Port Washington has 1 data center on the record; it is being built. No city rule about data centers is on the record for Port Washington yet. Ozaukee County's own decisions are on the Ozaukee County page.
Blank cell: not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record.
What Port Washington has decided
No facility record and no county act is on the record for Port Washington yet. The Wisconsin state rule applies: case by case.
Wisconsin state rule · case by case Wisconsin Department of Natural Resources found Vantage will meet air pollution limits and granted preliminary approval for air pollution control permits. (April 15, 2026) · Verified . wpr.org (opens in a new tab)local outlet
September 10, 2026Port Washington, WIPort Washington Common Council Cloverleaf AI Data Center Community HearingPort Washington Common Council3 clips
On September 10, 2026, Port Washington residents and officials scrutinized developers of the proposed 1,900 acre, multi gigawatt Cloverleaf AI data center campus over Lake Michigan cooling water withdrawals, We Energies transmission infrastructure, and farmland annexation.
Ted Neitzke, Mayor, City of Port WashingtonElected Officialtranscribed from local broadcast report
"high ranking executives from Vantage Data Centers, the company that is building that massive complex, as well as Oracle, one of two companies that will operate some of those four data centers, were here tonight to connect with the community. They said that this has been part of their community engagement plan all along. Though, as you mentioned, the timing to this open style house of meeting tonight is"
Resident public commentResident Public Commenttranscribed from local broadcast report
"progress made on this complex, which is known as Project Lighthouse, just west, again, of I-43 here in Port Washington. When it is done, the $15 billion project will have four data centers covering 2 and 1/2 million square feet. They'll be operated by Oracle and OpenAI with 1,000 permanent jobs. Now, just this week, a former OpenAI researcher accused the company of recklessly racing towards"
FOX6 News Milwaukee Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"trying to prove they will not hurt this community. Not all data centers are equal. We want to be part of the community. This is not just a construction project and temporary. We will be here for many, many years. And so, we're excited to be part of the community of Port Washington. It's part of being a good neighbor, and by my definition, responsible data center building is"
March 20, 2026Port Washington, WIPort Washington limiting outdoor construction at data center sitePort Washington Plan Commission2 clips
WISN 12 News report on Port Washington Plan Commission and community proceedings in Port Washington, WI: Port Washington limiting outdoor construction at data center site (March 20, 2026).
WISN 12 News Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"Neighbors of the new data center making their outrage known at a thursday planning commission meeting. Like kirk day. Heck. I’ve been here before. Who I spoke with over the phone friday. The backup beeper bells, the tracked equipment, the tailgates on quad axles, ground vibrations. The city says it listed voting to limit the hours of outdoor construction. We now lay down much clearer expectations for what it."
WISN 12 News Broadcast ReportBroadcast Reporttranscribed from local broadcast report
"During the week, the board voted unanimously for this construction change, but it’s a change that does not go into effect for several weeks. 24 hour construction is still allowed here until april 18th. You can’t stop a project of this magnitude overnight. It takes a wind down period of time, and we felt it was a really good compromise. Is there any regret allowing the 24 hour construction? Oh boy, that’s a with the 24 hour construction, had we known the volume of traffic, etc., we."
Ted Neitzke & Cloverleaf Infrastructure RepresentativesMayor of Port Washington & Project Developer
Venue:Port Washington Common Council Concept Briefing on Cloverleaf Campus
"Described the proposed Port Washington AI data center campus as a clean technology tax base investment compatible with municipal utility infrastructure."
Column B · Primary Government Record
Port Washington 1,900 Acre Farmland Annexation & We Energies Multi Gigawatt Load Filing
Port Washington Annexation & Utility Review (Sept 10, 2026 Hearing)
Agency or Venue:Port Washington Common Council & Public Service Commission of Wisconsin
"Municipal annexation and utility filings documented a 1,900 acre footprint requiring multi gigawatt We Energies transmission upgrades and Lake Michigan cooling water withdrawals, prompting intense resident opposition on September 10, 2026."
Summer Strand, PSC Chair, stated the decision was not opposition to data centers but rather that the application represented a cautionary tale of unrealistic speed to power expectations colliding with a deliberative regulatory process.
Summer Strand, Wisconsin Public Service Commission Chair · September 16, 2026 · paraphrased · VernonReporter (opens in a new tab)news outlet
Brendan Conway, We Energies spokesperson, said the power line project is a critical part of delivering generation to the data center
On Sept. 23, a Vantage official texted Port Washington Mayor Ted Neitzke about the governor's office seeking more information on why an EIS would kill the project
Vantage said backup generators are intended for emergencies and required testing and maintenance, running monthly with no more than four generators for 15 minutes, annually one at a time for an hour, and for 15 minutes to validate repairs
Vantage said generators will primarily be used one or a few at a time during monthly testing, well below DNR's established limit of 50 hours per generator annually
Mark Freeman, Vice President of Global Marketing for Vantage Data Centers, said the company is committed to working with the city on construction alignment
Port Mayor Ted Neitzke said 24 hour exterior construction would end in about a month, ending exterior 24 hour work weeks earlier than Vantage anticipated end of May
43 miles awayDodge County: 1 data center on the record.
43 miles awayCalumet County: 1 data center on the record.
Distances run between the centers the Census Bureau gives each place. Every Wisconsin county.
Disclosed figures
902 MW power, 1,000 jobs
Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.
Power, water, jobs and tax
Figure
Disclosed total
Disclosed
Without a figure
Basis
Power
902 MW
1
0
1 the developer's figure
Water, stated per day
0
1
Water, stated per year
0
1
Permanent jobs
1,000 jobs
1
0
1 the developer's figure
Tax each year
0
1
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
Use
Records
Power
Water
Jobs
Tax each year
No stated use
1
902 MW
1,000 jobs
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 1 tracked facility in Port Washington is for.
How the facilities are cooled
No source on file states how any of the 1 tracked facility in Port Washington is cooled.
FiguresOnly what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
LicenseData CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this pageData Center Record, "Data centers in Port Washington, Ozaukee County, Wisconsin", https://datacenterrecord.org/states/wi/ozaukee-county/port-washington, updated November 6, 2026.CSV · JSON
Data Center Record, "Data center records in Port Washington, Ozaukee County, Wisconsin", https://datacenterrecord.org/states/wi/ozaukee-county/port-washington. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
Researcher view · Port Washington, Ozaukee County, Wisconsin · 1 record, 0 rule rows · Census GEOID 5564450 · basis and source tier on every row · verified November 6, 2026