States / Wisconsin

Wisconsin, year by year.

Every act on the record for Wisconsin, on the day it happened, newest first by month. Under each month, one tap away, the background, plans and statements the same sources carried. The counts are the state hub's records; nothing is estimated.

The record by year

On the record as of October 27, 2026.

An act sits on the day it happened: the day its own sentence names, or the day its source gives for it. An act the record knows only from the date of the article that reported it sits under that article's month, one tap away, marked Reported with the article's date. So do background, plans and statements, which are not acts. The same act reported by several sources is one line with the reports behind it, on its day where any of them dates it. The milestones alone, for every state, are on the timeline.

47 acts on the line for Wisconsin, from 249 dated lines in the records' histories and the scorecard. 43 more acts are dated only by the article that reported them and sit under their month. 14 lines report an act already listed. 145 lines are background, plans or statements. 24 lines sit on a date other than the one they were filed under, because their own sentence names the day, the month or the year it happened; each says so. Where a line sits is read from its own words and the row is never changed (how dates are read).

Narrow the acts
Kind
Topic
Developer

Each count is the number of lines on this page the chip keeps. Topics are matched from the words of each line and are a finding aid, not a fact about the event.

2026 36 acts on the line from 49 reports; 43 reported, dated only by the article; 120 lines of background, plans and statements

October 2026 4 acts on the line from 5 reports

  1. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Common Council voted 7-0 to reject a conditional use permit for a hyper scale data center.

    waow.com (opens in a new tab), local outlet

    1 more report of this
    1. Oct 21 Wisconsin Rapids Common Council voted to deny conditional use permit for PNK Group data center on former paper mill site. wsaw.com (opens in a new tab)
  2. Moratorium adopted Wisconsin Rapids, Wisconsin

    Wisconsin Rapids enacted 12 month moratorium on data center construction with additional restrictions on future data centers.

    wsaw.com (opens in a new tab), local outlet

  3. proposed Microsoft Sturtevant Data Center, Sturtevant, Wisconsin

    Microsoft purchased 70 acres in Sturtevant, Racine County for $70 million and is considering building a data center adjacent to its operational Mount Pleasant facility.

    dailyreporter.com (opens in a new tab), local outlet

  4. Denial proposed PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Common Council voted unanimously to deny PNK Group's conditional use permit for a data center on Fourth Avenue North.

    yahoo.com (opens in a new tab), primary source

September 2026 9 acts on the line from 14 reports; 23 reported; 52 lines of background, plans and statements

  1. Moratorium adopted Janesville, Wisconsin

    The Janesville City Council unanimously passed a one year data center moratorium

    channel3000.com (opens in a new tab), news outlet

  2. Moratorium Milwaukee, Wisconsin

    Milwaukee City Plan Commission held public hearing and discussion on proposed one year moratorium on new data center developments

    wtmj.com (opens in a new tab), local outlet

  3. Litigation Ozaukee County, Wisconsin

    Judge Adam Gerol dismissed Great Lakes Neighbors' lawsuit challenging the tax incremental district

    wpr.org (opens in a new tab), local outlet

  4. Denial Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Planning Commission voted September 16 to deny both the conditional use permit and site plan application for PNK Group data center campus on former paper mill property along Fourth Avenue North.

    yahoo.com (opens in a new tab), national outlet

    5 more reports of this
    1. Reported September 17 Both votes were unanimous to deny the conditional use permit and site plan application. yahoo.com (opens in a new tab)
    2. Reported September 17 Wisconsin Rapids Planning Commission voted 7-0 to recommend denial of the permit application to redevelop old paper mill site into data center wsaw.com (opens in a new tab)
    3. Reported September 17 Wisconsin Rapids Planning Commission voted to recommend denial of the conditional use permit application for PNK Group data center at former Rapids mill site wjfw.com (opens in a new tab)
    4. Reported September 17 Wisconsin Rapids Planning Commission voted unanimously to deny PNK Group's conditional use permit reutersconnect.com (opens in a new tab)
    5. Reported September 17 Wisconsin Rapids Planning Commission voted 7-0 to deny recommendation of conditional use permit by PNK Group to construct a data center waow.com (opens in a new tab)
  5. Wisconsin Rapids, Wisconsin

    South Wood County Neighbors for Responsible Development held a data center education meeting on September 14, 2026

    waow.com (opens in a new tab), local outlet

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Companies behind Project Lighthouse held an open house on September 10, 2026

    fox11online.com (opens in a new tab), local outlet (the day its own sentence names; filed under Sep 11, 2026)

  7. Wisconsin Rapids, Wisconsin

    South Wood County Neighbors for Responsible Development held a public forum on hyperscale data centers at Lincoln High School Performing Arts Center on Monday at 6:30 PM

    wsau.com (opens in a new tab), local outlet (the weekday its sentence names, the last before the report; filed under Sep 13, 2026)

  8. Rate rule Wisconsin

    Alliant Energy submitted application September 4, 2026 to create a standard utility wide electric rate for large load customers of at least 100 megawatts, artificial intelligence data centers

    journaltimes.com (opens in a new tab), news outlet

  9. Filing reported PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Application from DC Rapids LLC for conditional use permit to construct data center

    wjfw.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Reported in September 2026, dated only by the article that carried them: 23 acts
  1. Denial PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Plan commission rejected PNK Group data center proposal after 4.5 months of vetting

    wsau.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Wisconsin

    Port Washington created a tax increment district (TID No. 5) to support a $15 billion data center campus being developed by Vantage Data Centers, OpenAI and Oracle.

    wislawjournal.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  3. Litigation Wisconsin

    Ozaukee County Circuit Court Judge Adam Gerol dismissed the lawsuit by Great Lakes Neighbors United challenging the tax increment district.

    wislawjournal.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  4. Litigation Port Washington, Wisconsin

    Ozaukee County judge dismissed lawsuit challenging Port Washington's tax incremental district (TID No. 5) supporting data center campus

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Referendum Port Washington, Wisconsin

    Port Washington voters approved referendum requiring future tax incremental districts with project costs or base value of at least $10 million receive voter approval before moving forward

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

    1 more report of this
    1. Reported September 23 Port Washington voters approved an ordinance requiring voter approval for certain future tax incremental districts. wislawjournal.com (opens in a new tab)
  6. Ozaukee County, Wisconsin

    Port Washington created tax incremental district TID No. 5 to support a data center campus being developed by Vantage Data Centers, OpenAI and Oracle

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  7. Approval Ozaukee County, Wisconsin

    Port Washington voters approved a referendum giving them more say over future development incentives, with roughly two-thirds in favor

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  8. Ordinance Ozaukee County, Wisconsin

    An ordinance passed by Port Washington voters would require future tax incremental districts with project costs or a base value of at least $10 million to receive approval from voters before they can move forward

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  9. Denial Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Plan Commission unanimously recommended denying the conditional use permit for the proposed data center at the former paper mill site.

    wtmj.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  10. Filing Vantage Port Washington Data Center, Port Washington, Wisconsin

    Ozaukee County Distribution Interconnection Project filed with PSC

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  11. Rate rule Wisconsin

    Public Service Commission ordered Alliant to return with a standard rate for all future large data centers

    journaltimes.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  12. Filing Vantage Port Washington Data Center, Port Washington, Wisconsin

    American Transmission Co. application removed artist Tom Uttech's property from its proposed routes

    wjfw.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  13. Wisconsin

    Wisconsin introduced SB 1061 and AB 1099 to prohibit data centers until 14 conditions met; bill failed.

    mashable.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  14. Moratorium Tigerton, Wisconsin

    Public hearing on data center moratorium held in Tigerton with residents raising concerns about wildlife impacts and noise pollution

    wsau.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  15. Wisconsin Rapids, Wisconsin

    A public meeting was held in Wisconsin Rapids regarding impacts of a possible data center.

    wsaw.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  16. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Microsoft has proposed a data center development in Kenosha

    urbanmilwaukee.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  17. Wisconsin

    Wisconsin state legislature adopted sales tax exemption for data centers estimated to cost the state more than $2 billion

    capitalandmain.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  18. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    PNK Group hosted series of four webinars and will host open house event on September 13, 2026.

    wisconsinrapidstribune.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  19. Wisconsin

    Local officials in at least four Wisconsin communities,Beaver Dam, Kenosha, Janesville and Menomonie,signed NDAs tied to major data center proposals

    newsweek.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  20. Moratorium adopted Sun Prairie, Wisconsin

    Sun Prairie City Council unanimously approved a one year moratorium on new or expanded data centers larger than 10,000 square feet, unless an accessory use to an existing business, effective September 1

    hngnews.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  21. Moratorium Milton, Wisconsin

    City of Milton implemented an 18 month moratorium on data centers

    hngnews.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  22. Vantage Port Washington Data Center, Port Washington, Wisconsin

    County Highway LL was fully closed for months for the water and sewer project before being resurfaced

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  23. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Fire hydrants were installed as part of a city infrastructure project to extend water and sewer service to the data center complex

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for September 2026, not acts of their own: 52 lines of background, plans and statements
  1. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids planning commission votes 7-0 to deny conditional use permit for data center

    waow.com (opens in a new tab) (a description, not an act)

  2. Wisconsin Rapids, Wisconsin

    Application had 33 shortcomings identified by the city

    wsaw.com (opens in a new tab) (a description, not an act)

  3. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids is currently drafting a data center moratorium after a vote last month

    wsaw.com (opens in a new tab) (a description, not an act)

  4. Wisconsin Rapids, Wisconsin

    Matter will be taken up for action at a future common council meeting, not yet scheduled

    wsaw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Wisconsin Rapids, Wisconsin

    Planning commission vote was 7-0 to recommend denial

    wjfw.com (opens in a new tab) (no act in the sentence)

  6. Wisconsin Rapids, Wisconsin

    City of Wisconsin Rapids has scheduled a public hearing for a moratorium on data center development for October 5

    wjfw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Meta Beaver Dam Data Center, Beaver Dam, Wisconsin

    Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027

    journaltimes.com (opens in a new tab) (a description, not an act)

  8. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Tom Uttech's property is 52 acres

    wjfw.com (opens in a new tab) (a description, not an act)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    A transmission line to power the Port Washington data center is no longer planned to run through artist Tom Uttech's property

    wjfw.com (opens in a new tab) (a description, not an act)

  10. Wisconsin Rapids, Wisconsin

    DC Rapids LLC is seeking a Conditional Use Permit to construct a data center facility at 950 Fourth Ave. N., the former papermill site in Wisconsin Rapids.

    wsaw.com (opens in a new tab) (a description, not an act)

  11. Wisconsin Rapids, Wisconsin

    The Wisconsin Rapids Planning Commission public hearing on the conditional use permit is scheduled for Wednesday, September 16, 2026, at 5:30 p.m.

    wsaw.com (opens in a new tab) (a description, not an act)

  12. Wisconsin

    Wisconsin should establish statewide standards for data center development including cost accountability, transparency, water and farmland protection, clean energy and community voice

    milwaukeecourier.com (opens in a new tab) (a plan or a schedule, not an act yet)

  13. Wisconsin

    Wisconsin Public Service Commission has taken steps to require large data center customers to bear costs of generation and infrastructure required to serve them

    civicmedia.us (opens in a new tab) (a description, not an act)

  14. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids holding permit hearing for possible data center

    wsaw.com (opens in a new tab) (no act in the sentence)

  15. Tigerton, Wisconsin

    Tigerton Village Board decided to move forward with a one year moratorium on AI data center projects

    wsau.com (opens in a new tab) (no act in the sentence)

  16. Brown County, Wisconsin

    Brown County Planning Commission meeting on June 2, 2026 drew more than 100 people to voice concerns and objections to data center developments

    nbc26.com (opens in a new tab) (no act in the sentence)

  17. Wisconsin

    Brown County Board of Supervisors set to vote on resolution requesting Wisconsin Legislature place moratorium on data center building until comprehensive statewide regulations in place

    nbc26.com (opens in a new tab) (a plan or a schedule, not an act yet)

  18. Vantage Port Washington Data Center, Port Washington, Wisconsin

    American Transmission Company refiled a grid upgrade application on Monday, September 16, 2026 for infrastructure to serve the Port Washington data center.

    vernonreporter.com (opens in a new tab) (a description, not an act)

  19. Wisconsin

    Invenergy is proposing two natural gas plants in Wisconsin totaling nearly 2 gigawatts, which We Energies plans to acquire

    civicmedia.us (opens in a new tab) (a plan or a schedule, not an act yet)

  20. Wisconsin

    We Energies seeking double digit rate hikes for the next two years

    civicmedia.us (opens in a new tab) (no act in the sentence)

  21. Wisconsin Rapids, Wisconsin

    A community group called South Wood County Neighbors for Responsible Development is holding a forum to oppose the data center.

    wsau.com (opens in a new tab) (a statement; who said what is on the statements pages)

  22. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Formal plans for the data center have not yet been submitted to the city.

    wsau.com (opens in a new tab) (a plan or a schedule, not an act yet)

  23. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    A data center is proposed for the site of the abandoned Verso Paper Mill in Wisconsin Rapids.

    wsau.com (opens in a new tab) (a description, not an act)

  24. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    A proposal to turn the old Verso paper mill into a data center has no formal plans yet presented to the city

    wsau.com (opens in a new tab) (a description, not an act)

  25. Wisconsin Rapids, Wisconsin

    South Wood County Neighbors for Responsible Development holding public forum on hyperscale data centers and community impacts on Sept. 14 at Lincoln High School Performing Arts Center at 6:30 p.m.

    waow.com (opens in a new tab) (no act in the sentence)

  26. Wisconsin Rapids, Wisconsin

    South Wood County Neighbors for Responsible Development will host a free public informational meeting on data center impacts.

    wsaw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  27. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Microsoft recently completed construction of the first of a series of data centers in Racine County in the village of Mount Pleasant

    urbanmilwaukee.com (opens in a new tab) (no act in the sentence)

  28. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Over 2,000 trees will be planted at the site and an 8 foot berm will be installed

    urbanmilwaukee.com (opens in a new tab) (a plan or a schedule, not an act yet)

  29. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Campus is expected to be operational beginning in and around 2028

    urbanmilwaukee.com (opens in a new tab) (a plan or a schedule, not an act yet)

  30. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Four data centers will be built at Lighthouse campus

    urbanmilwaukee.com (opens in a new tab) (a plan or a schedule, not an act yet)

  31. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers, Oracle and OpenAI are building a $15 billion data center campus called Lighthouse in Port Washington on 672 acres next to Interstate 43

    urbanmilwaukee.com (opens in a new tab) (a description, not an act)

  32. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Campus is named Lighthouse

    wpr.org (opens in a new tab) (a description, not an act)

  33. Vantage Port Washington Data Center, Port Washington, Wisconsin

    An 8 foot berm will be installed at the site

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  34. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Over 2,000 trees will be planted at the site

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  35. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Campus will use a closed loop cooling system for water

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  36. Vantage Port Washington Data Center, Port Washington, Wisconsin

    4,000 construction workers working on the project

    wpr.org (opens in a new tab) (no act in the sentence)

  37. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Campus expected to be operational beginning in and around 2028

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  38. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Four data centers will be built at the campus

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  39. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Massive data center campus on 672 acres next to Interstate 43, around 30 minutes from Milwaukee

    wpr.org (opens in a new tab) (no act in the sentence)

  40. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Project Lighthouse is expected to open in 2028

    fox11online.com (opens in a new tab) (a plan or a schedule, not an act yet)

  41. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Project Lighthouse is a four building data center campus

    fox11online.com (opens in a new tab) (a description, not an act)

  42. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Planning Commission scheduled public hearing on October 5, 2026 at 6 p.m. at Performing Arts Center to discuss temporary data center development moratorium.

    wisconsinrapidstribune.com (opens in a new tab) (a plan or a schedule, not an act yet)

  43. Wisconsin Rapids, Wisconsin

    Legal notice for public hearing posted September 3, 2026.

    wisconsinrapidstribune.com (opens in a new tab) (no act in the sentence)

  44. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Planning Commission will hold public hearing on September 16, 2026 at 5:30 p.m. to discuss PNK Group conditional use permit and site plan review.

    wisconsinrapidstribune.com (opens in a new tab) (a plan or a schedule, not an act yet)

  45. Wisconsin Rapids, Wisconsin

    Wisconsin Rapids Planning Commission will hold public hearing on September 16 at 5:30 p.m. at Lincoln High School Performing Arts Center to discuss project site plan and conditional use permit

    wsaw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  46. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Plans call for multi building data center campus encompassing approximately 670,000 square feet with retrofitting of existing building and new construction

    wsaw.com (opens in a new tab) (no act in the sentence)

