Data Center Record.
Statements / Chief executives

Chief executives

Chief executives, presidents, founders and chairs of companies, in technology, data centers, power and elsewhere.

154 statements from 73 speakers in 35 states and provinces, April 2, 2024 to October 3, 2026. Each appears as said, with the date and the source. No verdict is attached.

Quoted most

Narrow the list
Reported in
Pick a state or province (37)
Topic

Topics are matched from the words of each statement and are a finding aid, not a fact about it.

Every statement, by speaker

Jeff Chavez

Volition · 18 statements (grouped by the head of a company)

  • Jeff Chavez, CEO of Volition, said the company's closed loop cooling system uses about the amount of water equivalent to one or two Utah households.

    September 24, 2026 · Utah · ksl.com local outlet · the record (Paraphrased; said in the source itself)

  • Volition claims its data center would use natural gas powered fuel cells producing substantially lower emissions and heat and requiring significantly less water than traditional data centers

    September 1, 2026 · Utah · KSL News local outlet · the record (Paraphrased; said in the source itself)

  • CEO Jeff Chavez previously sought to build a 30 to-40 megawatt fuel cell powered data center in nearby Provo before pivoting to Spanish Fork

    September 1, 2026 · Utah · Hoodline local outlet · the record (Paraphrased; said in the source itself)

  • Volition CEO said their closed loop cooling system would only need about two Utah households' worth of water to fill

    August 19, 2026 · Utah · FOX 13 News Utah local outlet · the record (Paraphrased; said in the source itself)

  • Volition CEO Jeff Chavez stated the company generates their own power using natural gas powered fuel cells that do not connect to the existing power grid

    August 19, 2026 · Utah · KSL.com local outlet · the record (Paraphrased; said in the source itself)

    Also reported by 1 source: The Salt Lake Tribune local outlet

  • Volition CEO Jeff Chavez said the proposed facility would use two households' worth of water to fill when first starting operations, then only one household's worth annually

    August 19, 2026 · Utah · KSL News local outlet · the record (Paraphrased; said in the source itself)

  • Volition said cooling systems are located indoors to mitigate noise impacts

    August 19, 2026 · Utah · KSL News local outlet · the record (Paraphrased; said in the source itself)

  • Volition CEO Jeff Chavez said their data center project would generate about 250 megawatts of power and use an existing distribution center of about 28 acres

    August 19, 2026 · Utah · FOX 13 News Utah local outlet · the record (Paraphrased; said in the source itself)

  • Volition plans to create a community fund contributing at least $500,000 per year for addiction recovery, food security, housing support and other community needs

    August 19, 2026 · Utah · KSL.com local outlet · the record (Paraphrased; said in the source itself)

  • Jeff Chavez, Volition CEO, stated data center developers should reuse existing infrastructure instead of buying thousands of acres

    August 18, 2026 · Utah · YouTube video · the record (Paraphrased; said in the source itself)

  • Facility would generate its own power with natural gas fuel cells, never connect to the grid, use closed loop cooling with a one time 500,000 gal fill and 250,000 gal per year, and request no tax breaks.

    August 18, 2026 · Utah · Daily Herald local outlet · the record (Paraphrased; content date; reported from elsewhere)

  • Volition's data centers produce zero draw on Spanish Fork's municipal power grid and use no local utility power

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • The fuel cell technology generates electricity through an electrochemical reaction with no combustion, flame, or fumes

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • Volition is not requesting any additional water rights from the city

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • Volition will include enforceable covenants in the development agreement covering water caps, noise limits, no grid connection, and no diesel

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • Volition commits to providing more than 500,000 dollars per year in direct community contributions and educational partnerships

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • Converting the existing industrial building to a data center reduces traffic from 3,500 trucks per month to 100-200 employee car trips per day with zero heavy truck traffic

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

  • Volition received a New Minor Source air quality permit approval from the Utah Department of Environmental Quality

    August 5, 2026 · Utah · YouTube video · the record (Paraphrased; content date; reported from elsewhere)

Mirko Bibic

president of Bell Canada · 7 statements (grouped by a company head)

  • Bibic said Bell could start with a 30-50 megawatt data centre in Quebec and expand later.

    September 17, 2026 · Quebec · Les Affaires local outlet (Paraphrased; said in the source itself)

  • Bibic said the Quebec data centre project is neither preliminary nor advanced, and will wait until after the provincial election campaign.

    September 17, 2026 · Quebec · Les Affaires local outlet (Paraphrased; said in the source itself)

  • Bibic said Bell wants a national ecosystem of AI specialized data centres that are all connected, including Quebec.

    September 17, 2026 · Quebec · Les Affaires local outlet (Paraphrased; said in the source itself)

  • Bell Canada president Mirko Bibic said the company wants to make major investments in Quebec with an AI data centre.

    September 17, 2026 · Quebec · Les Affaires local outlet (Paraphrased; said in the source itself)

  • Bibic said initial electricity need does not have to come entirely from Hydro Quebec; the facility could use natural gas as well.

    September 17, 2026 · Quebec · Les Affaires local outlet (Paraphrased; said in the source itself)

  • Mirko Bibic, president and CEO of BCE and Bell Canada stated the investment creates path to 1.2GW of AI capacity

    September 15, 2026 · Saskatchewan · Data Center Dynamics trade press (Paraphrased; said in the source itself)

  • Mirko Bibic said company is in advanced discussions with potential partners and won't have trouble filling the 1.2GW capacity over time

    September 14, 2026 · Saskatchewan · theglobeandmail.com national outlet (Paraphrased; said in the source itself)

Sam Altman

OpenAI CEO · 7 statements (grouped by the head of a company)

  • Sam Altman said pacing AI development will be well worth the cost and that government help is needed for international coordination

    September 14, 2026 · Pennsylvania · The Philadelphia Inquirer local outlet (Paraphrased; said in the source itself)

    Also reported by 2 sources: Anchorage Daily News local outlet , Santa Fe New Mexican local outlet

  • OpenAI CEO Sam Altman said it takes 38,000 ChatGPT queries to use as much water as producing a single almond in California

    September 8, 2026 · California · thebusinessjournal.com local outlet (Paraphrased; said in the source itself)

    Also reported by 1 source: WRAL local outlet

  • Sam Altman, OpenAI CEO, compared rejecting AI to rejecting electricity, calling AI adoption essential for economic growth.

    September 3, 2026 · North Carolina · ETV Bharat local outlet (Paraphrased; said in the source itself)

  • About 38,000 ChatGPT queries use the water of one California almond; modern large data centers use about as much water as an office building; evaporative cooling has not been used in a long time. Speaker said the figure was from memory and might be wrong.

    September 2, 2026 · Tom's Hardware trade press (Paraphrased; content date; reported from elsewhere)

  • Altman previously publicly pointed out that the space data center initiative is not realistic.

    July 12, 2026 · Oregon · 매일경제 local outlet · the record (Paraphrased; said in the source itself)

  • Sam Altman said Musk is selling 'short term' space data centers to investors.

    July 12, 2026 · Oregon · 매일경제 local outlet · the record (Paraphrased; said in the source itself)

  • The average query uses about 0.34 watt hours and about 0.000085 gallons of water, roughly one fifteenth of a teaspoon.

    June 16, 2025 · blog.samaltman.com primary source (Quoted; content date; reported from elsewhere)

Jason Green

Chief Operating Officer, Raedan · 6 statements (grouped by the head of a company)

  • Jason Green, CEO of Raeden, said council did a poor job keeping the crowd civil and questioned why the mayor was not in attendance.

    September 23, 2026 · Colorado · Colorado Public Radio local outlet · the record (Paraphrased; said in the source itself)

  • Raeden founder Jason Green claimed there is a 40 megawatt data center 100 feet from homes in Colorado Springs; Colorado Springs Utilities said the largest data center customer is around six megawatts.

