Microsoft Mount Pleasant Data Center Campus

Street address 4800 90th Street, Mount Pleasant, WI 53403, Racine County verified address Exact, at the address EPA ECHO detailed facility report: Microsoft Corporation, Mke 3B Data Center (opens in a new tab)

Overview, regulatory gates and specifications

Microsoft operates and is expanding its hyperscale AI data center campus at 4800 90th Street in the Electronics and Information Technology Manufacturing Zone in Mount Pleasant, Racine County, Wisconsin. [1] Filings on the record specify disclosed capacity of 315 MW (the developer's figure), 8 planned or operational buildings. [1] Fairwater data center is now operational [8]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA air permit on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
315 MW
the developer's figure

Equivalent to ~261,450 U.S. homes (U.S. EIA 830 homes/MW baseline) · 15% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
8 buildings
agency filing

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 4800 90th Street, Mount Pleasant, WI 53403.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
315 MW developer figure Equivalent to the continuous electricity demand of about 261,500 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 3 percent of New York City's summer peak demand in 2024.
local.microsoft.com (opens in a new tab)
Water usage
Not disclosed
Land area
Not disclosed
Buildings
8 buildings operator page
local.microsoft.com (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2026 (first year)
Who leads it
Microsoft as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Microsoft Mount Pleasant Data Center Campus, capacity: 315 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 315 ÷ 10,245 = 0.03 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Microsoft
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Microsoft Mount Pleasant Data Center Campus.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 315 MW 315 MW the developer's figure
Site Footprint (Acres)
Data Hall Buildings 8 buildings 8 agency filing
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

April 19, 2023 Mount Pleasant, WI $1 billion Microsoft data center proposal gets final approval Mount Pleasant Village Board 2 clips

TMJ4 News report on Mount Pleasant Village Board and community proceedings in Mount Pleasant, WI: $1 billion Microsoft data center proposal gets final approval (April 19, 2023).

  1. TMJ4 News Broadcast Report Broadcast Report transcribed from local broadcast report
    "Center near the foxconn site in Mount Pleasant, a company rep says that the proposal would likely bring. Hundreds of jobs. Taylor lumpkin has more. Microsoft officials are eager to get started on their project to begin building their next billion dollar data center in Mount Pleasant all of the infrastructure. That's not the size that we need. It's ready to go. Microsoft representative said there are"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "They enter Racine County. And that's something residents including alphonso gardner is happy to hear. He says he has some reservations about the company coming to the area. And once a tech company to help improve the lives of black families in the county, microsoft need to understand when they come here, they have to deal with everybody. Everybody has you can get an opportunity. Only 8% of blacks in this county a"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Fairwater data center is now operational

    [8] wpr.org

  2. (content date)

    Class action lawsuit filed Wednesday in U.S. District Court for Eastern District of Wisconsin by three residents of Sturtevant

    [8] wpr.org

  3. (content date)

    Microsoft completed construction of its first data center facility in Mount Pleasant, Wisconsin, with the AI data center campus now fully operational and plans for additional facilities.

    local.microsoft.com (opens in a new tab) news outlet

  4. (source date; the content gives no date of its own)

    Microsoft's first Fairwater datacenter facility in Mount Pleasant is fully operational, with equipment brought online from April and close to 550 full time employees; a second facility next to it is under construction for 2028

    [9] news.microsoft.com

  5. (content date)

    June 18 update noted engineering team investigated source and put noise mitigations in place

    [8] wpr.org

  6. · Status: running (content date)

    April 15 update noted residents north of facility noticed tonal humming sound

    [8] wpr.org

Every event in order

11 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Timeline date

    Dated from its source: the row's own text states "June 18 update"

  5. · Timeline date

    Dated from its source: the row's own text states "April 15 update"

  6. · Timeline date

    Dated from its source: the article says the suit was filed "Wednesday"; published Thursday July 2, 2026, so Wednesday is July 1, 2026

  7. · Timeline date

    Dated from its source: the article's own publish date

Every correction on the record is on the corrections page.