  47. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Project involves acquiring nearly 209 acres of former paper mill property off Fourth Avenue North

    wsaw.com (opens in a new tab) (a description, not an act)

  48. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    PNK Group will host public open house on Sunday September 13 from 1 p.m. to 3 p.m. at Hotel Mead Resorts & Convention Center

    wsaw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  49. Wisconsin Rapids, Wisconsin

    Public hearing scheduled for September 16 at 5:30 p.m. on conditional use permit for data center at former Rapids mill site (950 Fourth Ave. North)

    wjfw.com (opens in a new tab) (a plan or a schedule, not an act yet)

  50. Jefferson County, Wisconsin

    Jefferson County passed a data center moratorium this summer, applicable to towns subject to county zoning

    hngnews.com (opens in a new tab) (an act at a time its sentence does not give)

  51. Wisconsin Rapids, Wisconsin

    Public hearing on conditional use permit for data center at 950 Fourth Ave. N.

    wrcitytimes.com (opens in a new tab) (a description, not an act)

  52. Wisconsin Rapids, Wisconsin

    Planning Commission will discuss and act on conditional use permit and site plan review.

    wrcitytimes.com (opens in a new tab) (a plan or a schedule, not an act yet)

August 2026 7 acts on the line from 10 reports; 4 reported; 17 lines of background, plans and statements

  1. Moratorium adopted Marathon County, Wisconsin

    Marathon County Board approved on Aug. 25 a 12 month moratorium on data center development in townships governed by county zoning

    wausaupilotandreview.com (opens in a new tab), news outlet

    1 more report of this
    1. Reported September 21 Marathon County imposed a 12 month moratorium on new data center development in 18 townships wausaupilotandreview.com (opens in a new tab)
  2. Moratorium Wisconsin Rapids, Wisconsin

    Data center moratorium was first discussed at August 10, 2026 Planning Commission meeting.

    wisconsinrapidstribune.com (opens in a new tab), local outlet

  3. Wisconsin

    The Public Service Commission of Wisconsin unanimously voted on Thursday to revoke a completeness determination for American Transmission Co.'s application to build a major distribution and interconnection project.

    wpr.org (opens in a new tab), local outlet

    1 more report of this
    1. Reported August 6 Wisconsin Public Service Commission revoked ATC completeness determination for power line application in December decision, forcing restart of application process wisn.com (opens in a new tab)
  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Public Service Commission of Wisconsin revoked American Transmission Company's completeness determination for the Ozaukee County Distribution Interconnection Project on August 6, 2026

    fox11online.com (opens in a new tab), local outlet (the day its own sentence names)

  5. Wisconsin

    Public Service Commission of Wisconsin revoked a completeness determination for a transmission line project for the campus last month

    urbanmilwaukee.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 11, 2026)

    1 more report of this
    1. August, no day given PSC revoked completeness determination for prior application last month wpr.org (opens in a new tab)
  6. Wisconsin

    The Wisconsin Public Service Commission directed ATC to resubmit the application in August 2026 after finding the original design was incomplete and had undergone multiple revisions.

    vernonreporter.com (opens in a new tab), news outlet (the month its own sentence names; no day is given; filed under Sep 16, 2026)

  7. PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    Four informational webinars hosted by PNK Group in August addressed local concerns regarding power and water consumption, noise mitigation plans, and projected job creation

    wsaw.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 8, 2026)

Reported in August 2026, dated only by the article that carried them: 4 acts
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    New traffic signal installed at I-43 interchange near data center construction in Port Washington

    yahoo.com (opens in a new tab), national outlet (dated only by the report that carried it, so under the month of the report)

  2. Moratorium adopted Madison, Wisconsin

    Madison passed a moratorium on AI data centers amid concerns about water use and high energy demands

    civicmedia.us (opens in a new tab), primary source (dated only by the report that carried it, so under the month of the report)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Cloverleaf Infrastructure was the original developer behind the Port Washington hyperscale data center before the project was transferred to Vantage

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Temporary traffic lights installed at highways 32 and H at I-43 interchange

    ozaukeepress.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for August 2026, not acts of their own: 17 lines of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Crews are working on widened lanes for trucks and dedicated right turn lanes at the interchange

    tmj4.com (opens in a new tab) (a description, not an act)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    New temporary traffic signals were scheduled to go online Wednesday at the I-43 interchange

    tmj4.com (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Much of the traffic increase is attributed to data center construction traffic in the area

    tmj4.com (opens in a new tab) (a description, not an act)

  4. Madison, Wisconsin

    The moratorium on AI data centers expires in January 2027

    civicmedia.us (opens in a new tab) (no act in the sentence)

  5. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Cloverleaf is reportedly looking to build a new hyperscale data center on the east side of Madison

    civicmedia.us (opens in a new tab) (a description, not an act)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Cloverleaf Infrastructure donated $100,000 to fund a sculpture at Coal Dock Park in Port Washington

    tmj4.com (opens in a new tab) (no act in the sentence)

  7. Ozaukee County, Wisconsin

    County widening lanes at I-43 ramps and Highway LL, creating dedicated turn lanes

    ozaukeepress.com (opens in a new tab) (no act in the sentence)

  8. Ozaukee County, Wisconsin

    Enhanced pedestrian control signal and lane widening at Highland Lane and Highland Drive intersection

    ozaukeepress.com (opens in a new tab) (no act in the sentence)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage is paying for traffic improvements and law enforcement officers for traffic control

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  10. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Project is expected to be completed in 2028

    ozaukeepress.com (opens in a new tab) (a plan or a schedule, not an act yet)

  11. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Traffic lights were to be operational by August 24, 2026

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  12. Vantage Port Washington Data Center, Port Washington, Wisconsin

    American Transmission Co. hoped to begin construction in December and complete the buildout by the end of 2027.

    wpr.org (opens in a new tab) (no act in the sentence)

  13. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Public hearings planned for August 18 in Fredonia and August 19 in Kiel on this project are cancelled

    fox11online.com (opens in a new tab) (a plan or a schedule, not an act yet)

  14. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project impacts parts of Ozaukee and Washington counties as well as Calumet, Fond du Lac and Sheboygan counties

    fox11online.com (opens in a new tab) (no act in the sentence)

  15. Vantage Port Washington Data Center, Port Washington, Wisconsin

    ATC's project includes new power lines, rebuilding existing power lines, building up to five new substations, and maintenance on existing power lines for the Port Washington AI data center

    fox11online.com (opens in a new tab) (a description, not an act)

  16. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Aerial drone video shows growth of Port Washington AI campus under construction.

    jsonline.com (opens in a new tab) (no act in the sentence)

  17. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Construction continues on Vantage Data Centers' AI data center campus project in Port Washington, Wisconsin as of August 6, 2026

    jsonline.com (opens in a new tab) (a description, not an act)

July 2026 5 acts on the line from 8 reports; 3 reported; 15 lines of background, plans and statements

  1. Litigation Wisconsin

    Sierra Club filed lawsuit in Ozaukee County Circuit Court on July 10, 2026 challenging DNR decision not to require environmental impact statement for Vantage Port Washington data center

    biztimes.com (opens in a new tab), local outlet

    3 more reports of this
    1. Reported July 10 Sierra Club filed lawsuit challenging environmental approval by Wisconsin Department of Natural Resources thecentersquare.com (opens in a new tab)
    2. Reported July 21 Sierra Club sued the Wisconsin Department of Natural Resources over the $15 billion Port Washington data center project lacking an environmental impact statement gmtoday.com (opens in a new tab)
    3. Reported July 30 Sierra Club challenges environmental review for Vantage Data Centers Port Washington campus dailycardinal.com (opens in a new tab)
  2. Litigation reported Microsoft Sturtevant Data Center, Sturtevant, Wisconsin

    Residents filed lawsuit against Microsoft over noise from Mount Pleasant data center

    wisn.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Litigation Wisconsin

    Environmental groups sued Wisconsin Department of Natural Resources over environmental review process for Port Washington data center in July 2026

    wisconsinexaminer.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jul 10, 2026)

  4. Columbia County, Wisconsin

    Columbia County Board adopted policy in July prohibiting supervisors from signing nondisclosure agreements regarding data centers

    theameryfreepress.com (opens in a new tab), news outlet (the month its own sentence names; no day is given; filed under Aug 3, 2026)

  5. Moratorium adopted Cottage Grove, Wisconsin

    Village of Cottage Grove passed a one year data center moratorium in July

    hngnews.com (opens in a new tab), news outlet (the month its own sentence names; no day is given; filed under Sep 3, 2026)

Reported in July 2026, dated only by the article that carried them: 3 acts
  1. Wisconsin

    Sierra Club Wisconsin suing the Wisconsin Department of Natural Resources claiming environmental impact statements were not completed

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Public Service Commission of Wisconsin released final environmental impact statement for Port Washington data center transmission lines

    gmtoday.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  3. Litigation Wisconsin

    Midwest Environmental Advocates and Sierra Club Wisconsin sued the Wisconsin Department of Natural Resources over the decision to issue permits without an environmental impact statement

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for July 2026, not acts of their own: 15 lines of background, plans and statements
  1. Wisconsin

    Wisconsin Public Service Commission and state regulators say ratepayers will not face bill increases because of data centers

    tmj4.com (opens in a new tab) (a plan or a schedule, not an act yet)

  2. Wisconsin

    Oracle is involved in a lawsuit against state regulators over tougher financial metrics and collateral requirements to cover infrastructure costs

    tmj4.com (opens in a new tab) (a description, not an act)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Total building area planned for the Port Washington campus is 2.5 million square feet.

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Number of data centers planned for the Port Washington campus is 4.

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Port Washington Lighthouse Data Center campus size is 672 acres.

    youtube.com (opens in a new tab) (a description, not an act)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Building area of the Port Washington campus is 2.5 million square feet.

    youtube.com (opens in a new tab) (a description, not an act)

  7. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Port Washington campus will have 4 data centers.

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  8. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Port Washington campus is 672 acres.

    youtube.com (opens in a new tab) (a description, not an act)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage expects 1,000 employees on site at Port Washington when combined with its customers Oracle and OpenAI.

    youtube.com (opens in a new tab) (a plan or a schedule, not an act yet)

  10. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Port Washington water utility installing two new water meters to track data center facility water usage

    tmj4.com (opens in a new tab) (no act in the sentence)

  11. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Second building on campus recently topped out

    tmj4.com (opens in a new tab) (no act in the sentence)

  12. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Port Washington facility called Lighthouse

    tmj4.com (opens in a new tab) (a statement; who said what is on the statements pages)

  13. Wisconsin

    DNR attorney Molly McNab informed Vantage representatives in July 2025 that an environmental impact statement would be required for the project

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  14. Wisconsin

    DNR staff initially required full Environmental Impact Statement but project ultimately did not require one after company pushback

    thecentersquare.com (opens in a new tab) (a description, not an act)

  15. Vantage Port Washington Data Center, Port Washington, Wisconsin

    DNR determined it satisfied environmental obligations on December 9 for the Vantage project

    biztimes.com (opens in a new tab) (no act in the sentence)

June 2026 5 acts on the line; 3 reported; 1 line of background, plans and statements

  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage topped out second building at Lighthouse campus in Port Washington on June 26, 2026

    datacenterdynamics.com (opens in a new tab), trade press (the day its own sentence names)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Topping out ceremony held June 26, 2026 for second of four data center buildings

    ozaukeepress.com (opens in a new tab), local outlet (the day its own sentence names; filed under Jul 1, 2026)

  3. running Microsoft Mount Pleasant Data Center Campus, Mount Pleasant, Wisconsin

    Microsoft's first Fairwater datacenter facility in Mount Pleasant is fully operational, with equipment brought online from April and close to 550 full time employees; a second facility next to it is under construction for 2028

    news.microsoft.com (opens in a new tab), primary source (dated only by the report that carried it, so under the month of the report)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The DNR issued permits for the project on June 12

    wpr.org (opens in a new tab), local outlet (the day its own sentence names; filed under Jul 10, 2026)

  5. Moratorium adopted Dane County, Wisconsin

    Dane County passed an 18 month data center moratorium in June, applicable to towns subject to county zoning

    hngnews.com (opens in a new tab), news outlet (the month its own sentence names; no day is given; filed under Sep 3, 2026)

Reported in June 2026, dated only by the article that carried them: 3 acts
  1. Litigation Wisconsin

    Oracle filed lawsuit against Wisconsin PSC in Ozaukee County court to force amendment of tariff decision

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Litigation Wisconsin

    Oracle sued the Public Service Commission of Wisconsin seeking to relax data center financial requirement rules

    wispolitics.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

  3. Moratorium Dane County, Wisconsin

    Dane County imposed a data center moratorium

    wispolitics.com (opens in a new tab), news outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for June 2026, not acts of their own: 1 line of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers is operating a massive Port Washington project

    bizjournals.com (opens in a new tab) (a description, not an act)

May 2026 No acts on the line; 1 reported; 3 lines of background, plans and statements

Reported in May 2026, dated only by the article that carried it: 1 act
  1. Approval Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage applied for and received preliminary approval to install up to 45 diesel generators

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for May 2026, not acts of their own: 3 lines of background, plans and statements
  1. Ozaukee County, Wisconsin

    Ozaukee County is in an area of nonattainment for pollutants such as ozone under National Ambient Air Quality Standards

    spectrumnews1.com (opens in a new tab) (a description, not an act)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The air permit is for 45 generators at the Vantage Lighthouse Campus

    spectrumnews1.com (opens in a new tab) (a description, not an act)

  3. Port Washington, Wisconsin

    Ozaukee County Sheriff's Office and Wisconsin State Patrol providing three officers for traffic control from 5:30-7:30 a.m. and 3:30-5:30 p.m. Mondays through Fridays

    ozaukeepress.com (opens in a new tab) (no act in the sentence)

April 2026 3 acts on the line; 2 reported; 16 lines of background, plans and statements

  1. Referendum Port Washington, Wisconsin

    Port Washington held a referendum on April 7, 2026, to require voter approval for future TIF districts over $10 million

    fox6now.com (opens in a new tab), local outlet (the day its own sentence names; filed under Apr 6, 2026)

  2. Rate rule Wisconsin

    Wisconsin Public Service Commission added tariffs in April targeting very large customers not carrying sufficiently high credit rating

    tmj4.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Jun 29, 2026)

  3. Filing PNK Group Wisconsin Rapids Data Center, Wisconsin Rapids, Wisconsin

    PNK Group submitted original conditional use permit application in April 2026 and updated application in July 2026.

    wisconsinrapidstribune.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Sep 9, 2026)

Reported in April 2026, dated only by the article that carried them: 2 acts
  1. Approval Port Washington, Wisconsin

    The Port Washington Common Council approved tax incremental financing to support public improvements tied to the Vantage data center development

    fox6now.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Litigation Port Washington, Wisconsin

    The Metropolitan Milwaukee Association of Commerce filed a lawsuit challenging the referendum

    fox6now.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for April 2026, not acts of their own: 16 lines of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    $15 billion Port Washington data center project under construction

    jsonline.com (opens in a new tab) (no act in the sentence)

  2. Wisconsin

    Wisconsin Department of Natural Resources found Vantage will meet air pollution limits and granted preliminary approval for air pollution control permits

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  3. Wisconsin

    Sierra Club Wisconsin suing the Department of Natural Resources over absence of environmental impact statement

    wpr.org (opens in a new tab) (no act in the sentence)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Construction of roughly 670 acre campus slated to wrap up in 2028

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage applying for permits to use 45 diesel fired generators for backup power

    wpr.org (opens in a new tab) (a description, not an act)

  6. Wisconsin

    Residents pleaded with Wisconsin DNR to deny Port Washington data center air pollution permit

    wisconsinexaminer.com (opens in a new tab) (no act in the sentence)

  7. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage is building the data center to LEED standards with a goal of 41% biodiversity net gain

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  8. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project is targeted for completion in 2028

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage is contributing $3 million to the Valley Creek project intended to improve water quality and reduce downstream flooding

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  10. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage is laying 48.3 miles of water lines at the site with a closed loop system using less water than Port Washington public schools

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  11. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The buildings should be weather tight by the end of 2026

    ozaukeepress.com (opens in a new tab) (a plan or a schedule, not an act yet)

  12. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Buildings are being constructed sequentially with work on each structure starting 30 to 45 days after the last

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  13. Vantage Port Washington Data Center, Port Washington, Wisconsin

    About 1,000 workers are on site each day, with the workforce expected to swell to about 5,000 at peak construction

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  14. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The campus will have four data center buildings, two measuring about 1,800 by 400 feet (560,000 and 725,000 square feet respectively), about 27 feet tall

    ozaukeepress.com (opens in a new tab) (a plan or a schedule, not an act yet)

  15. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers Lighthouse Campus is a 675 acre data center project in Port Washington

    ozaukeepress.com (opens in a new tab) (a description, not an act)

  16. Port Washington, Wisconsin

    The referendum follows controversy over a proposed $15 billion data center campus by Vantage Data Centers

    fox6now.com (opens in a new tab) (no act in the sentence)

March 2026 1 act on the line from 2 reports; 6 reported; 9 lines of background, plans and statements

  1. Port Washington, Wisconsin

    Port Washington Plan Commission unanimously passed amendment on Thursday limiting outdoor construction to 6 a.m. to 8 p.m. Monday through Saturday

    wpr.org (opens in a new tab), local outlet

    1 more report of this
    1. Reported March 19 Port Washington Planning Commission unanimously approved motion to end 24 hour outdoor construction at Vantage data center tmj4.com (opens in a new tab)
Reported in March 2026, dated only by the article that carried them: 6 acts
  1. Port Washington, Wisconsin

    Construction work on Sundays limited to one Sunday per month from 8 a.m. to 4 p.m.

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  2. Port Washington, Wisconsin

    Sunday work restricted to maximum one Sunday per month

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  3. Port Washington, Wisconsin

    Lighting limited to necessary security lighting after 8:30 p.m.

    tmj4.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  4. Approval Port Washington, Wisconsin

    Construction originally limited to 12 hour period, then city approved 24 hour construction on weekdays

    urbanmilwaukee.com (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  5. Port Washington, Wisconsin

    Residents presented a letter requesting that the city go back to enforcing the old hours by mid March, signed by 100 people.

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

  6. Approval Vantage Port Washington Data Center, Port Washington, Wisconsin

    Construction on the Vantage Data Centers Lighthouse Campus was originally limited to a 12 hour period but the city later approved 24 hour construction on weekdays.

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for March 2026, not acts of their own: 9 lines of background, plans and statements
  1. Port Washington, Wisconsin

    Lighting must be reduced to security levels after 8:30 p.m.

    wpr.org (opens in a new tab) (a description, not an act)

  2. Port Washington, Wisconsin

    When data center buildings are fully enclosed, construction can take place inside 24 hours a day Monday through Friday and until 11:59 p.m. on Saturdays

    wpr.org (opens in a new tab) (a description, not an act)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    New construction hour restrictions take effect April 18, 2026

    wpr.org (opens in a new tab) (no act in the sentence)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Construction was previously allowed 24 hours a day during weekdays

    wpr.org (opens in a new tab) (no act in the sentence)

  5. Port Washington, Wisconsin

    New rules limit exterior construction to 6 a.m. to 8 p.m. Monday through Saturday

    tmj4.com (opens in a new tab) (no act in the sentence)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Rules do not go into effect until April 18

    tmj4.com (opens in a new tab) (no act in the sentence)

  7. Port Washington, Wisconsin

    City reviewing whether to allow 24 hour construction through end of May

    urbanmilwaukee.com (opens in a new tab) (a description, not an act)

  8. Port Washington, Wisconsin

    Port Washington Planning Commission scheduled to address construction hours issue

    urbanmilwaukee.com (opens in a new tab) (a plan or a schedule, not an act yet)

  9. Port Washington, Wisconsin

    The Port Washington Planning Commission is set to take up the issue of whether to allow 24 hour construction through the end of May.

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

February 2026 No acts on the line; 1 reported; 4 lines of background, plans and statements

Reported in February 2026, dated only by the article that carried it: 1 act
  1. Litigation Port Washington, Wisconsin

    Great Lakes Neighbors filed a lawsuit against the city and its Joint Review Board challenging the TID.

    wpr.org (opens in a new tab), local outlet (dated only by the report that carried it, so under the month of the report)

Also on the record for February 2026, not acts of their own: 4 lines of background, plans and statements
  1. Wisconsin

    Power arrangements for the facility are being reviewed by the Public Service Commission

    youtube.com (opens in a new tab) (a description, not an act)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center campus in Port Washington has been under construction for over two months

    youtube.com (opens in a new tab) (a description, not an act)

  3. Port Washington, Wisconsin

    Proposed ordinance would require voter referendum approval for any new tax increment district with project cost or projected base value over $10 million

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Motion hearing scheduled for February 13, 2026

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

January 2026 2 acts on the line; 3 lines of background, plans and statements

  1. Litigation Port Washington, Wisconsin

    Metropolitan Milwaukee Association of Commerce and six other business groups filed lawsuit against Port Washington in late January 2026

    wpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Feb 4, 2026)

  2. Moratorium adopted Madison, Wisconsin

    City of Madison passed a one year data center moratorium in January

    hngnews.com (opens in a new tab), news outlet (the month its own sentence names; no day is given; filed under Sep 3, 2026)

Also on the record for January 2026, not acts of their own: 3 lines of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers Lighthouse Campus under construction in Port Washington

    jsonline.com (opens in a new tab) (no act in the sentence)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers is planting over 2,000 native trees throughout the project site.

    youtube.com (opens in a new tab) (a description, not an act)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers is preserving over 150 acres of land that will be restored to a native Wisconsin landscape.

    youtube.com (opens in a new tab) (a description, not an act)

2025 11 acts on the line; 25 lines of background, plans and statements

December 2025 7 acts on the line; 11 lines of background, plans and statements

  1. Groundbreaking Vantage Port Washington Data Center, Port Washington, Wisconsin

    Ceremonial groundbreaking held December 19, 2025

    tmj4.com (opens in a new tab), local outlet (the day its own sentence names)

  2. Groundbreaking Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers broke ground on a $15 billion data center campus in Port Washington on December 18, 2025

    dailyreporter.com (opens in a new tab), local outlet (the day its own sentence names)

  3. Groundbreaking being built Vantage Port Washington Data Center, Port Washington, Wisconsin

    Groundbreaking held December 17, 2025, with construction beginning on 672 acre site

    biztimes.com (opens in a new tab), local outlet (the day its own sentence names)

  4. Groundbreaking Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers Lighthouse Campus groundbreaking held December 17, 2025

    ozaukeepress.com (opens in a new tab), local outlet (the day its own sentence names; filed under Dec 23, 2025)

  5. Ordinance Port Washington, Wisconsin

    Port Washington City Council voted in December to place ordinance on April ballot

    wpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Feb 4, 2026)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Construction on the site began in December after DNR permitting was completed

    youtube.com (opens in a new tab), video (the month its own sentence names; no day is given; filed under Apr 16, 2026)

  7. Groundbreaking Vantage Port Washington Data Center, Port Washington, Wisconsin

    Data center campus broke ground in December 2025

    ozaukeepress.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Aug 19, 2026)

Also on the record for December 2025, not acts of their own: 11 lines of background, plans and statements
  1. Port Washington, Wisconsin

    Residents must collect signatures equal to 25 percent of ballots cast in 2022 gubernatorial election, roughly 1,600 signatures, within 60 days

    tmj4.com (opens in a new tab) (a description, not an act)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers building for Oracle and OpenAI

    tmj4.com (opens in a new tab) (no act in the sentence)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project is part of OpenAI and Oracle's $500 billion Stargate AI data center initiative

    dailyreporter.com (opens in a new tab) (a description, not an act)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project is expected to create 1,000 permanent jobs

    dailyreporter.com (opens in a new tab) (a plan or a schedule, not an act yet)

  5. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project is expected to create more than 4,000 construction jobs

    dailyreporter.com (opens in a new tab) (a plan or a schedule, not an act yet)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The project is expected to be completed in 2028

    dailyreporter.com (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center campus has 902 megawatts of capacity

    dailyreporter.com (opens in a new tab) (a description, not an act)

  8. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center campus includes four buildings totaling 2.5 million square feet

    dailyreporter.com (opens in a new tab) (a description, not an act)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center campus is 672 acres

    dailyreporter.com (opens in a new tab) (a description, not an act)

  10. Vantage Port Washington Data Center, Port Washington, Wisconsin

    End users are OpenAI and Oracle

    biztimes.com (opens in a new tab) (a description, not an act)

  11. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Developer is Vantage Data Centers

    biztimes.com (opens in a new tab) (a description, not an act)

November 2025 3 acts on the line; 1 line of background, plans and statements

  1. Port Washington, Wisconsin

    Port Washington City Clerk received petition for direct legislation in November 2025 with 15 percent of electors' signatures

    wpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Feb 4, 2026)

  2. Approval Port Washington, Wisconsin

    The Port Washington City Council in November approved a resolution creating a tax increment district to fund around $175 million in infrastructure improvements to serve the data center development.

    wpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Feb 13, 2026)

  3. Wisconsin

    Port Washington city agreed in November to allow construction around the clock Monday Friday and 6am-8pm Saturday Sunday

    ozaukeepress.com (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Mar 18, 2026)

Also on the record for November 2025, not acts of their own: 1 line of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    TID would remain open for up to 20 years or until Vantage is reimbursed for all costs

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

October 2025 No acts on the line; 13 lines of background, plans and statements

Also on the record for October 2025, not acts of their own: 13 lines of background, plans and statements
  1. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage said the data center campus will preserve 172 acres to support biodiversity and provide natural sound mitigation

    wpr.org (opens in a new tab) (a statement; who said what is on the statements pages)

  2. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers is underwriting 100 percent of the power infrastructure investment with a dedicated electricity rate from WEC Energy Group utility We Energies

    wpr.org (opens in a new tab) (a description, not an act)

  3. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center buildings will use a closed loop liquid cooling system

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  4. Vantage Port Washington Data Center, Port Washington, Wisconsin

    A $1.4 billion transmission line project from American Transmission Co. is proposed to support the Lighthouse campus

    wpr.org (opens in a new tab) (a description, not an act)

  5. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The Lighthouse campus is roughly 670 acres

    wpr.org (opens in a new tab) (a description, not an act)

  6. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers will have around 330 employees at the Lighthouse campus

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  7. Vantage Port Washington Data Center, Port Washington, Wisconsin

    OpenAI and Oracle will have around 700 jobs at the Lighthouse campus after construction

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  8. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The data center campus could create more than 4,000 construction jobs

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  9. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The four data center buildings are expected to need 1.3 gigawatts of electricity

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

  10. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The Lighthouse campus includes four data center buildings

    wpr.org (opens in a new tab) (a description, not an act)

  11. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The Lighthouse campus is part of OpenAI and Oracle's $500 billion Stargate program

    wpr.org (opens in a new tab) (a description, not an act)

  12. Vantage Port Washington Data Center, Port Washington, Wisconsin

    The Port Washington data center campus is named Lighthouse

    wpr.org (opens in a new tab) (a description, not an act)

  13. Vantage Port Washington Data Center, Port Washington, Wisconsin

    Vantage Data Centers, OpenAI, and Oracle plan to invest more than $15 billion at a Port Washington data center campus

    wpr.org (opens in a new tab) (a plan or a schedule, not an act yet)

August 2025 1 act on the line

  1. Approval approved Vantage Port Washington Data Center, Port Washington, Wisconsin

    The Port Washington Common Council approved the development agreement for the project in August

    wpr.org (opens in a new tab), local outlet (the month its own sentence names; no day is given; filed under Oct 24, 2025)