NorthMark Spartanburg County Data Center

Street address 4500 Country Club Road, Spartanburg, SC 29302, Spartanburg County verified address Exact, at the address [2] yahoo.com

Overview, regulatory gates and specifications

NorthMark Strategies and Valara Holdings are constructing a 457 megawatt data center campus at the former Kohler industrial site in Spartanburg County, South Carolina, after the South Carolina Public Service Commission dismissed regulatory challenges in August 2026. [2] Filings on the record specify disclosed capacity of 457 MW (the developer's figure), 3 planned or operational buildings. [2] NorthMark's Valara Data Center revised water use to 1.2 million gallons per day average, up to 1.6 million maximum, up from original 459,000 gallons per day [27]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Incentive review
4. Utility Grid Queue
457 MW disclosed
5. Air & Water Permits
Not yet on file
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand [2]
457 MW
the developer's figure

Equivalent to ~379,310 U.S. homes (U.S. EIA 830 homes/MW baseline) · 22% of Hoover Dam nameplate capacity (2,080 MW).

Electric utility: natural gas, 450 MW.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
3 buildings
zoning application

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 4500 Country Club Road, Spartanburg, SC 29302.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
457 MW developer figure Equivalent to the continuous electricity demand of about 379,300 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 4 percent of New York City's summer peak demand in 2024.
[2] yahoo.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
3 buildings operator page
[1] nytimes.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
NorthMark Strategies / Valara Holdings as stated by the source
Where its power comes from
natural gas, 450 MW as stated by the source
[19] goupstate.com
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. NorthMark Spartanburg County Data Center, capacity: 457 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 457 ÷ 10,245 = 0.04 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Monier Abusaft

Councilman · Spartanburg County Council

DID Recorded statement at Spartanburg County Council meeting (November 5, 2026)
SAID I believe that these industries will be as transformative to Spartanburg county as BMW was. (November 5, 2026) southcarolinapublicradio.org (opens in a new tab)

Annie Andrews

Pediatrician and Democratic U.S. Senate Nominee · South Carolina Democratic Party

DID Recorded statement at The New York Times (October 27, 2026) [1]
SAID Democratic U.S. Senate nominee Dr. Annie Andrews called for a two year statewide moratorium on new data center construction in South Carolina, arguing that unchecked hyperscale development threatens household electricity rates, water supplies, and county tax bases. (October 27, 2026) [1]
Darline Graham

Darline Graham

U.S. Senator · South Carolina

DID Recorded statement at The New York Times (October 27, 2026) [1]
SAID Senator Darline Graham opposed calls for a data center moratorium in South Carolina and defended hyperscale artificial intelligence infrastructure as essential to U.S. national security in competition with China, while the AI industry super PAC Building the Future reserved $1.5 million in television advertising supporting his reelection. (October 27, 2026) [1]

Pierre DuBois

Spokesperson · AIB Data Centers

DID Recorded statement at Company Statement (October 13, 2026)
SAID Since the site began operating, it has used about 14,000 gallons a day. We estimate the data center will use about 165 gallons a day. (October 13, 2026) postandcourier.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: NorthMark Strategies / Valara Holdings
UTILITIES
Electric utility: natural gas, 450 MW

View all 18 statements on the record in South Carolina →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for NorthMark Spartanburg County Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 457 MW the developer's figure [2] yahoo.com
Site Footprint (Acres)
Data Hall Buildings 3 buildings zoning application [1] nytimes.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Higher water demand figures were provided to Spartanburg Water on February 11, 2026, as part of the project's Large Water Meter Questionnaire

    [27] yahoo.com

  2. (source date; the content gives no date of its own)

    NorthMark's Valara Data Center revised water use to 1.2 million gallons per day average, up to 1.6 million maximum, up from original 459,000 gallons per day

    [27] yahoo.com

  3. (source date; the content gives no date of its own)

    South Carolina Department of Environmental Services granted permit September 18 for 11 natural gas turbines generating additional 408 megawatts, bringing total capacity to 457 megawatts

    [2] yahoo.com

  4. (source date; the content gives no date of its own)

    Spartanburg County Planning Commission voted last month to halt the stalled Lighthouse data center project.

    [18] southcarolinapublicradio.org

  5. (source date; the content gives no date of its own)

    Construction on the Valara site has already begun and continues while court considers the classification decision.

    [18] southcarolinapublicradio.org

  6. (source date; the content gives no date of its own)

    State Circuit Court judge delayed decision on Valara data center construction in Spartanburg.

    [18] southcarolinapublicradio.org

  7. (source date; the content gives no date of its own)

    The meeting lasted five hours with public, experts, and council members debating a data center project

    [11] wyff4.com

  8. (source date; the content gives no date of its own)

    Valara project became public in March 2025 when Spartanburg County began negotiating tax incentives for project creating 27 jobs

    [17] myclintonnews.com

14 earlier entries
  1. (source date; the content gives no date of its own)

    NorthMark Strategies converting Kohler kitchen and bath manufacturing plant into $2.8 billion computing center on 300 acres

    [17] myclintonnews.com

  2. (source date; the content gives no date of its own)

    NorthMark was approved about two years ago through a public process including three readings and a public hearing

    [16] foxcarolina.com

  3. (source date; the content gives no date of its own)

    NorthMark data center construction continues on South Pine Street

    [16] foxcarolina.com

  4. (source date; the content gives no date of its own)

    Valara Holdings data center initially approved as minor project, now subject to community opposition and legal challenge

    [6] foxcarolina.com

  5. (content date)

    A $2.8,$3 billion NorthMark data center project in Spartanburg County is under construction and faced legal challenges including an injunction request and lawsuit, but the SC Public Service Commission ruled the project is not subject to public power plant regulations.

    [2] yahoo.com

  6. (source date; the content gives no date of its own)

    South Carolina approved nearly $3 billion data center in Spartanburg County

    [4] yahoo.com

  7. Filing (source date; the content gives no date of its own)

    NorthMark submitted an application for a minor land development for the next phase of construction

    [26] goupstate.com

  8. (source date; the content gives no date of its own)

    Southern Environmental Law Center filed a request for a preliminary injunction to halt the Valara project

    [26] goupstate.com

  9. (source date; the content gives no date of its own)

    NorthMark received a fee in lieu of taxes incentive package from Spartanburg County Council in 2025

    [26] goupstate.com

  10. (source date; the content gives no date of its own)

    NorthMark plans to construct a 450 megawatt power generation facility to provide electricity for the data center

    [26] goupstate.com

  11. (source date; the content gives no date of its own)

    NorthMark's Valara subsidiary is constructing a data center on South Pine Street at the old Kohler plant site in Spartanburg

    [26] goupstate.com

  12. (source date; the content gives no date of its own)

    NorthMark Cloud and Compute announced quarterly philanthropic donations between $250,000 and $500,000

    [26] goupstate.com

  13. (source date; the content gives no date of its own)

    The project would have created about 50 jobs

    [3] wyff4.com

  14. · being built (source date; the content gives no date of its own)

    LightHouse Data Centers proposed a project covering about 151 acres along Jones Road with an approximately 200,000 square foot building

    [3] wyff4.com

Every event in order

17 corrections to this record

Every correction, with its reason
  1. · Timeline entry

    Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.

  2. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  3. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  9. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  10. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  11. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  12. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  13. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  14. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  15. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

See all 17 corrections for this record (2 more) →

Every correction on the record is on the corrections page.

Nearest data centers in South Carolina

Verified data center records in South Carolina within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
300 Jones Road Data Center Spartanburg, Spartanburg County 5 mi Proposed Lighthouse Data Centers / Wharton Digital 2 buildings
DartPoints Spartanburg Data Center (SPA1) Spartanburg, Spartanburg County 7 mi Running DartPoints 4 MW
Cherokee County Data Center Gaffney, Cherokee County 18 mi Proposed 3 buildings
DartPoints Greenville Data Center (GSP1) Greenville, Greenville County 25 mi Running DartPoints 4 MW
DC BLOX Greenville Data Center (GSP1) Greenville, Greenville County 25 mi Running DC Blox 9 MW
QTS York County Rock Hill, York County 47 mi Being built QTS Data Centers 300 MW

Blank cell: not disclosed by any source on file.

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Capacity at full buildout

2 figures, 2 sources
457 MW Developer's figure

Post and Courier, Sep 21, 2026

Show each source's words
  • 50 MW, South Carolina Public Radio: Northmark Strategies data center in Spartanburg County increased required generator capacity from 50MW to 450MW

Common questions about NorthMark Spartanburg County Data Center

Answered directly from the verified filings and local actions on this page.

Who is building NorthMark Spartanburg County Data Center?

NorthMark Strategies / Valara Holdings is the developer. No construction contractor is named on the record yet.

Who will use NorthMark Spartanburg County Data Center?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does NorthMark Spartanburg County Data Center say it needs?

Power: 457 MW (the developer's figure, yahoo.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does NorthMark Spartanburg County Data Center stand today?
What is still unknown about NorthMark Spartanburg County Data Center?

Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. AI Industry Super PAC Spends $1.5 Million to Back Graham in Tight South Carolina Senate Race (opens in a new tab), The New York Times, October 27, 2026

Reporting

  1. Spartanburg data center gets OK from SC regulators to generate 457 megawatts - Post and Courier (opens in a new tab), Post and Courier, September 21, 2026, national outlet
  2. Spartanburg County board blocks proposed data center - WYFF (opens in a new tab), WYFF, August 25, 2026, local outlet
  3. South Carolina approves nearly $3 billion data center in Spartanburg County despite lawsuit - Yahoo (opens in a new tab), Yahoo, August 28, 2026, national outlet
  4. Special meeting called over data center construction in Spartanburg County - Yahoo (opens in a new tab), Yahoo, September 21, 2026, national outlet
  5. Spartanburg County to hold special meeting on controversial data centers - FOX Carolina News (opens in a new tab), FOX Carolina News, September 9, 2026, local outlet
  6. Spartanburg County data center construction continues despite legal challenges - WYFF (opens in a new tab), WYFF, September 2, 2026, local outlet
  7. Public Service Commission sides with Spartanburg data center, says it won't regulate NorthMark - Post and Courier (opens in a new tab), Post and Courier, August 27, 2026, local outlet
  8. State commission sides with Spartanburg data center in legal challenge - WSPA 7News (opens in a new tab), WSPA 7News, August 27, 2026, local outlet
  9. SC Public Service Commission dismisses challenge to Spartanburg County data center project - FOX Carolina News (opens in a new tab), FOX Carolina News, August 27, 2026, local outlet
  10. Upstate leaders and public clash over future of data centers - WYFF (opens in a new tab), WYFF, September 11, 2026, local outlet
  11. Citizens group lawyers seek injunction to halt data center construction - Greenville Online (opens in a new tab), Greenville Online, August 20, 2026, local outlet
  12. Lawsuit targets Spartanburg County data center project, demands public planning review - FOX Carolina News (opens in a new tab), FOX Carolina News, July 7, 2026, local outlet
14 more sources
  1. Could data center challenge change the landscape in South Carolina? - WRDW (opens in a new tab), WRDW, August 5, 2026, local outlet
  2. Data center developer wants to build own power plant. Does it need SC’s approval? - The State (opens in a new tab), The State, August 6, 2026, local outlet
  3. Spartanburg council committee holds hearing on data centers, presses for credible evidence - FOX Carolina News (opens in a new tab), FOX Carolina News, September 9, 2026, local outlet
  4. DATA 2: Spartanburg data center not subject to public power plant rules, SC regulators rule - The Clinton Chronicle (opens in a new tab), The Clinton Chronicle, September 10, 2026, local outlet
  5. Judge punts decision on Spartanburg data center construction (opens in a new tab), South Carolina Public Radio, September 17, 2026, local outlet
  6. Spartanburg County data center ban advances. NorthMark to be included? (opens in a new tab), www.goupstate.com, July 21, 2026, news outlet
  7. South Carolina Public Service Commission approves nearly $3 billion data center - WYFF (opens in a new tab), WYFF, August 27, 2026, local outlet
  8. Spartanburg data center not subject to public power plant rules, SC regulators rule - South Carolina Daily Gazette (opens in a new tab), South Carolina Daily Gazette, August 27, 2026, news outlet
  9. They started building a $2.8 billion data center and no one really knew about it - selc.org (opens in a new tab), selc.org, August 26, 2026, news outlet
  10. Environmental group seeks to halt development of $3B data center in Spartanburg County - WYFF (opens in a new tab), WYFF, August 21, 2026, local outlet
  11. Development company responds to request for injunction to halt Upstate data center project - FOX Carolina News (opens in a new tab), FOX Carolina News, August 20, 2026, local outlet
  12. Environmental group files court order to stop Spartanburg County data center project - FOX Carolina News (opens in a new tab), FOX Carolina News, August 20, 2026, local outlet
  13. NorthMark pledges up to $500K in philanthropic gifts per quarter - GoUpstate (opens in a new tab), GoUpstate, August 26, 2026, news outlet
  14. Amount of water needed to operate Spartanburg Data Center more than double original estimate - WSPA 7News (opens in a new tab), WSPA 7News, September 21, 2026, national outlet

27 sources on file.

Regional grid context

This site is in the SERC Virginia and Carolina South (SRVC-S) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "NorthMark Spartanburg County Data Center", https://datacenterrecord.org/projects/northmark-spartanburg-county-data-center-sc, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "NorthMark Spartanburg County Data Center", https://datacenterrecord.org/projects/northmark-spartanburg-county-data-center-sc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
34.94806, -81.93472
How the location is known
Location from the site's street address.
Location source
https://www.psc.sc.gov/
Coordinate source
SC Public Service Commission docket and Spartanburg County parcel record
Location last verified
September 16, 2026
How capacity was disclosed
the developer's figure
Capacity, if disclosed
457 MW, the developer's figure
Published
September 5, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · NorthMark Spartanburg County Data Center · 27 sources, 22 entries · basis and source tier on every row · verified November 6, 2026