What was said about data centers in South Carolina
62 statements from 31 speakers, grouped by who spoke. Each appears as said, with the date and the source. No verdict is attached.
From September 26, 2024 to November 20, 2026. Statements from every state are on Statements.
Data center companies 5
Developers, operators and builders of data centers and the technology companies that fill them, speaking through their staff and spokespeople. Every state.
-
Pierre DuBois, Spokesperson, AIB Data Centers
Since the site began operating, it has used about 14,000 gallons a day. We estimate the data center will use about 165 gallons a day.
-
Valara Holdings Computing Center spokesperson
Sarah Knox, Valara Holdings spokesperson, said the project would use 97 percent of its own energy capacity and minimize grid reliance
-
Valara Holdings Computing Center spokesperson
Sarah Knox said the project will not use groundwater aquifers or wells
-
Sarah Knox, director of external affairs for NorthMark Strategies
NorthMark is complying with state laws and is still waiting on an air permit to operate and hopes to receive it by the end of the year
-
Sarah Knox, NorthMark Director of External Affairs, stated the project meets DES and EPA regulations according to plain reading
Government 23
Officials in office, lawmakers, regulators, public agencies and courts, federal, state, tribal and local. Every state.
-
General Manager, City of Orangeburg Department of Public Utilities
Warren Harley, General Manager of the City of Orangeburg Department of Public Utilities, said the city cannot serve hyperscale data centers of 100 to 500 megawatt range and finds 25 to 50 megawatt range more suitable
-
Director of Tribal Partnerships, Strata Expanse
Charles Snow, director of Tribal Partnerships at Strata Expanse, described three data center cooling methods: air based cooling, evaporative cooling, and closed loop liquid cooling
-
Monier Abusaft, Councilman, Spartanburg County Council
I believe that these industries will be as transformative to Spartanburg county as BMW was.
-
U.S. Senator
Senator Darline Graham opposed calls for a data center moratorium in South Carolina and defended hyperscale artificial intelligence infrastructure as essential to U.S. national security in competition with China, while the AI industry super PAC Building the Future reserved $1.5 million in television advertising supporting his reelection.
-
U.S. Senator (R-South Carolina)
Republican incumbent Darline Graham opposes a data center moratorium, citing national security competition with China
-
U.S. Senator
Darline Graham, Republican senator, said she is concerned about data centers and thinks there needs to be community involvement when it comes to data centers
-
U.S. Senator, Republican
Darline Graham, Republican U.S. Senator, said a two year moratorium on data centers would be dangerous to national security because China would get ahead.
-
Governor of South Carolina
Governor McMaster said September 23 2026 he does not plan to call for a statewide data center moratorium
-
Jessica Coker, Spartanburg County councilwoman, voted against the moratorium, saying no evidence had been presented demonstrating a clear threat to residents
-
Dr. Octavia Amaechi, Spartanburg County Commissioner of Public Works, expressed concern about the magnitude of the change in water demand projections and questions about how the projections changed and long term water use implications.
-
Theo Lane, District 7 Councilman, former Council Chairman, Greenwood County Council
We'd build a new school every five years and pay cash for it if that's what we chose to do
-
State Representative (House District 10)
State Rep. Thomas Beach said bill by Rep. April Cromer and co sponsored by Rep. Lee Hewitt would require data centers to pay for infrastructure including electricity and water.
-
U.S. Representative (R-South Carolina)
Rep. Nancy Mace said the U.S. must stay ahead of China with AI but should not put data centers in residential neighborhoods
-
U.S. Representative (R-South Carolina)
Rep. Ralph Norman said decisions about data centers should be left to states and local communities under 10th Amendment rights
-
Laurens County Vice Chairman
Matthew Brownlee says the time will be used to hear from residents, planners and industry experts and to look at issues like water use, electricity and environmental impacts
-
Laurens County Council Vice-chairman
Matthew Brownlee, Council Vice chairman, proposed the data center permit delay ordinance
-
Lee Zeldin, EPA director, said making the United States the artificial intelligence capital of the world is the agency's top priority
-
Rob Merchant, Planning Director
Many South Carolina counties studying the footprints of large data centers
-
U.S. Representative
U.S. Rep. Nancy Mace called for a one year moratorium on data center development in South Carolina
-
Governor of South Carolina
Governor Henry McMaster stated Google investment will strengthen South Carolina position as emerging leader in technology and innovation
Chief executives 1
Chief executives, presidents, founders and chairs of companies, in technology, data centers, power and elsewhere. Every state.
