Microsoft Mount Pleasant Data Center Campus, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
3 events, April 15, 2026 to July 1, 2026. Also on the record, under the month each belongs to: 3 dates when source pages were read and verified. The facts, newest first: the record; the place: Wisconsin.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2026 3 events
-
(content date)
running
April 15 update noted residents north of facility noticed tonal humming sound [8]
-
(content date)
Entry
Microsoft completed construction of its first data center facility in Mount Pleasant, Wisconsin, with the AI data center campus now fully operational and plans for additional facilities. local.microsoft.com (opens in a new tab) news outlet
-
Also in June 2026: 2 dates when source pages were read and verified
-
(content date)
Entry
June 18 update noted engineering team investigated source and put noise mitigations in place [8]
-
(source date; the content gives no date of its own)
Entry
Microsoft's first Fairwater datacenter facility in Mount Pleasant is fully operational, with equipment brought online from April and close to 550 full time employees; a second facility next to it is under construction for 2028 [9]
-
-
(content date)
Entry
Class action lawsuit filed Wednesday in U.S. District Court for Eastern District of Wisconsin by three residents of Sturtevant [8]
-
Also in July 2026: 1 date when a source page was read and verified
-
(source date; the content gives no date of its own)
Entry
Fairwater data center is now operational [8]
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- running
- Events on the timeline
- 3
- Under the months
- 3
- Stage changes
- 1
- Decisions
- 0
- Statements
- 0
- Figures
- 0
- Entries and decisions under the months
- 3