Vantage Port Washington Data Center, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

16 events, August 2025 to September 10, 2026. Also on the record, under the month each belongs to: 68 statements, 83 figures from other sources and 99 lines that are not events of their own. The facts, newest first: the record; the place: Wisconsin.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

2025 8 events

  1. (the month its own sentence names; no day is given; filed under Oct 24, 2025)

    Entry

    The Port Washington Common Council approved the development agreement for the project in August [44]

  2. (source date; the content gives no date of its own)

    approved

    Vantage Data Centers, OpenAI, and Oracle plan to invest more than $15 billion at a Port Washington data center campus [44]

  3. Also in October 2025: 2 statements and 12 lines that are not events of their own
    1. (said in the source itself)

      Statement · unnamed Vantage Data Centers representative

      In 2019, Vantage made a company decision to no longer use evaporative cooling systems in its data center design. YouTube video

    2. (said in the source itself)

      Statement · unnamed Vantage Data Centers representative

      The data center will not draw water directly from the lake, but will obtain water through existing Port Washington infrastructure. YouTube video

    3. (source date; the content gives no date of its own)

      Entry

      Vantage said the data center campus will preserve 172 acres to support biodiversity and provide natural sound mitigation [44]

    4. (source date; the content gives no date of its own)

      Entry

      The four data center buildings are expected to need 1.3 gigawatts of electricity [44]

    5. (source date; the content gives no date of its own)

      Entry

      The Lighthouse campus includes four data center buildings [44]

    6. (source date; the content gives no date of its own)

      Entry

      The Lighthouse campus is part of OpenAI and Oracle's $500 billion Stargate program [44]

    7. (source date; the content gives no date of its own)

      Entry

      The Port Washington data center campus is named Lighthouse [44]

    8. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers is underwriting 100 percent of the power infrastructure investment with a dedicated electricity rate from WEC Energy Group utility We Energies [44]

    9. (source date; the content gives no date of its own)

      Entry

      The data center buildings will use a closed loop liquid cooling system [44]

    10. (source date; the content gives no date of its own)

      Entry

      A $1.4 billion transmission line project from American Transmission Co. is proposed to support the Lighthouse campus [44]

    11. (source date; the content gives no date of its own)

      Entry

      The Lighthouse campus is roughly 670 acres [44]

    12. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers will have around 330 employees at the Lighthouse campus [44]

    13. (source date; the content gives no date of its own)

      Entry

      OpenAI and Oracle will have around 700 jobs at the Lighthouse campus after construction [44]

    14. (source date; the content gives no date of its own)

      Entry

      The data center campus could create more than 4,000 construction jobs [44]

  4. (source date; the content gives no date of its own)

    being built

    TID would remain open for up to 20 years or until Vantage is reimbursed for all costs [37]

  5. Also in November 2025: 5 statements and 4 figures from other sources
    1. (said in the source itself)

      Statement · Christine Le Jeune, Great Lakes Neighbors United

      Christine Le Jeune, Great Lakes Neighbors United, expressed concern that the TID was passed with little community input wpr.org local outlet

    2. (said in the source itself)

      Statement · Ted Neitzke IV, Port Washington Mayor

      Mayor Ted Neitzke said Vantage is putting all capital up front for infrastructure, city pays them back from TID revenues wpr.org local outlet

    3. (said in the source itself)

      Statement · Todd Taves, Ehlers Public Finance Advisors

      Todd Taves, Ehlers Public Finance Advisors, said the $175 million infrastructure cost estimate is conservative wpr.org local outlet

    4. (said in the source itself)

      Statement · Scott Lone, Port Washington resident

      Scott Lone, resident, said the council should vote against the TID creation and invest in people and local businesses instead wpr.org local outlet

    5. (source date; the content gives no date of its own)

      Figure · wpr.org

      2,700,000,000 USD: Project expected to contribute $2.7 billion to regional economy, according to Rebecca Gries, Milwaukee 7 Regional Partnership executive director wpr.org local outlet

    6. (source date; the content gives no date of its own)

      Figure · wpr.org

      700 jobs: OpenAI and Oracle will have around 700 jobs at campus, with Vantage having around 330 employees wpr.org local outlet

    7. (source date; the content gives no date of its own)

      Figure · wpr.org

      4,000 jobs: Vantage said campus could create more than 4,000 construction jobs wpr.org local outlet

    8. (source date; the content gives no date of its own)

      Figure · wpr.org

      175,000,000 USD: Vantage will pay upfront estimated $175 million for infrastructure improvements including water, sewer, and road improvements wpr.org local outlet

    9. (said in the source itself)

      Statement · unnamed narrator

      The Vantage Data Centers Lighthouse Campus is being built using Wisconsin's clean renewable energy without increasing rates on residents. YouTube video

  6. (the month its own sentence names; no day is given; filed under Aug 19, 2026)

    Entry

    Data center campus broke ground in December 2025 [28]

  7. (source date; the content gives no date of its own)

    Entry

    Groundbreaking held December 17, 2025, with construction beginning on 672 acre site [36]

  8. (the day its own sentence names; filed under Dec 23, 2025)

    Entry

    Vantage Data Centers Lighthouse Campus groundbreaking held December 17, 2025 [45]

  9. (source date; the content gives no date of its own)

    Entry

    Vantage Data Centers broke ground on a $15 billion data center campus in Port Washington on December 18, 2025 [43]

  10. (source date; the content gives no date of its own)

    Entry

    Ceremonial groundbreaking held December 19, 2025 [48]

  11. Also in December 2025: 9 statements, 12 figures from other sources and 10 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      End users are OpenAI and Oracle [36]

    2. (source date; the content gives no date of its own)