-
LightHouse CEO Nick Etschied stated the company has invested more than $28 million in the project
Candidates and campaigns 21
People running for office, their campaigns and their parties. A candidate who does not hold the office is not an official. Every state.
-
Pediatrician and Democratic U.S. Senate Nominee, South Carolina Democratic Party
Democratic U.S. Senate nominee Dr. Annie Andrews called for a two year statewide moratorium on new data center construction in South Carolina, arguing that unchecked hyperscale development threatens household electricity rates, water supplies, and county tax bases.
-
Nancy Lacore, Democratic candidate for U.S. House (District 1), South Carolina
They are a part of the national infrastructure now that is essential for the operations of our cell phones and our computers, and so we have to make sure that we are winning that race. China would love nothing more than for us to stop building data centers.
-
Libertarian U.S. Senate candidate for South Carolina
Libertarian candidate Kasie Whitener believes local communities should decide for themselves what to do about data centers without government permission
-
Democratic U.S. Senate candidate
Annie Andrews said her data center plan includes energy rate protections
-
Kasie Whitener, Libertarian U.S. Senate candidate, said local communities need to have a voice in data center decisions and it is a local issue.
-
Democratic candidate for U.S. House (District 1), South Carolina
In stark contrast, Nancy Lacore has called for a moratorium on data centers being built in South Carolina and will fight for federal guardrails to ensure the costs fall on the corporations, not consumers, while protecting the Lowcountry’s natural resources.
-
Republican candidate for U.S. House (District 2), South Carolina
Wilson, while also in support of guardrails, said a moratorium would take the option away from communities who want data centers.
-
Democratic gubernatorial candidate, South Carolina
Jermaine Johnson, Democratic gubernatorial candidate, supports a statewide moratorium on data centers until comprehensive approval and oversight processes are in place.
-
South Carolina Democratic Senate candidate
Andrews said large data centers are receiving billions of dollars in tax breaks while local families deal with high costs
-
Democratic candidate for U.S. Senate, South Carolina
Annie Andrews, Democratic candidate for U.S. Senate, accuses incumbent Darline Graham of supporting $70 billion in federal tax breaks for data centers.
-
South Carolina Democratic Senate candidate
Dr. Annie Andrews called for a two year moratorium on new data center projects in South Carolina
-
Dr. Annie Andrews, Senate candidate, called for a moratorium on data centers
-
Jermaine Johnson, Democratic nominee for governor, introduced a resolution in the General Assembly calling for a moratorium on data center construction until the Legislature passes an oversight and approval process.
-
Alan Wilson, Republican nominee for governor, said local communities should have the right to determine if they want data centers in their areas and that operators should be incentivized to lessen environmental impact.
Advocates and residents 6
Advocacy and community groups on every side, residents, neighbors and people speaking at public meetings. Every state.
-
Dr. Stephen Smith with Southern Alliance for Clean Energy expressed concern about electricity demand unknowns with future data center developments
-
Humans First
Data Center Revolt bus tour protesting data center development stopped in Spartanburg as sixth stop across 35 stops nationwide.
-
Frank Holleman, Southern Environmental Law Center, raised concerns about formaldehyde pollution from on site power generation
-
Southern Environmental Law Center advocated for a pause on data centers and raised concerns about a data center currently under construction on South Pine Street
-
Senior Attorney, Southern Environmental Law Center
Frank Holleman, senior attorney with Southern Environmental Law Center, questioned air quality modeling and formaldehyde exposure limits
-
Spartanburg resident
Eric A. runs a Facebook group against data centers with more than 8000 members
Other voices 6
Journalists, lawyers, former officials, and speakers the source describes in words that name none of the groups above. Every state.
-
Spartanburg Water (unnamed spokesperson)
Spartanburg Water reaffirmed that it has enough capacity to serve the project without negatively affecting existing or future customers.
-
Weston Adams, attorney with Nelson Mullins
Tech companies are committing to 100% offset of natural gas usage with renewable power on combined cycle gas turbine units
-
Weston Adams, attorney with Nelson Mullins
Parallel bills exist in the House and Senate to enable state utility commissions to address cost allocation for data center power generation, transmission, and distribution
-
Weston Adams, attorney with Nelson Mullins
Tech companies are covering their generation costs and sharing transmission and distribution costs for data centers
-
Weston Adams, attorney with Nelson Mullins
Ratepayer Protection Act has cleared a House subcommittee
-
Jessica Holdman, reporter, South Carolina Daily Gazette
Company originally said it needed 50 megawatts, then said it would need 450 megawatts worth of generators on site