$1 billion Microsoft data center proposal gets final approval

TMJ4 News report on Mount Pleasant Village Board and community proceedings in Mount Pleasant, WI: $1 billion Microsoft data center proposal gets final approval (April 19, 2023).

Jurisdiction Mount Pleasant, WI
Governing Body Mount Pleasant Village Board
Meeting Date April 19, 2023
Extracted Clips 2 clips · 1 opposed · 0 supporting
Local broadcast report · TMJ4 News Ready at Clip 1 (0:15 to 0:42) · TMJ4 News Broadcast Report
Open source video on YouTube ↗ (opens in a new tab)

Privacy enhanced player · zero third party requests until clicked

$1 billion Microsoft data center proposal gets final approval

Mount Pleasant Village Board · April 19, 2023

Timestamped Speaker & Testimony Ledger

2 verified timestamped clips extracted chronologically from the closed caption record. Select any clip to play that exact window in the master player or copy a canonical clip link.

  1. Clip 1 · 0:15 TMJ4 News Broadcast Report Broadcast Report Questioning transcribed from local broadcast report
    Zoning Power & Grid Water

    TMJ4 News broadcast report on Mount Pleasant, WI covering Mount Pleasant Village Board proceedings and community debate over grid capacity and utility rates, tax incentives and revenue projections (Segment 1).

    "Center near the foxconn site in Mount Pleasant, a company rep says that the proposal would likely bring. Hundreds of jobs. Taylor lumpkin has more. Microsoft officials are eager to get started on their project to begin building their next billion dollar data center in Mount Pleasant all of the infrastructure. That's not the size that we need. It's ready to go. Microsoft representative said there are"

    YouTube at 0:15 ↗ (opens in a new tab)
  2. Clip 2 · 1:30 Resident public comment Resident Public Comment transcribed from local broadcast report

    Resident interview in the TMJ4 News report on Mount Pleasant, WI addressing data center siting, utility demand, and neighborhood impacts before Mount Pleasant Village Board.

    "They enter Racine County. And that's something residents including alphonso gardner is happy to hear. He says he has some reservations about the company coming to the area. And once a tech company to help improve the lives of black families in the county, microsoft need to understand when they come here, they have to deal with everybody. Everybody has you can get an opportunity. Only 8% of blacks in this county a"

    YouTube at 1:30 ↗ (opens in a new tab)
Read full auto generated transcript (2 segments)

[0:15] TMJ4 News Broadcast Report: Center near the foxconn site in Mount Pleasant, a company rep says that the proposal would likely bring. Hundreds of jobs. Taylor lumpkin has more. Microsoft officials are eager to get started on their project to begin building their next billion dollar data center in Mount Pleasant all of the infrastructure. That's not the size that we need. It's ready to go. Microsoft representative said there are

[1:30] Resident public comment: They enter Racine County. And that's something residents including alphonso gardner is happy to hear. He says he has some reservations about the company coming to the area. And once a tech company to help improve the lives of black families in the county, microsoft need to understand when they come here, they have to deal with everybody. Everybody has you can get an opportunity. Only 8% of blacks in this county a