WIPort Washington Common CouncilSeptember 10, 2026
Port Washington Common Council Cloverleaf AI Data Center Community Hearing
On September 10, 2026, Port Washington residents and officials scrutinized developers of the proposed 1,900 acre, multi gigawatt Cloverleaf AI data center campus over Lake Michigan cooling water withdrawals, We Energies transmission infrastructure, and farmland annexation.
Privacy enhanced player · zero third party requests until clicked
Port Washington Common Council Cloverleaf AI Data Center Community Hearing
Port Washington Common Council · September 10, 2026
Timestamped Speaker & Testimony Ledger
3 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.
Clip 1 · 0:27Ted Neitzke, Mayor, City of Port WashingtonElected OfficialIn supporttranscribed from the official recording
WaterPower & GridZoning
Port Washington residents and officials question developers of the proposed multi gigawatt Port Washington AI data center campus.
"high ranking executives from Vantage Data Centers, the company that is building that massive complex, as well as Oracle, one of two companies that will operate some of those four data centers, were here tonight to connect with the community. They said that this has been part of their community engagement plan all along. Though, as you mentioned, the timing to this open style house of meeting tonight is"
Clip 2 · 1:00Resident public commentResident Public Commenttranscribed from the official recording
Residents and community speakers address Port Washington Common Council regarding local water, power grid, noise, and zoning impacts.
"progress made on this complex, which is known as Project Lighthouse, just west, again, of I-43 here in Port Washington. When it is done, the $15 billion project will have four data centers covering 2 and 1/2 million square feet. They'll be operated by Oracle and OpenAI with 1,000 permanent jobs. Now, just this week, a former OpenAI researcher accused the company of recklessly racing towards"
Clip 3 · 1:31Port Washington Common Council MemberElected OfficialQuestioningtranscribed from the official recording
WaterPower & GridZoning
Port Washington Common Council members deliberate on municipal siting standards, utility capacity, and the recorded ordinance action.
"trying to prove they will not hurt this community. >> Not all data centers are equal. We want to be part of the community. This is not just a construction project and temporary. We will be here for many, many years. And so, we're excited to be part of the community of Port Washington. >> It's part of being a good neighbor, and by my definition, responsible data center building is"
Ted Neitzke & Cloverleaf Infrastructure RepresentativesMayor of Port Washington & Project Developer
Venue:Port Washington Common Council Concept Briefing on Cloverleaf Campus
"Described the proposed Port Washington AI data center campus as a clean technology tax base investment compatible with municipal utility infrastructure."
Column B · Primary Government Record
Port Washington 1,900 Acre Farmland Annexation & We Energies Multi Gigawatt Load Filing
Port Washington Annexation & Utility Review (Sept 10, 2026 Hearing)
Agency or Venue:Port Washington Common Council & Public Service Commission of Wisconsin
"Municipal annexation and utility filings documented a 1,900 acre footprint requiring multi gigawatt We Energies transmission upgrades and Lake Michigan cooling water withdrawals, prompting intense resident opposition on September 10, 2026."