Data Center Record.
● 1 Facility on Record 1 local rule row · 902 MW disclosed

Data centers in Ozaukee County, Wisconsin

Ozaukee County has 1 data center on the record; it is being built. Ozaukee County has a scorecard row with no rating yet. The latest decision on the record: Judge Adam Gerol dismissed Great Lakes Neighbors' lawsuit challenging the tax incremental district, September 22, 2026.

The data center in Ozaukee County

Every Ozaukee County record 1 record · blank cell: not disclosed · sort by any column

Facility and county Stage Operator Power (MW) Latest entry Basis Located Tier Verified
Vantage Port Washington Data Center Campus Port Washington, Ozaukee County Being built Vantage Data Centers 902 Ozaukee County Distribution Interconnection Project filed with PSC wpr.org (opens in a new tab) local outlet reported September 18, 2026 the developer's figure site 1 2026-11-06

Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.

The cities in Ozaukee County on the record (1)

1 of 1 city has a record. A city without one is listed, not linked, until its first published record. No city in Ozaukee County has a rule, a statement by an official or a rating on the record yet.

CityCensus GEOIDProjects
Port Washington55644501

A city without a record is listed, not linked.

What Ozaukee County has decided 1 body, 4 decisions on the record

What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement one tap away, newest first, with its source.

BodyLevelRatingIn force untilLatest actActsVerified
Ozaukee Countycountynot ratedAn ordinance passed by Port Washington voters would require future tax incremental districts with project costs or a base value of at least $10 million to receive approval from voters before they can move forward. wpr.org (opens in a new tab) local outlet Reported Sep 224 acts on this row
Every act on the Ozaukee County row
  1. ordinance

    An ordinance passed by Port Washington voters would require future tax incremental districts with project costs or a base value of at least $10 million to receive approval from voters before they can move forward

    wpr.org (opens in a new tab) local outlet

  2. approval

    Port Washington voters approved a referendum giving them more say over future development incentives, with roughly two-thirds in favor

    wpr.org (opens in a new tab) local outlet

Last verified September 22, 2026.

42026-09-22

Reported: the source's date; the item names no day of its own. A rating rests only on a binding act in force; "not rated" means no person has set one. Blank cell: no end date or count on the record for that column.

September 10, 2026 Port Washington, WI Port Washington Common Council Cloverleaf AI Data Center Community Hearing Port Washington Common Council 3 clips

On September 10, 2026, Port Washington residents and officials scrutinized developers of the proposed 1,900 acre, multi gigawatt Cloverleaf AI data center campus over Lake Michigan cooling water withdrawals, We Energies transmission infrastructure, and farmland annexation.

  1. Ted Neitzke, Mayor, City of Port Washington Elected Official transcribed from local broadcast report
    "high ranking executives from Vantage Data Centers, the company that is building that massive complex, as well as Oracle, one of two companies that will operate some of those four data centers, were here tonight to connect with the community. They said that this has been part of their community engagement plan all along. Though, as you mentioned, the timing to this open style house of meeting tonight is"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "progress made on this complex, which is known as Project Lighthouse, just west, again, of I-43 here in Port Washington. When it is done, the $15 billion project will have four data centers covering 2 and 1/2 million square feet. They'll be operated by Oracle and OpenAI with 1,000 permanent jobs. Now, just this week, a former OpenAI researcher accused the company of recklessly racing towards"
  3. FOX6 News Milwaukee Broadcast Report Broadcast Report transcribed from local broadcast report
    "trying to prove they will not hurt this community. Not all data centers are equal. We want to be part of the community. This is not just a construction project and temporary. We will be here for many, many years. And so, we're excited to be part of the community of Port Washington. It's part of being a good neighbor, and by my definition, responsible data center building is"
March 20, 2026 Port Washington, WI Port Washington limiting outdoor construction at data center site Port Washington Plan Commission 2 clips

WISN 12 News report on Port Washington Plan Commission and community proceedings in Port Washington, WI: Port Washington limiting outdoor construction at data center site (March 20, 2026).

