Census GEOID: 55027 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 primary and 1 reporting sources

● Running Reported September 17, 2026 · 5 Buildings

Meta Beaver Dam Data Center

Street address Hemlock Road and US Highway 151, Beaver Dam, WI 53916, Dodge County verified address Exact, at the address [1] Meta: Our U.S. data center fleet

Overview, regulatory gates and specifications

Meta developed a hyperscale data center campus along Hemlock Road and US Highway 151 in Beaver Dam, Dodge County, Wisconsin. [1] Filings on the record specify disclosed capacity of 200 MW (the developer's figure), 5 planned or operational buildings. [1] Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027 [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
200 MW
the developer's figure

Equivalent to ~166,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 9.6% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
5 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: Hemlock Road and US Highway 151, Beaver Dam, WI 53916.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
200 MW developer figure Equivalent to the continuous electricity demand of about 166,000 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 2 percent of New York City's summer peak demand in 2024.
[1] datacenters.atmeta.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
5 buildings operator page
[1] datacenters.atmeta.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2022 (4 years)
Who leads it
Meta as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Meta Beaver Dam Data Center, capacity: 200 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 200 ÷ 10,245 = 0.02 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

David Steffen

Wisconsin state representative

DID Recorded statement at WSAW (May 27, 2026)
SAID Rep. David Steffen, chair of the Committee on Energy and Utilities, said legislation aimed at getting regulations for data centers set into place can be expected next session (May 27, 2026) wsaw.com (opens in a new tab)

Clean Wisconsin

Public Record Speaker

DID Recorded statement at WPR (December 10, 2025)
SAID Microsoft's data center campus in Mount Pleasant and Port Washington data center would use more power than all homes in Wisconsin, according to Clean Wisconsin analysis. (December 10, 2025) wpr.org (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Meta
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Meta Beaver Dam Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 200 MW 200 MW the developer's figure [1] datacenters.atmeta.com
Site Footprint (Acres)
Data Hall Buildings 5 buildings 5 operator page [1] datacenters.atmeta.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027

    [2] journaltimes.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Meta lists Meta Beaver Dam Data Center at Beaver Dam, Wisconsin on its own page of data center locations, read September 14, 2026.

    [1] datacenters.atmeta.com

1 correction to this record

Every correction, with its reason
  1. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

Every correction on the record is on the corrections page.

Nearest data centers in Wisconsin

Verified data center records in Wisconsin within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
QTS Dane County Data Center Campus (DeForest Vienna) DeForest, Dane County 32 mi Proposed QTS Data Centers 800 MW
Ethoplex Germantown Data Center Germantown, Washington County 38 mi Running Ethoplex 2 MW
EdgeConneX Madison Data Center (EDCMAD01) Madison, Dane County 39 mi Running EdgeConneX 5 MW
Network 222 Carrier Hotel and Data Center (Madison) Madison, Dane County 41 mi Running Fiore Companies 4 MW
SupraNet Communications Madison Data Center Madison, Dane County 45 mi Running SupraNet Communications 3 MW
US Signal and OneNeck Madison Data Center (WI02) Fitchburg, Dane County 47 mi Running OneNeck IT Solutions 6 MW

Blank cell: not disclosed by any source on file.

Comparisons

2 metrics with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Capacity at full buildout

3 figures, 3 sources
200 MW Developer's figure

Meta, Sep 14, 2026

Show each source's words
  • 1,300 MW, WPR: We Energies requested transmission interconnection for 1,300 megawatt facility at Port Washington data center.
  • 200 megawatts, WSAW: Democratic state Rep. Supreme Moore Omokunde highlighted a study showing upgrading energy efficiency of nearly 40,000 Wisconsin homes would offset the demand of a 200 megawatt data center, about the size of Meta's Beaver Dam data center

Project footprint

1 figure, 1 source
Show each source's words
  • 520 acres, fdlreporter.com: Meta data center in Beaver Dam spans 520 acres

Common questions about Meta Beaver Dam Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Meta Beaver Dam Data Center?

Meta is the developer. No construction contractor is named on the record yet.

Who will use Meta Beaver Dam Data Center?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Meta Beaver Dam Data Center say it needs?

Power: 200 MW (the developer's figure, datacenters.atmeta.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Meta Beaver Dam Data Center stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. The newest entry, reported September 17, 2026: Meta Beaver Dam data center is a $1 billion, 520 acre project expected to enter service in 2027 [2].

What is still unknown about Meta Beaver Dam Data Center?

Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Meta: Our U.S. data center fleet (opens in a new tab), Meta, September 14, 2026

Reporting

  1. Alliant Energy seeks new rate for data centers in southern Wisconsin - Journal Times (opens in a new tab), Journal Times, September 17, 2026, news outlet

2 sources on file.

Regional grid context

This site is in the MRO East (MROE) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Meta Beaver Dam Data Center", https://datacenterrecord.org/projects/meta-beaver-dam-data-center-wi, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Meta Beaver Dam Data Center", https://datacenterrecord.org/projects/meta-beaver-dam-data-center-wi. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
43.4862, -88.8145
How the location is known
Location from the site's street address.
Location source
https://datacenters.atmeta.com/
Coordinate source
City of Beaver Dam TID and Meta Beaver Dam campus plan
Location last verified
September 14, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
200 MW, the developer's figure
Published
September 14, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Meta Beaver Dam Data Center · 2 sources, 2 entries · basis and source tier on every row · verified November 6, 2026

Download CSV JSON