Last verified: · 3 primary and 53 reporting sources
● Being BuiltAnnounced October 23, 2025 · 4 Buildings · Vantage Data Centers
Vantage Port Washington Data Center Campus
Street addressLake Drive and Dixie Road, Port Washington, WI 53074, Ozaukee Countyverified addressExact, at the address [4] vantage-dc.com
Overview, regulatory gates and specifications
Vantage Data Centers is constructing a 4 building, 902 MW hyperscale data center campus on a 672 acre site in Port Washington, Ozaukee County, Wisconsin. [10] Ozaukee County Distribution Interconnection Project filed with PSC [20]
✓1. Land & Parcel
Parcel located
✓2. Local Zoning
Zoning approved
○3. Tax & EDA Deal
Not yet on file
✓4. Utility Grid Queue
902 MW disclosed
○5. Air & Water Permits
Not yet on file
What happens next:Campus is under construction; building inspections, utility energization and air permits are monitored.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Key specifications on the record
Power capacity
902 MWdeveloper figureEquivalent to the continuous electricity demand of about 748,700 average U.S. homes based on U.S. Energy Information Administration residential consumption data.About 9 percent of New York City's summer peak demand in 2024.
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Who is connected to this project
Connected government officials, corporate entities, utilities and local rules on the public record.
WL
Wisconsin Institute for Law and Liberty
Public Record Speaker
DID Recorded statement at The Center Square (September 17, 2026) [19]
SAIDWisconsin Institute for Law and Liberty argued that transmission line plans would destroy the landscape that shaped Tom Uttech's artistic career (September 17, 2026) [19]
SS
Summer Strand
Wisconsin Public Service Commission Chair
DID Recorded statement at VernonReporter (September 16, 2026) [18]
SAIDSummer Strand, PSC Chair, stated the decision was not opposition to data centers but rather that the application represented a cautionary tale of unrealistic speed to power expectations colliding with a deliberative regulatory process. (September 16, 2026) [18]
BC
Brendan Conway
We Energies spokesperson
DID Recorded statement at Milwaukee Journal Sentinel (September 16, 2026)
SAIDBrendan Conway, We Energies spokesperson, said the power line project is a critical part of delivering generation to the data center (September 16, 2026) jsonline.com (opens in a new tab)
PR
Port Washington residents
Public Record Speaker
DID Recorded statement at Urban Milwaukee (September 11, 2026) [17]
SAIDResidents complained about construction mentioning noise and light pollution (September 11, 2026) [17]
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Technical specification and permit ledger
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Vantage Port Washington Data Center Campus.
Water useA state water right filing or a water supply agreement.
Who would use itA lease announcement or a tenant named in a filing.
Hearings and statements on the record
September 10, 2026Port Washington, WIPort Washington Common Council Cloverleaf AI Data Center Community HearingPort Washington Common Council3 clips
On September 10, 2026, Port Washington residents and officials scrutinized developers of the proposed 1,900 acre, multi gigawatt Cloverleaf AI data center campus over Lake Michigan cooling water withdrawals, We Energies transmission infrastructure, and farmland annexation.
Ted Neitzke, Mayor, City of Port WashingtonElected Officialtranscribed from local broadcast report
"high ranking executives from Vantage Data Centers, the company that is building that massive complex, as well as Oracle, one of two companies that will operate some of those four data centers, were here tonight to connect with the community. They said that this has been part of their community engagement plan all along. Though, as you mentioned, the timing to this open style house of meeting tonight is"
Resident public commentResident Public Commenttranscribed from local broadcast report
"progress made on this complex, which is known as Project Lighthouse, just west, again, of I-43 here in Port Washington. When it is done, the $15 billion project will have four data centers covering 2 and 1/2 million square feet. They'll be operated by Oracle and OpenAI with 1,000 permanent jobs. Now, just this week, a former OpenAI researcher accused the company of recklessly racing towards"
FOX6 News Milwaukee Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"trying to prove they will not hurt this community. Not all data centers are equal. We want to be part of the community. This is not just a construction project and temporary. We will be here for many, many years. And so, we're excited to be part of the community of Port Washington. It's part of being a good neighbor, and by my definition, responsible data center building is"
March 20, 2026Port Washington, WIPort Washington limiting outdoor construction at data center sitePort Washington Plan Commission2 clips
WISN 12 News report on Port Washington Plan Commission and community proceedings in Port Washington, WI: Port Washington limiting outdoor construction at data center site (March 20, 2026).
WISN 12 News Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"Neighbors of the new data center making their outrage known at a thursday planning commission meeting. Like kirk day. Heck. I’ve been here before. Who I spoke with over the phone friday. The backup beeper bells, the tracked equipment, the tailgates on quad axles, ground vibrations. The city says it listed voting to limit the hours of outdoor construction. We now lay down much clearer expectations for what it."
WISN 12 News Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"During the week, the board voted unanimously for this construction change, but it’s a change that does not go into effect for several weeks. 24 hour construction is still allowed here until april 18th. You can’t stop a project of this magnitude overnight. It takes a wind down period of time, and we felt it was a really good compromise. Is there any regret allowing the 24 hour construction? Oh boy, that’s a with the 24 hour construction, had we known the volume of traffic, etc., we."