      Entry

      Developer is Vantage Data Centers [36]

    3. (said in the source itself)

      Statement · Great Lakes Neighbors United

      Opposition from residents has grown with protests and a recall effort announced against the mayor Milwaukee Business News local outlet

    4. (said in the source itself)

      Statement · Ted Neitzke, Port Washington Mayor

      Mayor Ted Neitzke said the project could create jobs, support local schools and help ensure future employment opportunities Milwaukee Business News local outlet

    5. (said in the source itself)

      Statement · Vantage Data Centers

      Part of Stargate project, a $500 billion public private initiative Milwaukee Business News local outlet

    6. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      1,400,000,000 USD: American Transmission Co. planning a $1.4 billion electrical infrastructure project to meet facility power needs Milwaukee Business News local outlet

    7. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      672 acres: Project is 672 acres Milwaukee Business News local outlet

    8. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      1.3 GW: Expected power use is 1.3 gigawatts with later phases potentially up to 3.5 gigawatts Milwaukee Business News local outlet

    9. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      15,000,000,000 USD: Project cost is $15 billion Milwaukee Business News local outlet

    10. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      200 workers: Expected to create thousands of construction jobs, with about 200 workers in 2025, 3,500 in 2026, 5,000 in 2027, and 2,000 in 2028 Milwaukee Business News local outlet

    11. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      3,000,000 USD: Vantage committed $3 million to Valley Creek Corridor Revitalization Project Milwaukee Business News local outlet

    12. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      300 jobs: Vantage plans to employ about 300 people at the data center, with tenant companies expected to employ an additional 700 Milwaukee Business News local outlet

    13. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      10,000 gallons per day: Expected to use up to 10,000 gallons of water per day for cooling operations Milwaukee Business News local outlet

    14. (source date; the content gives no date of its own)

      Entry

      The project is part of OpenAI and Oracle's $500 billion Stargate AI data center initiative [43]

    15. (source date; the content gives no date of its own)

      Entry

      The project is expected to create 1,000 permanent jobs [43]

    16. (source date; the content gives no date of its own)

      Entry

      The project is expected to create more than 4,000 construction jobs [43]

    17. (source date; the content gives no date of its own)

      Entry

      The project is expected to be completed in 2028 [43]

    18. (source date; the content gives no date of its own)

      Entry

      The data center campus has 902 megawatts of capacity [43]

    19. (source date; the content gives no date of its own)

      Entry

      The data center campus includes four buildings totaling 2.5 million square feet [43]

    20. (source date; the content gives no date of its own)

      Entry

      The data center campus is 672 acres [43]

    21. (said in the source itself)

      Statement · Mike Beaster, Great Lakes Neighbors United

      The group is concerned about the data center's expected 1.3 gigawatt electricity draw and its effect on local utility rates wpr.org local outlet

    22. (said in the source itself)

      Statement · Mike Beaster, Great Lakes Neighbors United

      The group is worried about how much water the $15 billion data center will use for cooling wpr.org local outlet

    23. (said in the source itself)

      Statement · Mike Beaster, Great Lakes Neighbors United

      According to the recall group, the mayor has been secretive about the data center details and hasn't taken residents' concerns seriously wpr.org local outlet

    24. (said in the source itself)

      Statement · Mike Beaster, Great Lakes Neighbors United

      Great Lakes Neighbors United is working to recall Port Washington Mayor Ted Neitzke wpr.org local outlet

    25. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers building for Oracle and OpenAI [48]

    26. (said in the source itself)

      Statement · Sebastian Elischer, Great Lakes Neighbors United

      Recall effort filed against Mayor Ted Neitzke over data center concerns TMJ4 News local outlet

    27. (said in the source itself)

      Statement · Dana Adams, Vantage Data Centers North America President

      Project is a cornerstone of Project Stargate, a $500 billion public private AI initiative Ozaukee Press local outlet

    28. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      675 acres: 675 acre site for Vantage Lighthouse Campus Ozaukee Press local outlet

    29. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      1.3 GW: 1.3 gigawatts of power capacity for Lighthouse Campus Ozaukee Press local outlet

    30. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      11,000 gallons per day: 11,000 gallons of water per day usage at Lighthouse Campus Ozaukee Press local outlet

    31. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      15,000,000,000 USD: $15 billion cost for Vantage Lighthouse Campus Ozaukee Press local outlet

2026 8 events

  1. Also in January 2026: 1 statement and 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers is planting over 2,000 native trees throughout the project site. [51]

    2. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers is preserving over 150 acres of land that will be restored to a native Wisconsin landscape. [51]

    3. (said in the source itself)

      Statement · Emily Backus, Sustainability Director, North America

      No water will be directly piped from Lake Michigan for the Lighthouse Campus. YouTube video

    4. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers Lighthouse Campus under construction in Port Washington [10]

  2. Also in February 2026: 2 statements, 5 figures from other sources and 2 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Motion hearing scheduled for February 13, 2026 [9]

    2. (said in the source itself)

      Statement · Dale Kooyenga, President, Metropolitan Milwaukee Association of Commerce

      Business groups argue ordinance conflicts with state law delegating TID authority to municipal governing bodies wpr.org local outlet

    3. (source date; the content gives no date of its own)

      Figure · wpr.org

      175,000,000 USD: To qualify for any incentive from the TID, Vantage must spend $175 million on installing, upgrading and repairing infrastructure. wpr.org local outlet

    4. (source date; the content gives no date of its own)

      Figure · wpr.org

      187,000,000 USD: The city will pay the developer $187 million in interest payments because the company will front the cost of building infrastructure supporting the project. wpr.org local outlet

    5. (source date; the content gives no date of its own)

      Figure · wpr.org

      120,000,000 USD: The TID's base property value is being certified in 2026 instead of 2025, adding $120 million in valuation going forward. wpr.org local outlet

    6. (source date; the content gives no date of its own)

      Figure · wpr.org

      30,000,000 USD: If the project delivers on the property value increases estimated in the city's project plan, Port Washington and other local taxing authorities would see an increase of more than $30 million annually in tax revenue from the project. wpr.org local outlet

    7. (source date; the content gives no date of its own)

      Figure · wpr.org

      458,000,000 USD: The TID provides property tax reimbursement and interest payments to the developer totaling more than $458 million over the next 18 years. wpr.org local outlet

    8. (source date; the content gives no date of its own)

      Entry

      The data center campus in Port Washington has been under construction for over two months [50]

    9. (said in the source itself)

      Statement · Edwin Van Velzen, Sr. Vice President for Construction, Vantage Data Centers

      The data center buildings are being constructed concurrently YouTube video

  3. Also in March 2026: 9 statements, 2 figures from other sources and 4 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Construction on the Vantage Data Centers Lighthouse Campus was originally limited to a 12 hour period but the city later approved 24 hour construction on weekdays. [32]

    2. (said in the source itself)

      Statement · Ted Neitzke, Port Washington Mayor

      Port Washington Mayor Ted Neitzke said the new work hours are necessary to help get the project back on track after delays. wpr.org local outlet

    3. (said in the source itself)

      Statement · Kim Tydrick, Port Washington resident

      Residents cite bright work lights shining 24 hours, incessant backup beeping, traffic, emissions and dust Urban Milwaukee local outlet

    4. (said in the source itself)

      Statement · Ted Neitzke, Mayor

      Mayor Ted Neitzke said 24 hour work hours necessary to help project recover from delays and generate tax revenue Urban Milwaukee local outlet

    5. (said in the source itself)

      Statement · Dean Wiegert, Port Washington resident

      Dean Wiegert, town resident, told Common Council 24 hour construction is hellish and backup alarms on trucks wake him throughout the night Ozaukee Press local outlet

    6. (said in the source itself)

      Statement · Ted Neitzke, Port Mayor

      Port Mayor Ted Neitzke said 24 hour exterior construction would end in about a month, ending exterior 24 hour work weeks earlier than Vantage anticipated end of May Ozaukee Press local outlet

    7. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      675 acres: Vantage Data Centers Lighthouse Campus is 675 acres Ozaukee Press local outlet

    8. (source date; the content gives no date of its own)

      Entry

      Rules do not go into effect until April 18 [47]

    9. (said in the source itself)

      Statement · Ted Neitzke, Mayor of Port Washington

      Port Washington Mayor Ted Neitzke said the one month delay gives developer time to adjust worker schedules TMJ4 News local outlet

    10. (said in the source itself)

      Statement · Vantage Data Centers

      Vantage stated they are committed to balancing schedule with community needs TMJ4 News local outlet

    11. (source date; the content gives no date of its own)

      Entry

      New construction hour restrictions take effect April 18, 2026 [35]

    12. (source date; the content gives no date of its own)

      Entry

      Construction was previously allowed 24 hours a day during weekdays [35]

    13. (said in the source itself)

      Statement · Mark Freeman, Vice President of Global Marketing, Vantage Data Centers

      Mark Freeman, Vice President of Global Marketing for Vantage Data Centers, said the company is committed to working with the city on construction alignment wpr.org local outlet

    14. (said in the source itself)

      Statement · Ted Neitzke, Mayor of Port Washington

      Port Washington Mayor Ted Neitzke said 24 hour construction was always going to be temporary wpr.org local outlet

    15. (source date; the content gives no date of its own)

      Figure · wpr.org

      15,000,000,000 USD: Vantage Data Centers is building a $15 billion data center campus in Port Washington wpr.org local outlet

  4. (source date; the content gives no date of its own)

    reported

    Construction on the site began in December after DNR permitting was completed [54]

  5. (source date; the content gives no date of its own)

    being built

    $15 billion Port Washington data center project under construction [16]

  6. Also in April 2026: 2 statements, 9 figures from other sources and 11 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Vantage is building the data center to LEED standards with a goal of 41% biodiversity net gain [18]

    2. (source date; the content gives no date of its own)

      Entry

      The project is targeted for completion in 2028 [18]

    3. (source date; the content gives no date of its own)

      Entry

      Vantage is contributing $3 million to the Valley Creek project intended to improve water quality and reduce downstream flooding [18]

    4. (source date; the content gives no date of its own)

      Entry

      Vantage is laying 48.3 miles of water lines at the site with a closed loop system using less water than Port Washington public schools [18]

    5. (source date; the content gives no date of its own)

      Entry

      The buildings should be weather tight by the end of 2026 [18]

    6. (source date; the content gives no date of its own)

      Entry

      Buildings are being constructed sequentially with work on each structure starting 30 to 45 days after the last [18]

    7. (source date; the content gives no date of its own)

      Entry

      About 1,000 workers are on site each day, with the workforce expected to swell to about 5,000 at peak construction [18]

    8. (source date; the content gives no date of its own)

      Entry

      The campus will have four data center buildings, two measuring about 1,800 by 400 feet (560,000 and 725,000 square feet respectively), about 27 feet tall [18]

    9. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers Lighthouse Campus is a 675 acre data center project in Port Washington [18]

    10. (source date; the content gives no date of its own)

      Entry

      Construction of roughly 670 acre campus slated to wrap up in 2028 [13]

    11. (source date; the content gives no date of its own)

      Entry

      Vantage applying for permits to use 45 diesel fired generators for backup power [13]

    12. (source date; the content gives no date of its own)

      Figure · wpr.org

      3.5 GW: Roughly 670 acre campus could need up to 3.5 gigawatts of electricity wpr.org local outlet

    13. (source date; the content gives no date of its own)

      Figure · wpr.org

      48,500 tons annually: DNR estimated diesel engines could generate maximum of around 48,500 tons of greenhouse gas emissions annually, equivalent to around 11,000 gas powered vehicles for a year wpr.org local outlet

    14. (source date; the content gives no date of its own)

      Figure · wpr.org

      4,000 jobs: Data center campus could create more than 4,000 construction jobs and more than 1,000 permanent positions wpr.org local outlet

    15. (source date; the content gives no date of its own)

      Figure · wpr.org

      3 GW: We Energies proposing to add almost 3 gigawatts of power to meet data center energy demand wpr.org local outlet

    16. (source date; the content gives no date of its own)

      Figure · wpr.org

      960,000 to 1,290,000 dollars annually: Clean Wisconsin analysis estimated pollution from diesel generators could cause $960,000 to $1.29 million in annual public health costs wpr.org local outlet

    17. (source date; the content gives no date of its own)

      Figure · wpr.org

      324,000 gallons annually: Vantage proposing to limit fuel use to roughly 324,000 gallons annually wpr.org local outlet

    18. (said in the source itself)

      Statement · Ted Neitzke, Mayor of Port Washington

      The data center uses a closed loop cooling system that circulates water like a car radiator YouTube video

    19. (said in the source itself)

      Statement · Ted Neitzke, Mayor of Port Washington

      Data centers do not discharge like manufacturing plants and do not require clean air credits or significant discharge permitting YouTube video

    20. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      75,000 USD: Vantage Data Centers donated $75,000 to the Port Washington Saukville School District educational foundation TMJ4 News local outlet

    21. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      75,000 USD: Oracle donated $75,000 to the Port Washington Saukville School District educational foundation TMJ4 News local outlet

    22. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      75,000 USD: OpenAI donated $75,000 to the Port Washington Saukville School District educational foundation TMJ4 News local outlet

  7. Also in May 2026: 8 statements, 3 figures from other sources and 3 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Vantage applied for and received preliminary approval to install up to 45 diesel generators [46]

    2. (said in the source itself)

      Statement · Patti Plough, Fredonia neighbor and Responsible Energy Alliance advocate

      Patti Plough, Fredonia neighbor, leading opposition group against power lines routing through communities TMJ4 News local outlet

    3. (said in the source itself)

      Statement · Vantage Data Centers

      Vantage said generators will primarily be used one or a few at a time during monthly testing, well below DNR's established limit of 50 hours per generator annually TMJ4 News local outlet

    4. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      15,000,000,000 USD: Vantage Data Centers Port Washington project estimated at $15 billion TMJ4 News local outlet

    5. (said in the source itself)

      Statement · Ben Donajkowski, Port Washington resident

      Large dump trucks and construction equipment creating traffic congestion near data center Ozaukee Press local outlet

    6. (said in the source itself)

      Statement · Ben Donajkowski, Port Washington resident

      Traffic situation described as genuinely inexcusable Ozaukee Press local outlet

    7. (said in the source itself)

      Statement · Christy Knowles, Sheriff

      Vantage paying for traffic control and supplementing with flagmen Ozaukee Press local outlet

    8. (said in the source itself)

      Statement · Christy Knowles, Sheriff

      Traffic control expected to continue until at least October Ozaukee Press local outlet

    9. (source date; the content gives no date of its own)

      Entry

      The air permit is for 45 generators at the Vantage Lighthouse Campus [27]

    10. (source date; the content gives no date of its own)

      Decision · Ozaukee County (county)

      Ozaukee County is in an area of nonattainment for pollutants such as ozone under National Ambient Air Quality Standards spectrumnews1.com

    11. (said in the source itself)

      Statement · Mark Freeman, Vantage Data Centers Vice President of Global Marketing

      Vantage said backup generators are intended for emergencies and required testing and maintenance, running monthly with no more than four generators for 15 minutes, annually one at a time for an hour, and for 15 minutes to validate repairs Spectrum News local outlet

    12. (said in the source itself)

      Statement · Ciaran Gallagher, Clean Wisconsin Energy and Air Manager

      Clean Wisconsin found the data centers will add about $100,000 of health harms per year in Ozaukee County from backup diesel generators Spectrum News local outlet

    13. (source date; the content gives no date of its own)

      Figure · Spectrum News

      902 MW: Vantage Data Centers Lighthouse Campus in Port Washington will have four data centers totaling 902 megawatts of critical IT load Spectrum News local outlet

    14. (source date; the content gives no date of its own)

      Figure · Milwaukee Journal Sentinel

      15,000,000,000 USD: Vantage Data Centers is building a $15 billion facility in Port Washington, Wisconsin Milwaukee Journal Sentinel local outlet

  8. (the day its own sentence names; filed under Jul 10, 2026)

    Entry

    The DNR issued permits for the project on June 12 [42]

  9. (source date; the content gives no date of its own)

    Entry

    Vantage topped out second building at Lighthouse campus in Port Washington on June 26, 2026 [7]

  10. (the day its own sentence names; filed under Jul 1, 2026)

    Entry

    Topping out ceremony held June 26, 2026 for second of four data center buildings [33]

  11. Also in June 2026: 1 statement, 1 figure from another source and 1 line that is not an event of its own
    1. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers is operating a massive Port Washington project [8]

    2. (said in the source itself)

      Statement · Kristy Nieto, Wisconsin Public Service Commission commissioner

      Wisconsin Public Service Commissioner Kristy Nieto said Wisconsin customers should not pay to subsidize data center service TMJ4 News local outlet

    3. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      100,000,000 USD: Oracle holds BBB credit rating and argues tariffs could amount to more than $100 million annually TMJ4 News local outlet

  12. Also in July 2026: 16 statements, 33 figures from other sources and 12 lines that are not events of their own
    1. (said in the source itself)

      Statement · Victoria Tyson-Bloyd, Vantage Vice President of Construction

      Victoria Tyson Bloyd, vice president of construction for Vantage, said disruptions from dust should be lessened soon Ozaukee Press local outlet

    2. (said in the source itself)

      Statement · Michael Graham, Whiting Turner project lead

      Michael Graham, Whiting Turner project lead, said there were 85 ironworkers at peak on that building Ozaukee Press local outlet

    3. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      5,000,000 cubic yards: More than 5 million cubic yards of earth was moved on the site Ozaukee Press local outlet

    4. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      5,000 jobs: Workforce expected to reach 5,000 going into winter Ozaukee Press local outlet

    5. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      1,700 workers: Approximately 1,700 workers on site at time of ceremony Ozaukee Press local outlet

    6. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      2,500,000 square feet: Campus includes four data center buildings that total about 2.5 million square feet Ozaukee Press local outlet

    7. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      750,000 square feet: Second building is 750,000 square feet Ozaukee Press local outlet

    8. (said in the source itself)

      Statement · Tricia Braun, executive director of the Wisconsin Data Center Coalition

      Every direct data center job in Wisconsin supported more than six additional jobs elsewhere in the economy The Capital Times local outlet

    9. (source date; the content gives no date of its own)

      Entry

      DNR determined it satisfied environmental obligations on December 9 for the Vantage project [11]

    10. (said in the source itself)

      Statement · Public Service Commission

      Public Service Commission estimates Wisconsin will need 40 percent more peak demand power in coming years due to data center boom thecentersquare.com local outlet

    11. (said in the source itself)

      Statement · MEA and Sierra Club

      MEA and Sierra Club filed a lawsuit after state regulators abandoned a required environmental review for the Port Washington data center Sierra Club local outlet

    12. (said in the source itself)

      Statement · Vantage official (unnamed)

      On Sept. 23, a Vantage official texted Port Washington Mayor Ted Neitzke about the governor's office seeking more information on why an EIS would kill the project wpr.org local outlet

    13. (said in the source itself)

      Statement · Michael Greif, Midwest Environmental Advocates attorney

      Michael Greif, Midwest Environmental Advocates attorney, said case is about transparency and accountability thecentersquare.com local outlet

    14. (source date; the content gives no date of its own)

      Figure · wpr.org

      5.4 GW: Environmental groups say data centers are driving construction of 5.4 gigawatts of new or updated gas fired power plants wpr.org local outlet

    15. (source date; the content gives no date of its own)

      Figure · wpr.org

      3.5 GW: The project could require up to 3.5 gigawatts of electricity in the future wpr.org local outlet

    16. (source date; the content gives no date of its own)

      Figure · wpr.org

      40 percent: A draft energy assessment released by the Public Service Commission of Wisconsin found electricity demand could grow more than 40 percent by 2032 due to demand from hyperscale data centers wpr.org local outlet

    17. (source date; the content gives no date of its own)

      Figure · wpr.org

      1.3 GW: The first phase of the project would use 1.3 gigawatts of energy, enough to power 640,000 homes wpr.org local outlet

    18. (source date; the content gives no date of its own)

      Figure · Milwaukee Business News

      670 acres: Vantage Port Washington project is $15 billion for a 670 acre site Milwaukee Business News local outlet

    19. (source date; the content gives no date of its own)

      Figure · wpr.org

      672 acres: The data center campus spans 672 acres and includes four data centers wpr.org local outlet

    20. (source date; the content gives no date of its own)

      Figure · thecentersquare.com

      1,500,000,000 USD: Data centers are beneficiary of estimated $1.5 billion in initial foregone state sales tax from four data center projects thecentersquare.com local outlet

    21. (source date; the content gives no date of its own)

      Figure · thecentersquare.com

      2,100,000,000 USD: Lawmakers estimated the $2.1 billion project will use as much electricity as the city of Los Angeles thecentersquare.com local outlet

    22. (source date; the content gives no date of its own)

      Figure · wpr.org

      4.7 acres: The project would result in filling 4.7 acres of wetlands wpr.org local outlet

    23. (source date; the content gives no date of its own)

      Entry

      Public Service Commission of Wisconsin released final environmental impact statement for Port Washington data center transmission lines [12]

    24. (source date; the content gives no date of its own)

      Entry

      Second building on campus recently topped out [31]

    25. (source date; the content gives no date of its own)

      Entry

      Port Washington facility called Lighthouse [31]

    26. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      11,800,000 gallons: Closed loop water cooling system uses 11.8 million gallons of water, roughly 18 Olympic sized swimming pools, but only once and is then recycled TMJ4 News local outlet

    27. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      1,000 employees: Vantage expects 1,000 employees on site at Port Washington facility when combined with customers Oracle and OpenAI TMJ4 News local outlet

    28. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      15,000,000,000 USD: Vantage forecasting $15 billion of investment in the Port Washington project TMJ4 News local outlet

    29. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      4,000 jobs: Vantage predicting 4,000 construction jobs TMJ4 News local outlet

    30. (source date; the content gives no date of its own)

      Entry

      Total building area planned for the Port Washington campus is 2.5 million square feet. [53]

    31. (source date; the content gives no date of its own)

      Entry

      Number of data centers planned for the Port Washington campus is 4. [53]

    32. (source date; the content gives no date of its own)

      Entry

      Port Washington Lighthouse Data Center campus size is 672 acres. [53]

    33. (source date; the content gives no date of its own)

      Entry

      Building area of the Port Washington campus is 2.5 million square feet. [52]

    34. (source date; the content gives no date of its own)

      Entry

      Port Washington campus will have 4 data centers. [52]

    35. (source date; the content gives no date of its own)

      Entry

      Port Washington campus is 672 acres. [52]

    36. (source date; the content gives no date of its own)

      Entry

      Vantage expects 1,000 employees on site at Port Washington when combined with its customers Oracle and OpenAI. [52]

    37. (source date; the content gives no date of its own)

      Entry

      Port Washington water utility installing two new water meters to track data center facility water usage [15]

    38. (said in the source itself)

      Statement · Dana Adams, Vantage North America president

      Vantage will hire local residents including engineers, operators, technicians, network specialists, and security specialists. YouTube video

    39. (said in the source itself)

      Statement · Ryan Kehoe, Vantage VP of operations

      The rooftop cooling system is relatively quiet by industry standards because much of the sound vectors upwards. YouTube video

    40. (said in the source itself)

      Statement · Dana Adams, Vantage North America president

      Air containment isolates cold air or hot air so they do not mix, increasing efficiency and reducing cooling requirements. YouTube video

    41. (said in the source itself)

      Statement · Ryan Kehoe, Vantage VP of operations

      The closed loop chilled water system requires only a one time fill of water. YouTube video

    42. (said in the source itself)

      Statement · Dana Adams, President, Vantage Data Centers North America

      Vantage will hire local residents to serve as engineers, electrical and mechanical operators, technicians, network specialists, and security specialists. YouTube video

    43. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      15,000,000,000 USD: Port Washington Lighthouse facility is $15 billion investment TMJ4 News local outlet

    44. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      22,000 gallons daily: Vantage facility will use 22,000 gallons of water daily for kitchens and bathrooms TMJ4 News local outlet

    45. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      3,000,000 USD: Vantage committed $3 million to fund watershed restoration project in Port Washington for Valley Creek Corridor TMJ4 News local outlet

    46. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      12,000,000 gallons: One time use of about 12 million gallons, equivalent to 18 Olympic sized swimming pools, for cooling TMJ4 News local outlet

    47. (source date; the content gives no date of its own)

      Figure · YouTube

      15,000,000,000 dollars: Cost of Vantage data center project in Ozaukee County is 15 billion dollars. YouTube video

    48. (said in the source itself)

      Statement · Dana Adams, Vantage North America President

      Vantage North America President Dana Adams said the facility will support Oracle and their end user OpenAI running AI workloads out of the building. TMJ4 News local outlet

    49. (said in the source itself)

      Statement · Dana Adams, Vantage North America President

      Tax revenue from the facility will begin flowing predominantly when construction is complete. TMJ4 News local outlet

    50. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      65,000,000 USD: Vantage has paid $65 million in property taxes in Virginia since 2019. TMJ4 News local outlet

    51. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      130 workers: Vantage currently employs about 130 workers at a campus location in Virginia. TMJ4 News local outlet

    52. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      1,000 employees: Vantage expects a combined 1,000 employees with its two biggest customers once the Port Washington facility opens. TMJ4 News local outlet

    53. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      458,000,000 USD: Vantage will pay property taxes in Port Washington over the next 20 years through a Tax Incremental District to cover $458 million in infrastructure costs for the project. TMJ4 News local outlet

    54. (said in the source itself)

      Statement · Brendan Conway, We Energies spokesperson

      No costs to serve data centers will be shifted to other customers TMJ4 News local outlet

    55. (said in the source itself)

      Statement · Brendan Conway, We Energies spokesperson

      Data centers have to pay their full costs under the data center rate structure TMJ4 News local outlet

    56. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      15,000,000,000 USD: Vantage Data Centers is building a $15 billion hyper scale AI facility in Port Washington TMJ4 News local outlet

    57. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      1,500,000,000 USD: Transmission costs are estimated at $1.5 billion in high voltage lines needed to move all that power TMJ4 News local outlet

    58. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      5,000,000,000 USD: Vantage estimates it will invest $5 billion in energy infrastructure, including solar, wind and battery storage TMJ4 News local outlet

    59. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      1,400 MW: The Port Washington facility will require 1,400 megawatts of power TMJ4 News local outlet

    60. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      2,000 MW: Vantage says it is paying for the buildout of 2,000 megawatts of energy TMJ4 News local outlet

    61. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      1,300,000 homes: The data center facility will consume more energy than 1.3 million Wisconsin homes TMJ4 News local outlet

  13. (source date; the content gives no date of its own)

    being built

    Construction continues on Vantage Data Centers' AI data center campus project in Port Washington, Wisconsin as of August 6, 2026 [14]

  14. (source date; the content gives no date of its own)

    stalled

    Public Service Commission of Wisconsin revoked American Transmission Company's completeness determination for the Ozaukee County Distribution Interconnection Project on August 6, 2026 [49]

  15. Also in August 2026: 7 statements, 6 figures from other sources and 18 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      Aerial drone video shows growth of Port Washington AI campus under construction. [17]

    2. (source date; the content gives no date of its own)

      Entry

      Public hearings planned for August 18 in Fredonia and August 19 in Kiel on this project are cancelled [49]

    3. (source date; the content gives no date of its own)

      Entry

      The project impacts parts of Ozaukee and Washington counties as well as Calumet, Fond du Lac and Sheboygan counties [49]

    4. (source date; the content gives no date of its own)

