1 rule at the state level: 1 statute. Each says what it requires in the words of its text, with the effective date the text gives and a link to the bill or order.

Last verified

Rules on the record
1
Passed
1
Statutes
1

Rules in Florida

  • S. 484 Statute

    Data Centers

    Passed passed May 8, 2026. 2026 Regular Session. This status is read from the bill's own record, not written here.

    S. 484 of the 2026 Regular Session was signed on May 8, 2026. The legislature titles it: Data Centers.

    What it requires

    By October 1, 2026 every public utility other than a gas utility must file a tariff for the Public Service Commission's approval whose terms reasonably ensure that each large load customer bears its own full cost of service, connection, incremental transmission and generation, other infrastructure and operations included, that the general body of ratepayers does not carry the...

    By October 1, 2026 every public utility other than a gas utility must file a tariff for the Public Service Commission's approval whose terms reasonably ensure that each large load customer bears its own full cost of service, connection, incremental transmission and generation, other infrastructure and operations included, that the general body of ratepayers does not carry the risk of nonpayment, and that the utility does not serve a large load customer which is a foreign entity. A large load customer is one with an anticipated monthly peak load of 50 megawatts or more at a single location, and a customer may not split a load at one location into smaller connections to fall below it. No tariff, contract or utility policy may hinder curtailment of a large load customer where that is meant to hold the grid stable, limit an outage or protect public safety. A water management district or the Department of Environmental Protection may not issue a consumptive use permit to a large scale data center where the use would harm the area's water resources or is barred by local zoning, may not approve one without a hearing, and must require reclaimed water in place of surface water or groundwater where the act's conditions are met; an application for an average of 100,000 gallons a day or more must come with every source, amount and loss of water and a conservation plan. The act also orders an independent study of large scale data centers, due to the Governor and the Legislature by July 1, 2027.

    Describes the act as enacted.

    The text: flsenate.gov (opens in a new tab) primary source

    Last verified September 24, 2026.

A law here is one statute, utility commission order, tariff, tax rule, moratorium or bill at the state level. What it requires is taken from the text, never summarized from coverage; a date the text does not give is left empty. Its status is one of five, defined on the laws index. The dated events beneath a law are the scorecard entries that cite it.

Bills tracked

8 bills tracked in the Florida legislature: 5 signed into law, 2 in committee, 1 failed or died. A row opens its own page, with its history, each recorded vote and the legislature's own text. A resolution states a position and does not change the law.

Signed into law 5

  • Data Centers

    SB 484 Signed

    2026 Regular Session.

    Specifying that local governments maintain authority to exercise power and responsibility over comprehensive planning and land development regulations relating to large load customers; requiring...

    Specifying that local governments maintain authority to exercise power and responsibility over comprehensive planning and land development regulations relating to large load customers; requiring public utilities to provide certain minimum tariff and service requirements for large load customers; prohibiting the governing board of a water management district or the Department of Environmental Protection from issuing a permit for the consumptive use of water to a large scale data center under certain circumstances; requiring the Office of Program Policy Analysis and Government Accountability to contract for a study relating to the construction and operation of large scale data centers, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology

    S. 2518 Signed

    2022 Regular Session.

    Providing that all functions, records, personnel, contracts, interagency agreements, and assets of the Department of Management Services State Data Center are transferred to the Northwest Regional...

    Providing that all functions, records, personnel, contracts, interagency agreements, and assets of the Department of Management Services State Data Center are transferred to the Northwest Regional Data Center; deleting the operational management and oversight of the state data center from the powers, duties, and functions of the department, acting through Florida Digital Service; requiring the department to assist customer entities transitioning from other cloud computing services to the Northwest Regional Data Center or a cloud computing service procured by the state data center; designating the Northwest Regional Data Center as the state data center, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Taxation

    H. 7061 Signed

    2021 Regular Session.

    Specifying that portions of property not used for certain purposes are not exempt from ad valorem taxation; specifying that exemptions for certain portions of property from ad valorem taxation are not...