Ted Neitzke & Cloverleaf Infrastructure RepresentativesMayor of Port Washington & Project Developer
Venue:Port Washington Common Council Concept Briefing on Cloverleaf Campus
"Described the proposed Port Washington AI data center campus as a clean technology tax base investment compatible with municipal utility infrastructure."
Column B · Primary Government Record
Port Washington 1,900 Acre Farmland Annexation & We Energies Multi Gigawatt Load Filing
Port Washington Annexation & Utility Review (Sept 10, 2026 Hearing)
Agency or Venue:Port Washington Common Council & Public Service Commission of Wisconsin
"Municipal annexation and utility filings documented a 1,900 acre footprint requiring multi gigawatt We Energies transmission upgrades and Lake Michigan cooling water withdrawals, prompting intense resident opposition on September 10, 2026."
Filing (source date; the content gives no date of its own)
American Transmission Company refiled a grid upgrade application on Monday, September 16, 2026 for infrastructure to serve the Port Washington data center.
(source date; the content gives no date of its own)
Vantage Data Centers, Oracle and OpenAI are building a $15 billion data center campus called Lighthouse in Port Washington on 672 acres next to Interstate 43
(source date; the content gives no date of its own)
ATC's project includes new power lines, rebuilding existing power lines, building up to five new substations, and maintenance on existing power lines for the Port Washington AI data center
· stalled (source date; the content gives no date of its own)
Public Service Commission of Wisconsin revoked American Transmission Company's completeness determination for the Ozaukee County Distribution Interconnection Project on August 6, 2026
A Vantage data center in Port Washington faces disputes over energy cost allocation, a state regulatory rejection of its power line project, and an environmental lawsuit filed against the Wisconsin DNR over the project's environmental review.
(source date; the content gives no date of its own)
The campus will have four data center buildings, two measuring about 1,800 by 400 feet (560,000 and 725,000 square feet respectively), about 27 feet tall
(source date; the content gives no date of its own)
Construction on the Vantage Data Centers Lighthouse Campus was originally limited to a 12 hour period but the city later approved 24 hour construction on weekdays.
(source date; the content gives no date of its own)
Vantage Data Centers is underwriting 100 percent of the power infrastructure investment with a dedicated electricity rate from WEC Energy Group utility We Energies
OpenAI, Oracle, and Vantage announced the Stargate data center campus in Port Washington with close to one gigawatt of AI capacity, expecting to create over 4,000 construction jobs and scheduled for completion in 2028.
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
Speaker read again from the statement's source line, "Pastor Patti Plough, Responsible Energy Alliance": the title in front of the name (Pastor) is the role, not part of the name.
Speaker read again from the statement's source line, "Pastor Patti Plough, Responsible Energy Alliance": the title in front of the name (Pastor) is the role, not part of the name.
Speaker read again from the statement's source line, "Sheriff Christy Knowles": the title in front of the name (Sheriff) is the role, not part of the name.
Speaker read again from the statement's source line, "Sheriff Christy Knowles": the title in front of the name (Sheriff) is the role, not part of the name.
Speaker read again from the statement's source line, "Sheriff Christy Knowles": the title in front of the name (Sheriff) is the role, not part of the name.
5.4 GW, wpr.org: Environmental groups say data centers are driving construction of 5.4 gigawatts of new or updated gas fired power plants
3.5 GW, wpr.org: Roughly 670 acre campus could need up to 3.5 gigawatts of electricity
3.5 GW, wpr.org: The project could require up to 3.5 gigawatts of electricity in the future
3 GW, wpr.org: We Energies proposing to add almost 3 gigawatts of power to meet data center energy demand
2,000 MW, TMJ4 News: Vantage says it is paying for the buildout of 2,000 megawatts of energy
1,400 MW, TMJ4 News: The Port Washington facility will require 1,400 megawatts of power
1.3 GW, Milwaukee Business News: Expected power use is 1.3 gigawatts with later phases potentially up to 3.5 gigawatts
1.3 GW, Ozaukee Press: 1.3 gigawatts of power capacity for Lighthouse Campus
1.3 GW, wpr.org: The first phase of the project would use 1.3 gigawatts of energy, enough to power 640,000 homes
902 MW, Spectrum News: Vantage Data Centers Lighthouse Campus in Port Washington will have four data centers totaling 902 megawatts of critical IT load
902 MW, YouTube: Critical IT load capacity planned for the Port Washington campus is 902 MW.
902 MW, YouTube: Critical IT load for the Port Washington campus is 902 megawatts.
5,000 workers, Ozaukee Press: Project expected to have 5,000 workers at peak
5,000 workers, Ozaukee Press: Workforce expected to reach 5,000 going into winter
5,000 workers, Ozaukee Press: Vantage Data Centers Lighthouse Campus workforce increased to approximately 5,000 workers in summer 2026
4,000 jobs, wpr.org: Data center campus could create more than 4,000 construction jobs and more than 1,000 permanent positions
4,000 jobs, Urban Milwaukee: 4,000 construction workers are working on the project and 1,000 permanent jobs will be at the campus once it is operational
1,700 workers, Ozaukee Press: Approximately 1,700 workers on site at time of ceremony
1,000 jobs, YouTube: The project brings 1,000 operations jobs.