      Entry

      ATC's project includes new power lines, rebuilding existing power lines, building up to five new substations, and maintenance on existing power lines for the Port Washington AI data center [49]

    5. (said in the source itself)

      Statement · Patti Plough, Pastor, Responsible Energy Alliance

      Pastor Patti Plough of Responsible Energy Alliance celebrated the PSC decision WISN local outlet

    6. (said in the source itself)

      Statement · Public Service Commission of Wisconsin

      ATC filed numerous substantial changes to its project application during the proceedings, which led to the revocation WLUK local outlet

    7. (said in the source itself)

      Statement · Summer Strand, PSC Chairperson

      PSC Chairperson Summer Strand described ATC application as clearly underwater and revoked completeness determination WISN local outlet

    8. (source date; the content gives no date of its own)

      Entry

      American Transmission Co. hoped to begin construction in December and complete the buildout by the end of 2027. [34]

    9. (said in the source itself)

      Statement · Summer Strand, PSC Chair

      PSC chair Summer Strand said ATC filed or refiled 564 application documents after receiving a completeness determination late last year. wpr.org local outlet

    10. (source date; the content gives no date of its own)

      Figure · wpr.org

      1,300,000,000 to 1,700,000,000 dollars: The cost of the Ozaukee County Distribution project was estimated to be between $1.3 billion and $1.7 billion. wpr.org local outlet

    11. (said in the source itself)

      Statement · Haley Dobre, Pier Street Development developer

      Haley Dobre, Pier Street Development, said job growth from the $15 billion data center complex north of downtown has increased demand for housing TMJ4 News local outlet

    12. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      15,000,000,000 USD: Data center complex in Port Washington valued at $15 billion TMJ4 News local outlet

    13. (source date; the content gives no date of its own)

      Entry

      Vantage is paying for traffic improvements and law enforcement officers for traffic control [28]

    14. (source date; the content gives no date of its own)

      Entry

      Project is expected to be completed in 2028 [28]

    15. (source date; the content gives no date of its own)

      Entry

      Traffic lights were to be operational by August 24, 2026 [28]

    16. (source date; the content gives no date of its own)

      Entry

      Temporary traffic lights installed at highways 32 and H at I-43 interchange [28]

    17. (source date; the content gives no date of its own)

      Decision · Ozaukee County (county)

      Enhanced pedestrian control signal and lane widening at Highland Lane and Highland Drive intersection ozaukeepress.com

    18. (source date; the content gives no date of its own)

      Decision · Ozaukee County (county)

      County widening lanes at I-43 ramps and Highway LL, creating dedicated turn lanes ozaukeepress.com

    19. (said in the source itself)

      Statement · Roger Strohm, City Engineer, Port Washington

      City Engineer Roger Strohm said traffic at shift change is crazy Ozaukee Press local outlet

    20. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      5,000 workers: Vantage Data Centers Lighthouse Campus workforce increased to approximately 5,000 workers in summer 2026 Ozaukee Press local outlet

    21. (source date; the content gives no date of its own)

      Figure · Ozaukee Press

      672 acres: The 672 acre site will contain four data center buildings, warehouse, operations center and support buildings Ozaukee Press local outlet

    22. (source date; the content gives no date of its own)

      Entry

      Cloverleaf is reportedly looking to build a new hyperscale data center on the east side of Madison [1]

    23. (source date; the content gives no date of its own)

      Entry

      Cloverleaf Infrastructure was the original developer behind the Port Washington hyperscale data center before the project was transferred to Vantage [19]

    24. (source date; the content gives no date of its own)

      Entry

      Cloverleaf Infrastructure donated $100,000 to fund a sculpture at Coal Dock Park in Port Washington [19]

    25. (said in the source itself)

      Statement · MG&E

      Energy utility MG&E filed a new data center tariff proposal with the Public Service Commission civicmedia.us primary source

    26. (source date; the content gives no date of its own)

      Figure · NBC26

      100,000 USD: Former data center developer donated $100,000 sculpture to Coal Dock Park NBC26 local outlet

    27. (source date; the content gives no date of its own)

      Entry

      New traffic signal installed at I-43 interchange near data center construction in Port Washington [20]

    28. (source date; the content gives no date of its own)

      Entry

      Crews are working on widened lanes for trucks and dedicated right turn lanes at the interchange [22]

    29. (source date; the content gives no date of its own)

      Entry

      New temporary traffic signals were scheduled to go online Wednesday at the I-43 interchange [22]

    30. (source date; the content gives no date of its own)

      Entry

      Much of the traffic increase is attributed to data center construction traffic in the area [22]

    31. (source date; the content gives no date of its own)

      Figure · TMJ4 News

      76 percent: Exiting traffic at Interstate 43 interchange at exit 100 rose 76 percent between 2023 and August 2026 TMJ4 News local outlet

  16. (the day its own sentence names; filed under Sep 11, 2026)

    Entry

    Companies behind Project Lighthouse held an open house on September 10, 2026 [30]

  17. Also in September 2026: 6 statements, 8 figures from other sources and 23 lines that are not events of their own
    1. (source date; the content gives no date of its own)

      Entry

      County Highway LL was fully closed for months for the water and sewer project before being resurfaced [21]

    2. (source date; the content gives no date of its own)

      Entry

      Fire hydrants were installed as part of a city infrastructure project to extend water and sewer service to the data center complex [21]

    3. (source date; the content gives no date of its own)

      Entry

      Microsoft has proposed a data center development in Kenosha [23]

    4. (source date; the content gives no date of its own)

      Entry

      Campus will use a closed loop cooling system for water [29]

    5. (source date; the content gives no date of its own)

