Data centers in North Dakota

North Dakota has 4 data center sites, 0 buildings where disclosed on the record: 1 running, 2 being built and 1 proposed. The counties with the most are Cass County (1) and Dickey County (1), and records are in 4 of 53 counties. The largest proposal is Applied Digital Polaris Forge 3 (Oliver County) in Oliver County; it is being built, as reported July 29, 2026.

North Dakota allows new data centers. From the state's own rule: The 2015 Legislature approved the original data center tax exemption with the current version set by the 2021 Legislature, August 27, 2026.

1 site the EPA's registry shows and no record has verified is on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Every North Dakota record 4 records, and 1 site not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Apld Jamestown DatacenterJamestown, StutsmanNot yet verifiedEPA registry22026-10-20
Applied Digital Polaris Forge 3 (Oliver County)OliverBeing builtApplied Digital430centroid12026-10-07
Applied Digital Polaris Forge 1 (Ellendale)Ellendale, DickeyRunningApplied Digital400centroid12026-10-16
Proposed data center near MandanMandan, MortonProposedcentroid12026-09-17
Applied Digital Polaris Forge 2 (Harwood)Harwood, CassBeing builtApplied Digital280centroid12026-10-16

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every North Dakota county (53)

4 of 53 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRulesHow it treats data centers
Cass County3801710
Dickey County3802110
Morton County3805912case by case
Oliver County3806510
Williams County3810502case by case

A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.

48 counties with no records yet
  • Adams County
  • Barnes County
  • Benson County
  • Billings County
  • Bottineau County
  • Bowman County
  • Burke County
  • Burleigh County
  • Cavalier County
  • Divide County
  • Dunn County
  • Eddy County
  • Emmons County
  • Foster County
  • Golden Valley County
  • Grand Forks County
  • Grant County
  • Griggs County
  • Hettinger County
  • Kidder County
  • LaMoure County
  • Logan County
  • McHenry County
  • McIntosh County
  • McKenzie County
  • McLean County
  • Mercer County
  • Mountrail County
  • Nelson County
  • Pembina County
  • Pierce County
  • Ramsey County
  • Ransom County
  • Renville County
  • Richland County
  • Rolette County
  • Sargent County
  • Sheridan County
  • Sioux County
  • Slope County
  • Stark County
  • Steele County
  • Stutsman County
  • Towner County
  • Traill County
  • Walsh County
  • Ward County
  • Wells County

The rules in North Dakota 6 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
North DakotastateopenThe 2015 Legislature approved the original data center tax exemption with the current version set by the 2021 Legislature. inforum.com (opens in a new tab) local outlet Aug 27, 202624 acts on this row
Every act on the North Dakota row
  1. event

    North Dakota state and local leaders held informational event on data centers on September 9, 2026

    journalnd.com (opens in a new tab) local outlet

  2. denial

    ND lawmakers rejected a ban on data center non disclosure agreements

    knoxradio.com (opens in a new tab) local outlet

  3. event

    North Dakota Senate defeated a bill banning NDAs for data center and industrial projects

    kfgo.com (opens in a new tab) local outlet

  4. moratorium rejected

    North Dakota House voted down data center moratorium proposal 68-25

    knoxradio.com (opens in a new tab) local outlet

  5. moratorium

    North Dakota special session killed data center NDA ban proposal

    inforum.com (opens in a new tab) local outlet

  6. event

    North Dakota Senate rejected Senate Bill 2406 on a 32-15 vote on September 3, 2026, which would have banned nondisclosure agreements between government entities and data center developers.

    mydakotan.com (opens in a new tab) local outlet

    Also reported by 4 sources
  7. moratorium rejected

    Democrats' bill to pause data center development failed in North Dakota House and Senate

    kfgo.com (opens in a new tab) local outlet

  8. moratorium rejected

    North Dakota Legislature rejected Democratic led attempts to add data center moratorium for special session

    northdakotamonitor.com (opens in a new tab) local outlet

  9. event

    Senate Bill 2406 received do not pass recommendation from joint House Senate policy committee

    northdakotamonitor.com (opens in a new tab) local outlet

  10. hearing

    AI and Data Center Committee held third official meeting

    kxnet.com (opens in a new tab) news outlet

  11. event

    North Dakota Legislature held a special session in early September where majority lawmakers refused to pass a ban on nondisclosure agreements between data center companies and local elected officials.