    Specifying that portions of property not used for certain purposes are not exempt from ad valorem taxation; specifying that exemptions for certain portions of property from ad valorem taxation are not affected so long as such portions of property are used for specified purposes; exempting certain multifamily projects from ad valorem taxation; requiring, rather than authorizing, tax collectors to accept late payments of prepaid property taxes within a certain timeframe; extending the expiration date of the sales tax exemption for data center property; exempting specified items that assist in independent living from the sales tax, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology Governance

    H. 7073 Signed

    2014 Regular Session.

    Creates Agency for State Technology (AST); provides for appointment of executive director of AST, who shall serve as chief information officer; transfers certain assets and authority of Agency for...

    Creates Agency for State Technology (AST); provides for appointment of executive director of AST, who shall serve as chief information officer; transfers certain assets and authority of Agency for Enterprise Information Technology, Northwood Shared Resource Center, & Southwood Shared Resource Center to AST; establishes single state data center; revises schedules for consolidation of state agency data centers & computing facilities into state data center; provides additional duties of FDLE Cybercrime Office; repeals provisions for statewide e mail service; provides appropriations. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Information Technology [WPSC]

    S. 2020 Signed

    2010 Regular Session.

    Revises the duties and responsibilities of the Agency for Enterprise Information Technology. Requires that the agency develop standards for information technology services.

    Revises the duties and responsibilities of the Agency for Enterprise Information Technology. Requires that the agency develop standards for information technology services. Specifies the contents of financial statements that must be provided by primary data centers. Requires that each data center submit to its board of trustees cost reduction proposals and organizational plans, etc. APPROPRIATION: $300,000. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

In committee 2

  • Data Centers

    H. 1007 In committee

    2026 Regular Session.

    Prohibits agency from entering into nondisclosure agreement or other contract that restricts agency from disclosing certain information to public; specifies that local governments maintain authority...

    Prohibits agency from entering into nondisclosure agreement or other contract that restricts agency from disclosing certain information to public; specifies that local governments maintain authority to exercise power & responsibility over comprehensive planning & land development regulations related to large load customers; prohibits large load customer from being considered electric substation; requires applicants for construction permits for certain new data center in specified areas to demonstrate that operation of data center will comply with certain provisions & submit specified study in support of such application; requires PSC to develop minimum tariff & service requirements for large load customers; prohibits governing board of water management district or DEP from issuing permit for consumptive use of water to large scale data center; requires governing board or DEP to require use of reclaimed water for large scale data center applicant's allocation when certain requirements are met. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

  • Public Records/Data Centers

    S. 1118 In committee

    2026 Regular Session.

    Providing an exemption from public records requirements for information relating to the plans, intentions, or interest of a person to locate a data center; providing for future legislative review and...

    Providing an exemption from public records requirements for information relating to the plans, intentions, or interest of a person to locate a data center; providing for future legislative review and repeal of the exemption; providing a statement of public necessity, etc. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

Failed or died 1

  • Approval of Data Center Facilities

    H. 1517 Died at adjournment

    2026 Regular Session.

    Requires applications for approval of data center facilities to include specified disclosures; requires existing data centers to disclose specified information; requires DEP to make such information...

    Requires applications for approval of data center facilities to include specified disclosures; requires existing data centers to disclose specified information; requires DEP to make such information publicly available on its website; provides penalty; prohibits certain tax credits, exemptions, protections, & restrictions for such information; requires DEP to adopt rules. As published by the legislature, found through LegiScan.

    Source: the legislature's page (opens in a new tab). Found through LegiScan.

8 bills tracked in Florida; 2026 Sixth Special Session, legislature adjourned. 4 bills matched the watch terms as of October 26, 2026. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill. LegiScan is credited as the finder; the citation is the legislature's own page. How bills and votes are recorded.

This page as data CSV JSON
Cite this page

Data Center Record, "Data center laws in Florida", https://datacenterrecord.org/laws/fl. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change

Researcher view · basis and source tier on every row · docket and Census GEOIDs · citation and export tools

Commercial and bulk data