Nearest data centers in Wisconsin

Verified data center records in Wisconsin within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Microsoft Sturtevant Data Center Sturtevant, Racine County 2 mi Proposed Microsoft 2 buildings
Microsoft Caledonia Data Center Proposal Caledonia, Racine County 11 mi Stalled or cancelled Microsoft 2 buildings
CyberLynk Milwaukee Data Center (MKE1) Franklin, Milwaukee County 13 mi Running Wisconsin CyberLynk Network 2 MW
TierPoint Milwaukee Data Center Milwaukee, Milwaukee County 23 mi Running TierPoint 5 MW
324 East Wisconsin Carrier Hotel (Wells Building Milwaukee) Milwaukee, Milwaukee County 25 mi Running Wells Interconnection 5 MW
DataBank Milwaukee Data Center (formerly CoSentry) Milwaukee, Milwaukee County 25 mi Running DataBank 6 MW

Blank cell: not disclosed by any source on file.

Common questions about Microsoft Mount Pleasant Data Center Campus

Answered directly from the verified filings and local actions on this page.

Who is building Microsoft Mount Pleasant Data Center Campus?

Microsoft is the developer. No construction contractor is named on the record yet.

How much power and water does Microsoft Mount Pleasant Data Center Campus say it needs?

Power: 315 MW (the developer's figure, local.microsoft.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Microsoft Mount Pleasant Data Center Campus stand today?

It is running, since April 15, 2026. The newest entry, reported July 2, 2026: Fairwater data center is now operational [8].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. EPA ECHO detailed facility report: Microsoft Corporation, Mke 3B Data Center (opens in a new tab), U.S. Environmental Protection Agency

Reporting

  1. Mount Pleasant approves site plans for Microsoft data center expansion - WPR (opens in a new tab), WPR, January 28, 2026, local outlet
  2. Microsoft wants to build 15 more data centers in Mount Pleasant - WPR (opens in a new tab), WPR, January 20, 2026, local outlet
  3. Microsoft's plans for 15 more data centers win approval at former Wisconsin Foxconn site - CNBC (opens in a new tab), CNBC, January 26, 2026, national outlet
  4. Barnes Exits Wisconsin Governor Race, Leaving AI Data Center Moratorium Fight to Hong - Tech Times (opens in a new tab), Tech Times, July 30, 2026, news outlet
  5. Mount Pleasant commission approves Microsoft’s plans for data center expansion - WPR (opens in a new tab), WPR, January 22, 2026, local outlet
  6. Microsoft’s Wisconsin AI Data Center Campus Now Fully Operational - Data Center Knowledge (opens in a new tab), Data Center Knowledge, June 24, 2026, trade press
  7. Microsoft sued over noise complaints at new Mount Pleasant data center facility - WPR (opens in a new tab), wpr.org, local outlet
  8. Microsoft completes construction on first datacenter facility in Mount Pleasant, Wisconsin - Microsoft Source (opens in a new tab), Microsoft Source, June 23, 2026, news outlet
  9. Microsoft finishes construction of Mount Pleasant data center, plans for more - WPR (opens in a new tab), WPR, June 23, 2026, local outlet

10 sources on file.

Regional grid context

This site is in the MRO East (MROE) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Microsoft Mount Pleasant Data Center Campus", https://datacenterrecord.org/projects/microsoft-mount-pleasant-data-center-campus-wi, last verified October 27, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Microsoft Mount Pleasant Data Center Campus", https://datacenterrecord.org/projects/microsoft-mount-pleasant-data-center-campus-wi. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
In court, Built from one source
Coordinates
42.6815, -87.9255
How the location is known
Location from the site's street address.
Location source
https://local.microsoft.com/wisconsin/
Coordinate source
Wisconsin DNR Air Permit and Racine County GIS parcel
Location source number
[1]
Location last verified
October 4, 2026
EPA registry id
110071538060
How capacity was disclosed
the developer's figure
Capacity, if disclosed
315 MW, the developer's figure
Published
September 4, 2026
Last verified
October 27, 2026
Not disclosed
Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows