Meta Beaver Dam Data Center
Meta lists a data center at Beaver Dam, Wisconsin among the sites it operates. It is running; the record holds no sourced date for when it reached that stage.
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Land
- Not disclosed
- Power it would draw
- Not disclosed
- Reported by others: 1,300 MW (WPR). Their figure, not the record's.
- Water
- Not disclosed
- Who leads it
- Meta
- as stated by the source
- Who would use it
- Not disclosed
- Jobs once it runs
- Not disclosed
- Tax each year
- Not disclosed
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Meta | as stated by the source | September 17, 2026 | |
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | Not disclosed | |||
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
How much power it needs, also reported: 1,300 MW, 2025 (WPR: We Energies requested transmission interconnection for 1,300 megawatt facility at Port Washington data center.) .
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water useA state water right filing or a water supply agreement.
- Who would use itA lease announcement or a tenant named in a filing.
- Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
- Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.
What happened
-
(source date; the content gives no date of its own)
Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027 [2]
-
· Status: running (the day the page was read; it gives no date of its own)
Meta lists Meta Beaver Dam Data Center at Beaver Dam, Wisconsin on its own page of data center locations, read September 14, 2026. [1]
The full Meta Beaver Dam Data Center timeline, in order
1 correction to this record
Every correction, with its reason
-
· the summary of a record items row
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word The old and new text.
Every correction on the record is on the corrections page.
What was said
Microsoft's data center campus in Mount Pleasant and Port Washington data center would use more power than all homes in Wisconsin, according to Clean Wisconsin analysis.
The site
Where in Beaver Dam is not in the public record. The pin marks the center of Beaver Dam, not a building, and the outline is Dodge County.
Tap a pin for the data center, the parcel for its record
- This record: Running, ringed
- data center
- Dashed edge: the exact site is not in the public record
- Smaller pins: 6 other published records in Wisconsin
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
- Where
- Beaver Dam, Dodge County, Wisconsin
- How exactly it is located
- Town level, the center of the city
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- Nearest records are not computed for a record placed at the center of its town.
Comparisons
1 metric with more than one figure
Capacity at full buildout
1 figure, 1 sourceShow each source's words
- 1,300 MW, WPR: We Energies requested transmission interconnection for 1,300 megawatt facility at Port Washington data center.
Questions about this project
7 questions answered from the record
How big is Meta Beaver Dam Data Center?
-
Not disclosed. No source on file gives its capacity, its acreage or a count of buildings. What the record holds instead is under Disclosed.
Who is building Meta Beaver Dam Data Center?
-
Meta is the developer. No construction contractor is named on the record yet.
Who will use Meta Beaver Dam Data Center?
-
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
How much power and water does Meta Beaver Dam Data Center say it needs?
-
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
Where does Meta Beaver Dam Data Center stand today?
-
It is running; the date it reached that stage is not sourced, only the day a page was read. The newest entry, reported September 17, 2026: Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027 [2].
What has Beaver Dam or Dodge County decided about it?
-
No decision by Beaver Dam or Dodge County about data centers is on the record. The Dodge County page and the Wisconsin scorecard list every rated row the day a person publishes one.
What is still unknown about Meta Beaver Dam Data Center?
-
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
Sources
Primary documents
- Meta: Our U.S. data center fleet, Meta, September 14, 2026
Reporting
- Alliant Energy seeks new rate for data centers in southern Wisconsin - Journal Times, Journal Times, September 17, 2026, local outlet
2 sources on file.
Cite this record
Data Center Record, "Meta Beaver Dam Data Center", https://datacenterrecord.org/projects/meta-beaver-dam-data-center-wi, last verified September 17, 2026.
Cite this page
Data Center Record, "Meta Beaver Dam Data Center", https://datacenterrecord.org/projects/meta-beaver-dam-data-center-wi. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Slug
- meta-beaver-dam-data-center-wi
- Status value
- operational
- Stage
- Running
- Tier
- skeleton
- Tags
- skeleton
- Place id
- us/wi/dodge-county/beaver-dam
- Coordinates
- 43.4740618, -88.8295539
- Location precision
- city
- Location source
- U.S. Census Bureau TIGERweb city centroid, public domain
- Coordinate source
- tigerweb city centroid
- Location source number
- Not disclosed
- Location last verified
- September 14, 2026
- EPA registry id
- Not disclosed
- Use type values
- not_disclosed
- Tenancy value
- not_disclosed
- Cooling type value
- not_disclosed
- Capacity basis
- not_disclosed
- Water basis
- not_disclosed, gallons_per_day
- Acreage basis
- Not disclosed
- Interconnection value
- not_disclosed
- Capacity, if disclosed
- Not disclosed
- Rating of the county's rows
- Not disclosed
- Published
- 2026-09-14
- Last verified
- 2026-09-17