Data centers in Orange County, Florida
Orange County has 3 data centers on the record: 2 running and 1 proposed. Orange County has a scorecard row with no rating yet. The latest decision on the record: Orange County commissioners voted in support of temporary moratorium on large data centers used for AI, reported September 16, 2026.
The 3 data centers in Orange County
Every Orange County record 3 records · blank cell: not disclosed · sort by any column
| Facility and county | Stage | Operator | Power (MW) | Latest entry | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| CoreSite Orlando Data Center Campus (OR1) Orlando, Orange County | Running | CoreSite | 14 | the developer's figure | site | 1 | 2026-10-27 | |
| HostDime Orlando Tier IV Global Data Center Orlando, Orange County | Running | HostDime | 10 | the developer's figure | site | 1 | 2026-10-27 | |
| Eatonville Wymore Road AI Data Center Proposal Eatonville, Orange County | Proposed | Eatonville AI Data Center Developer | HostDime data center originally slated for completion in 2020 but repeatedly delayed wftv.com (opens in a new tab) local outlet reported September 1, 2026 | site | 4 | 2026-11-06 |
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
The cities in Orange County on the record (2)
| City | Census GEOID | Projects |
|---|---|---|
| Orlando | 1253000 | |
| Eatonville | 1219650 |
A city without a record is listed, not linked.
What Orange County has decided 1 body, 1 decision on the record
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Orange County | county | not rated | Orange County commissioners voted in support of temporary moratorium on large data centers used for AI. wusf.org (opens in a new tab) local outlet Reported Sep 161 act on this rowEvery act on the Orange County row
| 1 | 2026-09-16 |
Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.
July 3, 2026 Orlando, FL Florida's new AI data center law takes effect amid ongoing concerns across party lines
WESH 2 News report on Orange County Legislative Delegation and community proceedings in Orlando, FL: Florida's new AI data center law takes effect amid ongoing concerns across party lines (July 3, 2026).
- WESH 2 News Broadcast Report Broadcast Report transcribed from local broadcast report
"There’s agreement across party lines in florida. I think that there is no law that can go strong enough against data centers. The new data center law, signed by governor ron desantis that went into effect wednesday, isn’t perfect. Ultimately, this was about having no data center regulations, or at least some protections for consumers. Under this new law, big tech companies have to foot the bill for these centers are the engines of the AI boom ratepayers and consumers like you and me will not have to"
- WESH 2 News Broadcast Report Broadcast Report transcribed from local broadcast report
"Front the cost of any of these data centers, which have really impacted energy bills for consumers in other states. Orange County democrat carlos guillermo smith voted yes, along with 31 other state senators after, in his opinion, the florida house weakened the bill. He says lawmakers in future sessions need to address transparency around the proliferation of data centers. Earlier versions of this bill would have prohibited local governments from signing non disclosure agreements with data center companies, which was a transparency measure that"
- Resident public comment Resident Public Comment transcribed from local broadcast report
"Expanding data center will impact their communities. Power, water and noise levels. This one developed and operated by host. Time isn’t for artificial intelligence, but rather it supports data storage and servers in lake county, commissioners there have already moved to create a one year moratorium. While more research is done on how data centers could impact electricity and water usage. We have beautiful rural areas, and we have these awesome small downtowns."
Using this data in a report? Support the record.
The rules across Florida · Report missing data or a local act
What happened
-
MoratoriumOrange County
wusf.org (opens in a new tab) local outlet -
Now proposedEatonville Wymore Road AI Data Center Proposal
wftv.com (opens in a new tab) local outlet
Nearby places with records
Distances run between the centers the Census Bureau gives each place. Every Florida county.
Disclosed figures
24 MW power
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 24 MW | 2 | 1 | 2 the developer's figure |
| Water, stated per day | 0 | 3 | ||
| Water, stated per year | 0 | 3 | ||
| Permanent jobs | 0 | 3 | ||
| Tax each year | 0 | 3 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 3 | 24 MW |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 3 tracked facilities in Orange County are for.
How the facilities are cooled
No source on file states how any of the 3 tracked facilities in Orange County are cooled.
About this data
Report a correction · Send a tip about Orange County · The rows here are part of the Florida export.
Cite this page
Data Center Record, "Data center records in Orange County, Florida", https://datacenterrecord.org/states/fl/orange-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
For researchers
- Level
- county
- Census GEOID
- 12095
- Census geography
- County, Orange County
- Rating
- Not rated