  1. WISN 12 News Broadcast Report Broadcast Report transcribed from local broadcast report
    "Neighbors of the new data center making their outrage known at a thursday planning commission meeting. Like kirk day. Heck. I’ve been here before. Who I spoke with over the phone friday. The backup beeper bells, the tracked equipment, the tailgates on quad axles, ground vibrations. The city says it listed voting to limit the hours of outdoor construction. We now lay down much clearer expectations for what it."
  2. WISN 12 News Broadcast Report Broadcast Report transcribed from local broadcast report
    "During the week, the board voted unanimously for this construction change, but it’s a change that does not go into effect for several weeks. 24 hour construction is still allowed here until april 18th. You can’t stop a project of this magnitude overnight. It takes a wind down period of time, and we felt it was a really good compromise. Is there any regret allowing the 24 hour construction? Oh boy, that’s a with the 24 hour construction, had we known the volume of traffic, etc., we."
Said and filed

Said and filed

Statements and filings, side by side

Water Power & Grid land_use Zoning
Column A · Dated Statement
Ted Neitzke & Cloverleaf Infrastructure Representatives Mayor of Port Washington & Project Developer
Venue: Port Washington Common Council Concept Briefing on Cloverleaf Campus
"Described the proposed Port Washington AI data center campus as a clean technology tax base investment compatible with municipal utility infrastructure."
Column B · Primary Government Record
Port Washington 1,900 Acre Farmland Annexation & We Energies Multi Gigawatt Load Filing
Port Washington Annexation & Utility Review (Sept 10, 2026 Hearing)
Agency or Venue: Port Washington Common Council & Public Service Commission of Wisconsin
"Municipal annexation and utility filings documented a 1,900 acre footprint requiring multi gigawatt We Energies transmission upgrades and Lake Michigan cooling water withdrawals, prompting intense resident opposition on September 10, 2026."
FOX6 News Milwaukee

The rules across Wisconsin · Report missing data or a local act

What happened

  1. Broke groundVantage Port Washington Data Center Campus

    Construction continues on Vantage Data Centers' AI data center campus project in Port Washington, Wisconsin as of August 6, 2026

Wisconsin, year by year

What was said

Wisconsin Institute for Law and Liberty argued that transmission line plans would destroy the landscape that shaped Tom Uttech's artistic career
Wisconsin Institute for Law and Liberty · September 17, 2026 · paraphrased · The Center Square (opens in a new tab) local outlet
Summer Strand, PSC Chair, stated the decision was not opposition to data centers but rather that the application represented a cautionary tale of unrealistic speed to power expectations colliding with a deliberative regulatory process.
Summer Strand, Wisconsin Public Service Commission Chair · September 16, 2026 · paraphrased · VernonReporter (opens in a new tab) news outlet
Brendan Conway, We Energies spokesperson, said the power line project is a critical part of delivering generation to the data center
Brendan Conway, We Energies spokesperson · September 16, 2026 · paraphrased · Milwaukee Journal Sentinel (opens in a new tab) local outlet
Pastor Patti Plough of Responsible Energy Alliance celebrated the PSC decision
Patti Plough, Pastor, Responsible Energy Alliance · August 6, 2026 · paraphrased · WISN (opens in a new tab) local outlet

View all 66 Wisconsin statements on the record →

62 more on this page, one per speaker and claim; 66 statements in all

Haley Dobre, Pier Street Development, said job growth from the $15 billion data center complex north of downtown has increased demand for housing

Pier Street Development developer TMJ4 News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: TMJ4 News (opens in a new tab).

ATC filed numerous substantial changes to its project application during the proceedings, which led to the revocation

Public Service Commission of Wisconsin WLUK (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WLUK (opens in a new tab).

Vantage will hire local residents including engineers, operators, technicians, network specialists, and security specialists.

Dana Adams, Vantage North America president YouTube (opens in a new tab) video project record
· Dana Adams · YouTube · July 28, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

The rooftop cooling system is relatively quiet by industry standards because much of the sound vectors upwards.

Ryan Kehoe, Vantage VP of operations YouTube (opens in a new tab) video project record
· Ryan Kehoe · YouTube · July 28, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Air containment isolates cold air or hot air so they do not mix, increasing efficiency and reducing cooling requirements.

Dana Adams, Vantage North America president YouTube (opens in a new tab) video project record
· Dana Adams · YouTube · July 28, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

The closed loop chilled water system requires only a one time fill of water.

Ryan Kehoe, Vantage VP of operations YouTube (opens in a new tab) video project record
· Ryan Kehoe · YouTube · July 28, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

On Sept. 23, a Vantage official texted Port Washington Mayor Ted Neitzke about the governor's office seeking more information on why an EIS would kill the project

Vantage official (unnamed) wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

Wisconsin Public Service Commissioner Kristy Nieto said Wisconsin customers should not pay to subsidize data center service

Wisconsin Public Service Commission commissioner TMJ4 News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: TMJ4 News (opens in a new tab).

