● Proposed Campus Announced June 1, 2026 · ValorC3

ValorC3 Boise Data Center

Location Boise, Ada County, Idaho city centroid Town level, the center of the city

Overview, regulatory gates and specifications

ValorC3 secured a credit facility to fund a 10 MW data center in Boise, Idaho. [3] ValorC3 Boise data center built in 2020 using hybrid cooling [4]

Verified Site & Permit Summary
Verified address
Boise, Ada County, Idaho city centroid
Operator / developer
ValorC3
Permit / registry ID
KBOI on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
ValorC3 as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Lauren McLean

Boise Mayor

DID Recorded statement at KBOI (September 23, 2026) [3]
SAID Boise Mayor Lauren McLean stated opposition to proposed data center on federal land south of Boise, calling sale of public lands shortsighted and calling for statewide framework protecting natural resources. (September 23, 2026) [3]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: ValorC3
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for ValorC3 Boise Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 14 MW Disclosed filing [4] godatacenters.com
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    ValorC3 Boise data center built in 2020 using hybrid cooling

    [4] godatacenters.com

  2. · Status: proposed (content date)

    ValorC3 Data Centers announced plans to develop a second colocation data center facility in Boise, Ada County, Idaho.

    [1] datacenterdynamics.com

Every event in order

6 corrections to this record

Every correction, with its reason
  1. · Site coordinates

    Boise is in Ada County; the record had filed it under Boise County and placed it at Idaho City, that county's seat. On the editor's word of October 16, 2026.

  2. · County (Boise County to Ada County)

    Boise is in Ada County; the record had filed it under Boise County and placed it at Idaho City, that county's seat. On the editor's word of October 16, 2026.

  3. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  4. · Site acreage (924 acres to 92 acres)

    The site read 924 acres. The source said approximately 92 acres (4 million square feet), and the approval ran the two numbers together. Corrected to the 92 acres the source gives.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Idaho

Verified data center records in Idaho within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Kuna Data Centers (two projects) Kuna, Ada County ~1 mi Proposed
Meta Kuna Data Center Kuna, Ada County ~11 mi Running Meta 2 buildings

Blank cell: not disclosed by any source on file.

Common questions about ValorC3 Boise Data Center

Answered directly from the verified filings and local actions on this page.

Who is building ValorC3 Boise Data Center?

ValorC3 is the developer. No construction contractor is named on the record yet.

How much power and water does ValorC3 Boise Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does ValorC3 Boise Data Center stand today?

It is proposed, since June 1, 2026. The newest entry, reported September 10, 2026: ValorC3 Boise data center built in 2020 using hybrid cooling [4].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. ValorC3 to develop second data center in Boise, Idaho - Data Center Dynamics (opens in a new tab), Data Center Dynamics, May 6, 2025, news outlet
  2. ValorC3 secures credit facility to fund 10MW data center in Boise, Idaho - Data Center Dynamics (opens in a new tab), Data Center Dynamics, April 30, 2026, trade press
  3. Boise mayor: "Sell offs of public lands to build mega data centers is shortsighted" - KBOI (opens in a new tab), KBOI, September 23, 2026, local outlet
  4. ValorC3 Boise Data Center Data Center, Boise, Idaho (opens in a new tab), godatacenters.com, September 10, 2026, news outlet
  5. ValorC3 Data Centers Announces 10MW Data Center in Boise, Idaho (opens in a new tab), valorc3.com, May 5, 2025, news outlet

5 sources on file.

Regional grid context

This site is in the Northwest Power Pool (NWPP) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "ValorC3 Boise Data Center", https://datacenterrecord.org/projects/valorc3-boise-data-center-id, last verified October 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "ValorC3 Boise Data Center", https://datacenterrecord.org/projects/valorc3-boise-data-center-id. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
43.60023, -116.2298
How the location is known
Location is the city center; exact site not disclosed.
Location source
U.S. Census Bureau 2020 Gazetteer, internal point of Boise City city (GEOID 1608830), public domain
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Capacity, if disclosed
14 MW, not disclosed
Published
September 5, 2026
Last verified
October 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows