in a new tab)
Water usage
Not disclosed
Land area
Not disclosed
Buildings
2 buildings operator page
cologix.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2017 (9 years)
Who leads it
Cologix as stated by the source
Official project website
cologix.com (opens in a new tab) verified October 28, 2026
cologix.com (opens in a new tab)
Archived promotional websites
cologix.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Cologix Jacksonville Data Center Campus (JAX1 and JAX2), capacity: 9 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 9 ÷ 10,245 = 0.00088 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Karen McAllister

JEA media relations manager

DID Recorded statement at Data Center Dynamics (July 15, 2022)
SAID Cologix building meets Category 5 hurricane rating requirements (July 15, 2022) datacenterdynamics.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Cologix
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Cologix Jacksonville Data Center Campus (JAX1 and JAX2).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 9 MW 9 MW the developer's figure
Site Footprint (Acres)
Data Hall Buildings 2 buildings 2 operator page
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Cologix lists Cologix JAX1, Cologix JAX2 at Jacksonville, Florida on its own page of data center locations, read September 14, 2026.

    [1] cologix.com

Nearest data centers in Florida

Verified data center records in Florida within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
JaxNAP Jacksonville Carrier Hotel (SBA Edge) Jacksonville, Duval County Less than 1 mi Running SBA Edge 14 MW
Cologix Jacksonville (JAX2) Jacksonville, Duval County 5 mi Running Cologix 1 building
EdgeConneX Jacksonville Data Center (EDCJAX01) Jacksonville, Duval County 6 mi Running EdgeConneX 6 MW
Flexential Jacksonville Deerwood Data Center (JAX01 and JAX02) Jacksonville, Duval County 8 mi Running Flexential 8 MW
TierPoint Jacksonville Baymeadows Data Center Jacksonville, Duval County 9 mi Running TierPoint 6 MW

Blank cell: not disclosed by any source on file.

Common questions about Cologix Jacksonville Data Center Campus (JAX1 and JAX2)

Answered directly from the verified filings and local actions on this page.

Who is building Cologix Jacksonville Data Center Campus (JAX1 and JAX2)?

Cologix is the developer. No construction contractor is named on the record yet.

How much power and water does Cologix Jacksonville Data Center Campus (JAX1 and JAX2) say it needs?

Power: 9 MW (the developer's figure, cologix.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Cologix Jacksonville Data Center Campus (JAX1 and JAX2) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Cologix: Data centers (opens in a new tab), Cologix, September 14, 2026

1 source on file.

Regional grid context

This site is in the FRCC All (FRCC) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Cologix Jacksonville Data Center Campus (JAX1 and JAX2)", https://datacenterrecord.org/projects/cologix-jacksonville-fl, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Cologix Jacksonville Data Center Campus (JAX1 and JAX2)", https://datacenterrecord.org/projects/cologix-jacksonville-fl. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
30.331375, -81.662322
How the location is known
Location from the site's street address.
Location source
https://www.cologix.com/data-centers/jacksonville/
Coordinate source
Duval County Property Appraiser / Cologix
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
9 MW, the developer's figure
Published
September 14, 2026
Last verified
October 27, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Cologix Jacksonville Data Center Campus (JAX1 and JAX2) · 1 source, 1 entry · basis and source tier on every row · verified October 27, 2026