Vantage said backup generators are intended for emergencies and required testing and maintenance, running monthly with no more than four generators for 15 minutes, annually one at a time for an hour, and for 15 minutes to validate repairs

Mark Freeman, Vantage Data Centers Vice President of Global Marketing Spectrum News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Spectrum News (opens in a new tab).

Patti Plough, Fredonia neighbor, leading opposition group against power lines routing through communities

Fredonia neighbor and Responsible Energy Alliance advocate TMJ4 News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: TMJ4 News (opens in a new tab).

Vantage said generators will primarily be used one or a few at a time during monthly testing, well below DNR's established limit of 50 hours per generator annually

Vantage Data Centers TMJ4 News (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: TMJ4 News (opens in a new tab).

The data center uses a closed loop cooling system that circulates water like a car radiator

Ted Neitzke, Mayor of Port Washington YouTube (opens in a new tab) video project record
· Ted Neitzke · YouTube · April 16, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Data centers do not discharge like manufacturing plants and do not require clean air credits or significant discharge permitting

Ted Neitzke, Mayor of Port Washington YouTube (opens in a new tab) video project record
· Ted Neitzke · YouTube · April 16, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Mark Freeman, Vice President of Global Marketing for Vantage Data Centers, said the company is committed to working with the city on construction alignment

Vice President of Global Marketing, Vantage Data Centers wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

The data center buildings are being constructed concurrently

Edwin Van Velzen, Sr. Vice President for Construction, Vantage Data Centers YouTube (opens in a new tab) video project record
· Edwin Van Velzen · YouTube · February 25, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Business groups argue ordinance conflicts with state law delegating TID authority to municipal governing bodies

Dale Kooyenga, President, Metropolitan Milwaukee Association of Commerce wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

No water will be directly piped from Lake Michigan for the Lighthouse Campus.

Emily Backus, Sustainability Director, North America YouTube (opens in a new tab) video project record
· Emily Backus · YouTube · January 9, 2026 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

The group is concerned about the data center's expected 1.3 gigawatt electricity draw and its effect on local utility rates

Mike Beaster, Great Lakes Neighbors United wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

According to the recall group, the mayor has been secretive about the data center details and hasn't taken residents' concerns seriously

Mike Beaster, Great Lakes Neighbors United wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

The Vantage Data Centers Lighthouse Campus is being built using Wisconsin's clean renewable energy without increasing rates on residents.

unnamed narrator YouTube (opens in a new tab) video project record
· unnamed narrator · YouTube · November 18, 2025 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Mayor Ted Neitzke said Vantage is putting all capital up front for infrastructure, city pays them back from TID revenues

Ted Neitzke IV, Port Washington Mayor wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

Scott L., resident, said the council should vote against the TID creation and invest in people and local businesses instead

Port Washington resident wpr.org (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wpr.org (opens in a new tab).

In 2019, Vantage made a company decision to no longer use evaporative cooling systems in its data center design.

unnamed Vantage Data Centers representative YouTube (opens in a new tab) video project record
· unnamed Vantage Data Centers representative · YouTube · October 16, 2025 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

The data center will not draw water directly from the lake, but will obtain water through existing Port Washington infrastructure.

unnamed Vantage Data Centers representative YouTube (opens in a new tab) video project record
· unnamed Vantage Data Centers representative · YouTube · October 16, 2025 · Privacy enhanced player · loads on click
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: YouTube (opens in a new tab).

Nearby places with records

21 miles away Washington County: 1 data center on the record.
40 miles away Milwaukee County: 5 data centers on the record.
43 miles away Dodge County: 1 data center on the record.
43 miles away Calumet County: 1 data center on the record.

Distances run between the centers the Census Bureau gives each place. Every Wisconsin county.

Disclosed figures

902 MW power, 1,000 jobs

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedWithout a figureBasis
Power902 MW101 the developer's figure
Water, stated per day01
Water, stated per year01
Permanent jobs1,000 jobs101 the developer's figure
Tax each year01

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
No stated use1902 MW1,000 jobs

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 1 tracked facility in Ozaukee County is for.

How the facilities are cooled

No source on file states how any of the 1 tracked facility in Ozaukee County is cooled.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Ozaukee County, Wisconsin", https://datacenterrecord.org/states/wi/ozaukee-county, updated November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Data center records in Ozaukee County, Wisconsin", https://datacenterrecord.org/states/wi/ozaukee-county. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Level
county
Census GEOID
55089
Census geography
County, Ozaukee County
Rating
Not rated

Researcher view · Ozaukee County, Wisconsin · 1 record, 1 rule row · Census GEOID 55089 · basis and source tier on every row · verified November 6, 2026