      Entry

      4,000 construction workers working on the project [29]

    6. (source date; the content gives no date of its own)

      Entry

      Campus expected to be operational beginning in and around 2028 [29]

    7. (source date; the content gives no date of its own)

      Entry

      Four data centers will be built at the campus [29]

    8. (source date; the content gives no date of its own)

      Entry

      Massive data center campus on 672 acres next to Interstate 43, around 30 minutes from Milwaukee [29]

    9. (source date; the content gives no date of its own)

      Entry

      Project Lighthouse is expected to open in 2028 [30]

    10. (source date; the content gives no date of its own)

      Entry

      Project Lighthouse is a four building data center campus [30]

    11. (source date; the content gives no date of its own)

      Entry

      Microsoft recently completed construction of the first of a series of data centers in Racine County in the village of Mount Pleasant [23]

    12. (source date; the content gives no date of its own)

      Entry

      Over 2,000 trees will be planted at the site and an 8 foot berm will be installed [23]

    13. (source date; the content gives no date of its own)

      Entry

      Campus is expected to be operational beginning in and around 2028 [23]

    14. (source date; the content gives no date of its own)

      Entry

      Four data centers will be built at Lighthouse campus [23]

    15. (source date; the content gives no date of its own)

      Entry

      Vantage Data Centers, Oracle and OpenAI are building a $15 billion data center campus called Lighthouse in Port Washington on 672 acres next to Interstate 43 [23]

    16. (source date; the content gives no date of its own)

      Entry

      Campus is named Lighthouse [29]

    17. (source date; the content gives no date of its own)

      Entry

      An 8 foot berm will be installed at the site [29]

    18. (source date; the content gives no date of its own)

      Entry

      Over 2,000 trees will be planted at the site [29]

    19. (said in the source itself)

      Statement · Port Washington residents

      Residents complained about construction mentioning noise and light pollution Urban Milwaukee local outlet

    20. (said in the source itself)

      Statement · Misty Allen, Vantage Data Centers vice president of public policy North America

      The campus will use a closed loop cooling system for water Urban Milwaukee local outlet

    21. (source date; the content gives no date of its own)

      Figure · Wisconsin Public Radio

      1,000 jobs: 1,000 permanent jobs will be at the campus once operational Wisconsin Public Radio local outlet

    22. (source date; the content gives no date of its own)

      Figure · Urban Milwaukee

      4,000 jobs: 4,000 construction workers are working on the project and 1,000 permanent jobs will be at the campus once it is operational Urban Milwaukee local outlet

    23. (source date; the content gives no date of its own)

      Figure · WLUK

      250,000 dollars: Companies contributed 250,000 dollars to local education foundation WLUK local outlet

    24. (source date; the content gives no date of its own)

      Figure · WLUK

      1,000 jobs: Project Lighthouse is expected to provide 1,000 permanent jobs WLUK local outlet

    25. (source date; the content gives no date of its own)

      Figure · WLUK

      2,500,000 square feet: Project Lighthouse encompasses 2.5 million square feet WLUK local outlet

    26. (source date; the content gives no date of its own)

      Figure · WLUK

      15,000,000,000 dollars: Project Lighthouse costs 15 billion dollars WLUK local outlet

    27. (source date; the content gives no date of its own)

      Entry

      American Transmission Company refiled a grid upgrade application on Monday, September 16, 2026 for infrastructure to serve the Port Washington data center. [24]

    28. (said in the source itself)

      Statement · Summer Strand, Wisconsin Public Service Commission Chair

      Summer Strand, PSC Chair, stated the decision was not opposition to data centers but rather that the application represented a cautionary tale of unrealistic speed to power expectations colliding with a deliberative regulatory process. VernonReporter local outlet

    29. (said in the source itself)

      Statement · Brendan Conway, We Energies spokesperson

      Brendan Conway, We Energies spokesperson, said the power line project is a critical part of delivering generation to the data center Milwaukee Journal Sentinel local outlet

    30. (source date; the content gives no date of its own)

      Figure · VernonReporter

      1,300,000,000 USD: The grid upgrade project is estimated at more than $1.3 billion and includes a high voltage transmission line and five new substations across Fond du Lac, Ozaukee, Sheboygan and Washington counties, needed to serve the data center by December 2027. VernonReporter local outlet

    31. (source date; the content gives no date of its own)

      Entry

      Tom Uttech's property is 52 acres [25]

    32. (source date; the content gives no date of its own)

      Entry

      American Transmission Co. application removed artist Tom Uttech's property from its proposed routes [25]

    33. (source date; the content gives no date of its own)

      Entry

      A transmission line to power the Port Washington data center is no longer planned to run through artist Tom Uttech's property [25]

    34. (said in the source itself)

      Statement · Wisconsin Institute for Law and Liberty

      Wisconsin Institute for Law and Liberty argued that transmission line plans would destroy the landscape that shaped Tom Uttech's artistic career The Center Square local outlet

    35. (said in the source itself)

      Statement · Wisconsin Institute for Law and Liberty

      The Uttechs did not plan to sell the property so it would have needed to be taken by eminent domain The Center Square local outlet

    36. (source date; the content gives no date of its own)

      Entry

      Ozaukee County Distribution Interconnection Project filed with PSC [26]

    37. (source date; the content gives no date of its own)

      Figure · wislawjournal.com

      175,000,000 USD: TID No. 5 will fund approximately $175 million in infrastructure improvements for the data center campus. wislawjournal.com local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Slug
vantage-port-washington-data-center-wi
Status value
under_construction
Events on the timeline
16
Under the months
250
Stage changes
6
Decisions
3
Statements
68
Figures
83
Entries and decisions under the months
99