1,000 jobs, TMJ4 News: Expected to create approximately 1,000 operational jobs
1,000 jobs, YouTube: The project will create 1,000 permanent jobs
1,000 jobs, YouTube: The project will feature four data centers employing nearly 1,000 people once operational
1,000 jobs, TMJ4 News: Vantage expects 1,000 employees on site at Port Washington facility when combined with customers Oracle and OpenAI
1,000 jobs, YouTube: Expected on site workforce at the Port Washington campus including customers is 1,000 employees.
1,000 jobs, TMJ4 News: Vantage expects a combined 1,000 employees with its two biggest customers once the Port Washington facility opens.
1,000 jobs, Wisconsin Public Radio: 1,000 permanent jobs will be at the campus once operational
1,000 jobs, WLUK: Project Lighthouse is expected to provide 1,000 permanent jobs
700 jobs, wpr.org: OpenAI and Oracle will have around 700 jobs at campus, with Vantage having around 330 employees
700 jobs, YouTube: Around 700 workers are currently working on the site during ground preparation
500 workers, Ozaukee Press: Approximately 500 workers on site causing traffic problems
300 jobs, Milwaukee Business News: Vantage plans to employ about 300 people at the data center, with tenant companies expected to employ an additional 700
200 workers, Milwaukee Business News: Expected to create thousands of construction jobs, with about 200 workers in 2025, 3,500 in 2026, 5,000 in 2027, and 2,000 in 2028
1,500,000,000 USD, thecentersquare.com: Data centers are beneficiary of estimated $1.5 billion in initial foregone state sales tax from four data center projects
458,000,000 USD, wpr.org: The TID provides property tax reimbursement and interest payments to the developer totaling more than $458 million over the next 18 years.
458,000,000 USD, TMJ4 News: Vantage will pay property taxes in Port Washington over the next 20 years through a Tax Incremental District to cover $458 million in infrastructure costs for the project.
458,000,000 USD, WPR: The suit argued the TID would lead to the city issuing more than $458 million in property tax reimbursement and interest payments to the developer over 18 years
120,000,000 dollars, YouTube: Property taxes will be paid on 120 million dollars of land value starting in 2027
30,000,000 USD, wpr.org: If the project delivers on the property value increases estimated in the city's project plan, Port Washington and other local taxing authorities would see an increase of more than $30 million annually in tax revenue from the project.
Common questions about Vantage Port Washington Data Center Campus
Answered directly from the verified filings and local actions on this page.
Who is building Vantage Port Washington Data Center Campus?
Vantage Data Centers is the developer. No construction contractor is named on the record yet.
Who will use Vantage Port Washington Data Center Campus?
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
How much power and water does Vantage Port Washington Data Center Campus say it needs?
What is still unknown about Vantage Port Washington Data Center Campus?
Not disclosed by any source on file: how much water it would use, how loud it would be, tax it would pay each year, who is constructing it, how much land, where its power comes from, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
Sources
Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.
Tracked project domains
Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Cite this page
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Vantage Port Washington Data Center Campus. Last verified November 6, 2026. https://datacenterrecord.org/projects/vantage-port-washington-data-center-wi. Accessed November 22, 2026.
Get this data
Every row on this page is available to download with its source, its basis and the date it was last verified.
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Use this data in your work
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Reporters, researchers and nonprofits: free to use and republish with attribution under CC BY-NC 4.0. If you are working on a story or a study and want the full state or national file, ask and we will send it.
Utilities, law firms, lenders, consultants and AI teams: commercial use, bulk feeds and API access require a commercial license. Revenue from commercial licenses pays for the public record so it stays free for residents and local governments.
States, counties and cities: a public agency can use the record free, link to it, or contact us for an embed or feed of the records in its jurisdiction. Agencies that keep their own permit tracker can send us their rows and we will link each one to the primary document and keep the history. Contact us.
Request data or a license
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Keep the record open
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
FiguresEach figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
LicenseData CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this pageData Center Record, "Vantage Port Washington Data Center Campus", https://datacenterrecord.org/projects/vantage-port-washington-data-center-wi, last verified November 6, 2026.CSV · JSON
Data Center Record, "Vantage Port Washington Data Center Campus", https://datacenterrecord.org/projects/vantage-port-washington-data-center-wi. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
City of Port Washington annexation and Vantage campus plan
Location last verified
September 16, 2026
How capacity was disclosed
the developer's figure
Interconnection
Connection agreement signed
Capacity, if disclosed
902 MW, the developer's figure
Published
September 5, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Rating of the county's rows
Researcher view · Vantage Port Washington Data Center Campus · 56 sources, 115 entries · basis and source tier on every row · verified November 6, 2026