    northdakotamonitor.com (opens in a new tab) local outlet

  12. hearing

    Costs and benefits of data centers discussed at North Dakota legislative meeting

    northdakotamonitor.com (opens in a new tab) local outlet

  13. event

    North Dakota Legislative Management Artificial Intelligence and Data Center Committee convened at State Capitol to review policy, electrical grid and regulatory frameworks

    wdayradionow.com (opens in a new tab) local outlet

    Also reported by 1 source
  14. hearing

    North Dakota AI and Data Center Committee hearing was held on August 31 2026

    inforum.com (opens in a new tab) local outlet

    Also reported by 2 sources
  15. event

    North Dakota Artificial Intelligence and Data Center Committee met Monday to evaluate data center growth, grid impacts and regulatory frameworks

    am1100theflag.com (opens in a new tab) local outlet

    Also reported by 1 source
  16. event

    The 2015 Legislature approved the original data center tax exemption with the current version set by the 2021 Legislature

    inforum.com (opens in a new tab) local outlet

  17. event

    North Dakota lawmakers advanced proposal to ban nondisclosure agreements for data centers and other industrial developments through June 30 2027

    devilslakejournal.com (opens in a new tab) news outlet

  18. event

    North Dakota AI and Data Center Committee directed to work toward child AI use regulations

    inforum.com (opens in a new tab) local outlet

  19. filing

    Sen. Tim Mathern filed a bill draft to put a temporary ban on new data center permits and another to prevent public officials from agreeing not to share information about data center development plans.

    northdakotamonitor.com (opens in a new tab) local outlet

  20. filing

    Sen. Desiree van Oosting filed a bill that would mandate data centers file quarterly reports with three state agencies and legislative leaders, reporting electricity use, water use, and requiring operators to pay for facility shutdown costs.

    northdakotamonitor.com (opens in a new tab) local outlet

  21. hearing

    North Dakota AI and Data Center Committee first meeting held in Bismarck with presentations on state and federal AI regulation

    wdayradionow.com (opens in a new tab) local outlet

  22. event

    North Dakota Legislature established Artificial Intelligence and Data Center Committee chaired by State Representative Jonathan Warrey

    wdayradionow.com (opens in a new tab) local outlet

  23. approval

    Oliver County Commission voted 2-1 to approve building permit for Applied Digital data center with conditions on water, waste, traffic, noise and reclamation

    inforum.com (opens in a new tab) local outlet

  24. event

    North Dakota Legislature established an interim Artificial Intelligence and Data Center Committee with citizen members

    governor.nd.gov (opens in a new tab) primary source

Last verified September 23, 2026.

242026-09-23
Harwoodcitynot ratedData center impacts discussed at public forum in Harwood. valleynewslive.com (opens in a new tab) local outlet Reported Aug 291 act on this row
Every act on the Harwood row
  1. hearing

    Data center impacts discussed at public forum in Harwood

    valleynewslive.com (opens in a new tab) local outlet

Last verified September 10, 2026.

12026-09-10
Mandancitynot ratedMandan residents gathered over 700 signatures on a petition to limit data centers to 25 megawatts or less of power use. news.prairiepublic.org (opens in a new tab) local outlet Reported Sep 231 act on this row
Every act on the Mandan row
  1. event

    Mandan residents gathered over 700 signatures on a petition to limit data centers to 25 megawatts or less of power use

    news.prairiepublic.org (opens in a new tab) local outlet

Last verified September 23, 2026.

12026-09-23
Morton Countycountycase by caseOrdinance passed 5-1, with Tokach voting against due to tonal noise issue. bismarcktribune.com (opens in a new tab) local outlet Sep 19, 20262 acts on this row
Every act on the Morton County row
  1. ordinance

    Ordinance passed 5-1, with Tokach voting against due to tonal noise issue

    bismarcktribune.com (opens in a new tab) local outlet

  2. ordinance

    Morton County Commission approved data center ordinance on September 10, 2026

    bismarcktribune.com (opens in a new tab) local outlet

Last verified September 19, 2026.

22026-09-19
Williams Countycountycase by caseWilliams County Commission approved conditional use permit for Enerfore Digital Data Center in Feb. 2025 but permit expired Aug. 4, 2026 due to inactivity. willistonherald.com (opens in a new tab) news outlet Sep 2, 20261 act on this row
Every act on the Williams County row
  1. litigation

    Williams County Commission approved conditional use permit appeal for Project Trinity in Feb. 2025

    willistonherald.com (opens in a new tab) news outlet

Last verified September 2, 2026.

12026-09-02
Willistoncitycase by caseProject Fighting Pike Critical Data House approved by Williston City Commission on March 25, 2025. willistonherald.com (opens in a new tab) news outlet Mar 25, 20251 act on this row
Every act on the Williston row
  1. approval

    Project Fighting Pike Critical Data House approved by Williston City Commission on March 25, 2025

    willistonherald.com (opens in a new tab) news outlet

Last verified September 2, 2026.

12026-09-02

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

North Dakota laws and the full scorecard

Bills and laws in North Dakota

1 signed into law, 3 bills tracked

3 bills tracked in the North Dakota legislature, 1 of them signed into law, grouped by where each stands. A row opens its own page; the North Dakota laws page has what each law requires.

Signed into law 1

In committee 2

3 bills tracked, 1 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
H.B. 1239 69th Legislative Assembly In committee 2025-02-13 Blockchain technology and protection for digital asset mining.
H.B. 1427 69th Legislative Assembly In committee 2025-01-13 Authorization for the public service commission to regulate the siting compatibility for data centers; and to provide a penalty.
1089 64th Legislative Assembly Signed 2015-04-10 A sales tax exemption for enterprise information technology equipment and computer software purchased for use in a qualified data center; to provide for a retroactive effective date; and to provide an expiration date.

3 bills tracked in North Dakota; 69th Legislative Assembly Special Session 2, legislature in session; last checked October 26, 2026. The last check found no bill not already tracked; the 3 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. North Dakota's members: 1 yea, 0 nay. How each member voted

MemberPartyPosition
FedorchakRYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. North Dakota's members: 2 yea, 0 nay. How each member voted

MemberPartyPosition
Cramer (R-ND)RYea
Hoeven (R-ND)RYea

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

  1. OrdinanceMorton County

    Ordinance passed 5-1, with Tokach voting against due to tonal noise issue

  2. DenialNorth Dakota

    ND lawmakers rejected a ban on data center non disclosure agreements

The full North Dakota timeline, year by year

What was said

We're in full respect for the land and everything that you're asking for, because we got burned at Atlas. We implemented the first data center ordinance in the state and a lot of other counties have modeled it after us.
Steve Kemp, County commissioner, Williams County Commission · October 22, 2026 · quoted · Williston Herald (opens in a new tab) news outlet
We would be happy to slow down and talk. We've been offering that all the way through. There's no interest from the other side.
Blake Nixon, Chief Executive Officer, Geronimo Power · October 22, 2026 · quoted · kvrr.com (opens in a new tab) local outlet · also reported by 1 more source

Every North Dakota statement, by speaker (65)

62 more on this page, one per speaker and claim; 65 statements in all
"I just want to make sure that North Dakota still keeps its pristine environments that we have, so that our children and our grandchildren can grow up and be farmers. I just want to make sure that we have in place language that people understand that we are protecting and are going to do this for our land."
Carole Herbert, Local resident and fourth generation landowner, Williams County, ND Williams County Commission meeting Williston Herald (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Williams County Commission meeting.

Primary source: Williston Herald (opens in a new tab).

"I find it ironic when we get asked about being open and transparent, and then the people that are entrusted to ensure openness and transparency want to shut down a process before it even starts"
Blake Nixon, Chief Executive Officer, Geronimo Power Community Data Center Forum, Grand Farm Innovation Campus KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Community Data Center Forum, Grand Farm Innovation Campus.

Primary source: KFGO (opens in a new tab).

"Sending a message like no development of anything ... for 24 months says 'this community is closed for business.' And I just don't believe that represents this community"
Blake Nixon, Chief Executive Officer, Geronimo Power Community Data Center Forum, Grand Farm Innovation Campus KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Community Data Center Forum, Grand Farm Innovation Campus.

Primary source: KFGO (opens in a new tab).

Pederson said the current regulatory framework for commercial data centers resembles 'the Wild West' with out of state tech corporations negotiating individual non disclosure agreements with single townships or counties.

North Dakota Public Service Commission candidate The Mighty 790 KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Mighty 790 KFGO (opens in a new tab).

Pederson cited a crypto mining facility built in Williston where added infrastructure demands led to higher monthly utility bills for local ratepayers.

North Dakota Public Service Commission candidate The Mighty 790 KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Mighty 790 KFGO (opens in a new tab).

Vern Thompson, Democrat, is running for North Dakota agriculture commissioner in part to oversee data center oversight and natural gas pipeline

Democratic candidate for North Dakota agriculture commissioner route-fifty.com (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: route-fifty.com (opens in a new tab).

Vern Thompson has led a series of meetings on data centers, with attendees concerned about health effects, using up prime farmland and the state being overwhelmed by demand for electricity and water

Democratic candidate for North Dakota agriculture commissioner Route Fifty (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Route Fifty (opens in a new tab).

House Majority Leader Steve Scalise and Rep. Julie Fedorchak promoted the bill at press conference in Fargo on September 22, 2026.

U.S. House Majority Leader InForum (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: InForum (opens in a new tab).

Chairman Nathan Boehm said ordinance will need tweaks in the future and there is need for more discussion on general tonal noise policy

Morton County Commission Chairman Bismarck Tribune (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Bismarck Tribune (opens in a new tab).

Vern Thompson, agriculture commissioner candidate, hosted data center forum at Central Cass High School on September 15, 2026

candidate for North Dakota Agriculture Commissioner The Forum (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Forum (opens in a new tab).

Vern Thompson stated data centers being built on land that would have otherwise been used for agricultural purposes

candidate for North Dakota Agriculture Commissioner The Forum (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The Forum (opens in a new tab).

Civic West hosting Fire Hall Chat on September 17 at 7 p.m. to discuss data center benefits and drawbacks with residents and Applied Digital representative

Mary Tintes, Civic West Steering Committee member InForum (opens in a new tab) local outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: InForum (opens in a new tab).

Applied Digital is projected to be the largest property taxpayer in North Dakota by 2028 or 2029, at more than $25 million a year

Dave Nehring, Applied Digital Director of Local & Regional Affairs Jamestown Sun (opens in a new tab) news outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Jamestown Sun (opens in a new tab).

Vern Thompson, Democratic NPL candidate for North Dakota agriculture commissioner, criticized use of non disclosure agreements by public officials in data center developer negotiations

KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

Vern Thompson spoke for 6 minutes 46 seconds during public comment period at North Dakota data center hearing

Democratic-NPL candidate for agriculture commissioner InForum (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: InForum (opens in a new tab).

Applied Digital spokesman Nick Phillips spoke for 5 minutes 12 seconds during public comment period at North Dakota data center hearing

InForum (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: InForum (opens in a new tab).

Sen. Tim Mathern, D Fargo, introduced Senate Bill 2406 and proposed amendments including one to eliminate state sales tax exemption for data center developers and another to exempt public entities that are energy providers

North Dakota State Senator The Mighty 790 KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: The Mighty 790 KFGO (opens in a new tab).

Applied Digital used nondisclosure agreements in North Dakota for about six weeks during project viability determination before permitting and lifting the NDA

Nick Phillips The Mighty 790 KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: The Mighty 790 KFGO (opens in a new tab).

Gov. Kelly Armstrong, R, testified against Senate Bill 2406 but favored an amendment clarifying the law would not prohibit nondisclosure agreements to maintain confidentiality of information already considered confidential or exempt under state law

Governor of North Dakota The Mighty 790 KFGO (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: The Mighty 790 KFGO (opens in a new tab).

Nick Phillips, executive vice president of external affairs for Applied Digital, testified company used NDAs for Harwood project in compliance with state laws

Executive Vice President of External Affairs, Applied Digital North Dakota Monitor (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: North Dakota Monitor (opens in a new tab).

It was less than three months when the public became aware of the project in Oliver County to when construction began

Michel Berg, local farmer KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

The Executive Director for the North Dakota Association of Counties spoke about the role local governments play in deciding where, how and under what conditions data centers can be built

Aaron Birst, Executive Director, North Dakota Association of Counties KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

Representative Julie Fedorchak supports the federal Ratepayer Protection Act, which ensures data center facilities pay their fair share for energy

North Dakota Representative KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

Fedorchak said data center permitting and building decisions should be made locally, not from Washington or Bismarck

North Dakota Representative KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

Fedorchak said data center companies must be completely transparent with local leaders about their impact on noise, roads and energy before any deals are made

North Dakota Representative KFYR-TV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KFYR-TV (opens in a new tab).

On the November 3, 2026 ballot in North Dakota: U.S. House, at large (4); 4 of 4 candidates with a statement on data centers on the record. Every candidate.

Already running in North Dakota

1 site is serving load, 1 of them in Dickey County.

See the 1 running site
  1. Applied Digital Polaris Forge 1 (Ellendale) Ellendale, Dickey County Running 400 MW

Questions about North Dakota data centers

How many data center projects are on the record in North Dakota?

4 projects are on the record in North Dakota: 1 reported, 2 being built, 1 running and 1 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in North Dakota are they?

Records are in 4 counties: Cass County (1), Dickey County (1), Morton County (1) and Oliver County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in North Dakota?

Not disclosed. None of the 4 records on file for North Dakota states a power figure. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in North Dakota say they will use?

Not disclosed. None of the 4 records on file for North Dakota states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in North Dakota?

1 developer is named on the record: Applied Digital (3 records). 1 record names no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in North Dakota have rules about data centers?

5 county and city rows are on the record, 3 of them rated: Morton County is rated case by case: Ordinance passed 5-1, with Tokach voting against due to tonal noise issue, September 19, 2026, source (opens in a new tab), Williams County is rated case by case: Williams County Commission approved conditional use permit for Enerfore Digital Data Center in Feb. 2025 but permit expired Aug. 4, 2026 due to inactivity, September 2, 2026, source (opens in a new tab) and Williston is rated case by case: Project Fighting Pike Critical Data House approved by Williston City Commission on March 25, 2025, source (opens in a new tab). The state's own row is rated open, with 24 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in North Dakota, by county?

3 records are not yet running. Cass County: Applied Digital Polaris Forge 2 (Harwood) (being built); Morton County: Proposed data center near Mandan (reported); and Oliver County: Applied Digital Polaris Forge 3 (Oliver County) (being built). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of North Dakota itself decided?

1 state law is on the record: 1089 (signed, April 10, 2015, source (opens in a new tab)). The state's own scorecard row carries 24 dated acts, the newest September 9, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

nothing disclosed by 4 records

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power04
Water, stated per day04
Water, stated per year04
Permanent jobs04
Tax each year04

A blank cell means no record in North Dakota disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power04
Water, stated per day04
Water, stated per year04
Permanent jobs04
Tax each year04

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 4 tracked facilities in North Dakota are for. 1 site not yet verified is named apart and is not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use4

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

No source on file states how any of the 4 tracked facilities in North Dakota are cooled. 1 site not yet verified is named apart and is not in that number.

Sources read for North Dakota

8 sources

8 sources are read for North Dakota:

Newspapers
Bismarck Tribune, The Forum
Public broadcaster
Prairie Public
Utility commission dockets
North Dakota Public Service Commission
Economic development
North Dakota Commerce Department
Search feeds
3 news searches
Every feed, with its kind and tier

What the monitor reads for North Dakota: feeds every four hours, pages daily.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in North Dakota", https://datacenterrecord.org/states/nd, updated October 24, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in North Dakota", https://datacenterrecord.org/states/nd. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
ND
Rating of the state's own row
Open
Count by status
reported 1, being built 2, running 1, not yet verified 1
Located records
0 located, 4 at a centroid, 0 without coordinates

Researcher view · North Dakota · 4 data center sites, 0 buildings where disclosed, 6 rule rows, 3 bills · basis and source tier on every row · verified October 24, 2026