    September 18, 2026 · Colorado · Colorado Public Radio local outlet · the record (Paraphrased; said in the source itself)

  • Green stated the company views Project Taurus as something positive for the Colorado Springs community

    May 15, 2026 · Colorado · KRDO local outlet · the record (Paraphrased; said in the source itself)

  • Jason Green, Chief Operating Officer for Raedan, stated that the company will continue pursuing the project despite community opposition and threats

    May 15, 2026 · Colorado · KRDO local outlet · the record (Paraphrased; said in the source itself)

  • Green stated developers would provide full data and studies required for permitting the project

    April 7, 2026 · Colorado · KOAA News 5 local outlet · the record (Paraphrased; said in the source itself)

  • Jason Green, co founder of the development company, acknowledged concerns about energy consumption, heat, water for cooling, and noise pollution

    April 7, 2026 · Colorado · KOAA News 5 local outlet · the record (Paraphrased; said in the source itself)

Matt Garman

CEO of Amazon Web Services · 5 statements (grouped by the head of a company)

  • Amazon says direct data center water consumption accounts for 0.5% of all industrial water usage in the United States

    October 3, 2026 · New York · TechCrunch national outlet (Paraphrased; said in the source itself)

  • Amazon says more than 100 data center moratoriums are being considered across the United States

    October 3, 2026 · New York · TechCrunch national outlet (Paraphrased; said in the source itself)

  • Amazon claims data center generators run roughly 10 hours per year for maintenance testing, idle 99.9% of the time

    October 3, 2026 · New York · TechCrunch national outlet (Paraphrased; said in the source itself)

  • Amazon Web Services CEO Matt Garman said the company has stopped using nondisclosure agreements (NDAs) in its dealings with government agencies

    October 3, 2026 · New York · TechCrunch national outlet (Paraphrased; said in the source itself)

  • Amazon has contributed more than $1 billion to communities across the U.S. in which the company has a meaningful data center presence over the past three years

    October 3, 2026 · New York · TechCrunch national outlet (Paraphrased; said in the source itself)

Dana Adams

Vantage North America president · 5 statements (grouped by the head of a company)

  • Vantage North America President Dana Adams said the facility will support Oracle and their end user OpenAI running AI workloads out of the building.

    July 29, 2026 · Wisconsin · TMJ4 News local outlet · the record (Paraphrased; said in the source itself)

  • Tax revenue from the facility will begin flowing predominantly when construction is complete.

    July 29, 2026 · Wisconsin · TMJ4 News local outlet · the record (Paraphrased; said in the source itself)

  • Vantage will hire local residents including engineers, operators, technicians, network specialists, and security specialists.

    July 28, 2026 · Wisconsin · YouTube video · the record (Paraphrased; said in the source itself)

  • Air containment isolates cold air or hot air so they do not mix, increasing efficiency and reducing cooling requirements.

    July 28, 2026 · Wisconsin · YouTube video · the record (Paraphrased; said in the source itself)

  • Project is a cornerstone of Project Stargate, a $500 billion public private AI initiative

    December 23, 2025 · Wisconsin · Ozaukee Press local outlet · the record (Paraphrased; said in the source itself)

Joi Harris

DTE Energy CEO · 4 statements (grouped by the head of a utility)

  • Joi Harris, DTE Energy president and CEO, said the plan would be $3.5 billion less expensive than the company's previous IRP from 2022

    September 24, 2026 · Michigan · Michigan Public local outlet · the record (Paraphrased; said in the source itself)

  • DTE Energy has 2.4 gigawatts of executed agreements with hyperscalers including a 1.4 GW Oracle deal under construction and a 1 GW Google agreement in Van Buren Township.

    September 18, 2026 · Michigan · 24/7 Wall St. national outlet (Paraphrased; said in the source itself)

  • CEO Joi Harris said signing 3 GW of contracts unlocks 8%-plus EPS growth.

    September 18, 2026 · Michigan · 24/7 Wall St. national outlet (Paraphrased; said in the source itself)

  • DTE Energy has another five to six gigawatts of pipeline with two gigawatts in advanced discussions targeting a signed contract by year end.

    September 18, 2026 · Michigan · 24/7 Wall St. national outlet (Paraphrased; said in the source itself)

Bryan Hannegan

president and CEO of Holy Cross Energy · 4 statements (grouped by the head of a utility)

  • Holy Cross Energy serves approximately 46,500 member owners across Garfield, Pitkin and Eagle counties with about 90% carbon free energy.

    September 18, 2026 · Colorado · Aspen Daily News local outlet (Paraphrased; said in the source itself)

  • Hannegan said his organization has had multiple conversations with developers wanting to build smaller data centers.

    September 18, 2026 · Colorado · Aspen Daily News local outlet (Paraphrased; said in the source itself)

  • Bryan Hannegan, CEO of Holy Cross Energy, told Garfield County commissioners that he believes the county could see data center developers asking to build by 2031.

    September 18, 2026 · Colorado · Aspen Daily News local outlet (Paraphrased; said in the source itself)

  • Hannegan predicted more likely scenario: Garfield County could be eyed for smaller data centers consuming 10 to 20 megawatts.

    September 18, 2026 · Colorado · Aspen Daily News local outlet (Paraphrased; said in the source itself)

Dario Amodei

Anthropic CEO · 4 statements (grouped by the head of a company)

  • Dario Amodei, CEO of Anthropic, called for slowing the pace of AI development.

    September 16, 2026 · Mississippi · tippahnews.com local outlet (Paraphrased; said in the source itself)

  • Amodei cited a July 2026 cyberattack by OpenAI models on Hugging Face as reason to slow AI development

    September 14, 2026 · Pennsylvania · The Philadelphia Inquirer local outlet (Paraphrased; said in the source itself)

    Also reported by 1 source: Anchorage Daily News local outlet

  • Dario Amodei published essay calling for slower development of AI, citing AI's growing ability to build next generation of AI and July cyberattack by OpenAI models

    September 14, 2026 · New Mexico · Santa Fe New Mexican local outlet (Paraphrased; content date; reported from elsewhere)

    Also reported by 2 sources: The Philadelphia Inquirer local outlet , Anchorage Daily News local outlet

  • Tech leaders including Dario Amodei, Sam Altman, and Elon Musk are calling for greater government oversight of AI

    September 14, 2026 · Pennsylvania · The Philadelphia Inquirer local outlet (Paraphrased; said in the source itself)

Hassane El-Khoury

CEO of Onsemi · 3 statements (grouped by a company head)

  • Hassane El Khoury, CEO of Onsemi, said data center moratoriums like New York's are short sighted

    September 11, 2026 · New York · Semafor national outlet (Paraphrased; said in the source itself)

  • Onsemi is discussing energy transparency standards with federal and state lawmakers in Arizona

    September 11, 2026 · New York · Semafor national outlet (Paraphrased; said in the source itself)

  • El Khoury said policymakers should demand data centers report energy efficiency metrics rather than blanket bans

    September 11, 2026 · New York · Semafor national outlet (Paraphrased; said in the source itself)

Jensen Huang

Nvidia CEO · 3 statements (grouped by the head of a company)

  • Jensen Huang stated every country needs AI data center infrastructure as foundational as water, roads, electricity and internet.

    September 3, 2026 · North Carolina · ETV Bharat local outlet (Paraphrased; said in the source itself)

  • Jensen Huang, Nvidia CEO, at G20 Innovation Ministerial said work that takes ten years could take one year, and year long projects could finish within a month.

    September 3, 2026 · North Carolina · ETV Bharat local outlet (Paraphrased; said in the source itself)

  • Nvidia CEO Jensen Huang said now is the time to scale the AI infrastructure that will power the next industrial revolution

    August 17, 2026 · Ohio · Washington Examiner national outlet · the record (Paraphrased; said in the source itself)

Drew Marsh

chair and CEO of Entergy · 3 statements (grouped by the head of a utility)

  • Drew Marsh, Entergy chair and CEO, said large customers like data centers help pick up grid maintenance costs existing customers would otherwise bear alone

    August 27, 2026 · Mississippi · PR Newswire local outlet · the record (Paraphrased; said in the source itself)

  • Drew Marsh, Chair and CEO, Entergy, says Google's investment will put Arkansas at the forefront of American innovation as the new facility joins Google's global network

    October 8, 2025 · Arkansas · YouTube video · the record (Paraphrased; said in the source itself)

  • Entergy Arkansas partnering to power the project

    October 2, 2025 · Arkansas · arkansasonline.com local outlet · the record (Paraphrased; said in the source itself)

Peter Marin

T5 CEO · 2 statements (grouped by a company head)

  • T5 stated it has a separate rate agreement with ComEd and will pay for all power consumed.

    September 28, 2026 · Illinois · NBC 5 Chicago local outlet · the record (Paraphrased; content date; reported from elsewhere)

  • T5 CEO Peter Marin stated the company followed all procedural requirements and conducted 18 public meetings with advance notice.

    September 28, 2026 · Illinois · NBC 5 Chicago local outlet · the record (Paraphrased; content date; reported from elsewhere)

Milton Todd Ault III

Executive Chairman of Hyperscale Data · 2 statements (grouped by the head of a company)

  • Company believes separation would improve transparency and position Michigan facility to operate as standalone AI data center

    September 22, 2026 · Michigan · TradingView local outlet (Paraphrased; said in the source itself)

  • Hyperscale Data intends to form Patriot BTC subsidiary to hold cryptocurrency mining operations, Montana data center, Bitcoin miners and related infrastructure

    September 22, 2026 · Michigan · TradingView local outlet (Paraphrased; said in the source itself)

Trenton Thornock

Prometheus Hyperscale founder · 2 statements (grouped by the head of a company)

  • Prometheus Founder Trenton Thornock said during an information session that the data center itself would not provide long term, high paying jobs for the community

    September 15, 2026 · Wyoming · Oil City News local outlet · the record (Paraphrased; said in the source itself)

  • Prometheus founder Trenton Thornock previously said the data center would be powered by natural gas reciprocating engines supplied by Jenbacher

    August 31, 2026 · Wyoming · Oil City News local outlet · the record (Paraphrased; content date; reported from elsewhere)

Ray Conley

CEO of Creekstone Energy · 2 statements (grouped by the head of a company)

  • GIGAWATER technology aims to capture water vapor from natural gas combustion and convert it into usable water.

    September 9, 2026 · Utah · KSL local outlet (Paraphrased; said in the source itself)

  • Water capture technology remains in research and testing stage and has not yet been proven

    September 9, 2026 · Utah · Fox 13 Salt Lake City local outlet (Paraphrased; said in the source itself)

Louis Wolfson

DeepGreen Western Passage managing member · 2 statements (grouped by the head of a company)

  • Developer Louis Wolfson said preliminary permit is a license to study, not a license to construct

    September 7, 2026 · Maine · newscentermaine.com national outlet · the record (Paraphrased; said in the source itself)

  • Company said it wants to create a sealed, behind the meter facility that would not use outside power.

    August 10, 2026 · Maine · Maine Public local outlet · the record (Paraphrased; said in the source itself)

Ruth Porat

Google President, Chief Investment Officer · 2 statements (grouped by the head of a company)

  • Google states it is collaborating with Entergy to ensure it covers the full cost of powering the facility

    September 3, 2026 · Arkansas · YouTube video · the record (Paraphrased; said in the source itself)

  • Google executive Ruth Porat said at 2025 groundbreaking that Google would cover the full cost of powering the West Memphis facility

    September 3, 2026 · Arkansas · Gadget Review national outlet · the record (Paraphrased; said in the source itself)

William Horne

Hyperscale Data Chief Executive Officer · 2 statements (grouped by the head of a company)

  • William Horne, Hyperscale Data CEO, said the facility is being prepared for AI usage and customer deployment.

    September 3, 2026 · Michigan · Data Center Dynamics trade press · the record (Paraphrased; said in the source itself)

  • CEO William Horne said the transition to AI data center operations will allow focus on the facility's preparation for customer usage

    September 2, 2026 · Michigan · PR Newswire local outlet · the record (Paraphrased; said in the source itself)

Michael Rose

President and CEO · 2 statements (grouped by a company head)

  • 60 percent of LEO Construction's staff works on data center projects in northern Virginia

    September 1, 2026 · Virginia · acppubs.com local outlet (Paraphrased; said in the source itself)

  • LEO Construction operates in Prince William, Loudoun, Stafford, and Fauquier counties

    September 1, 2026 · Virginia · acppubs.com local outlet (Paraphrased; said in the source itself)

John Watson

Bell Canada Group President · 2 statements (grouped by a company head)

  • John Watson, Bell Canada group president, states that diesel generators are being installed at the site for backup power

    August 27, 2026 · Saskatchewan · BNN Bloomberg local outlet (Paraphrased; said in the source itself)

  • Bell Canada Group President John Watson said company has engaged community significantly on Bell AI data centre project and implemented measures including 12 foot berm and 8 foot fence in response to feedback

    August 27, 2026 · Saskatchewan · 620 CKRM local outlet (Paraphrased; said in the source itself)

Tag Greason

QTS Co-CEO · 2 statements (grouped by the head of a company)

  • QTS announced a five million dollar grant to local organizations including the Iowa Workforce Development Foundation

    July 14, 2026 · Iowa · thegazette.com local outlet · the record (Paraphrased; said in the source itself)

  • Grant intended to address labor concerns for data center development

    July 14, 2026 · Iowa · thegazette.com local outlet · the record (Paraphrased; said in the source itself)

Laura Landreaux

president and CEO of Entergy Arkansas · 2 statements (grouped by the head of a utility)

  • The partnership involves Entergy Arkansas, Google, and ICF working together to deliver energy efficiency improvements

    April 29, 2026 · Arkansas · Entergy local outlet · the record (Paraphrased; said in the source itself)

  • Entergy Arkansas President and CEO Laura Landreaux said Google's investment will bring unprecedented economic opportunity to Arkansas

    October 2, 2025 · Arkansas · KATV local outlet · the record (Paraphrased; said in the source itself)

KR Sridhar

Bloom Energy CEO · 1 statement (grouped by a company head)

  • KR Sridhar, Bloom Energy CEO, stated that Bloom boxes are fungible and can be redirected from one location to another after shipment, unlike conventional power plants

    October 2, 2026 · New Mexico · TradingView local outlet · the record (Paraphrased; content date; reported from elsewhere)

Melissa Seixas

Duke Energy Florida president · 1 statement (grouped by the head of a utility)

  • Duke Energy Florida does not currently have any large load data center customers within its service territory but has developed a proposal with safeguards requiring new data center customers to sign long term agreements, provide significant collateral, meet minimum payment requirements, and pay penalties for early termination

    October 2, 2026 · Florida · Florida Politics local outlet (Paraphrased; said in the source itself)

Rich Sloan

CEO of WAVR Technologies · 1 statement (grouped by a company head)

  • WAVR Technologies targeting 2028 for consumer ready version of atmospheric water harvesting technology.

    October 2, 2026 · Nevada · KSNV local outlet (Paraphrased; said in the source itself)

John Arnold

Arnold Ventures Co-founder and Co-Chair · 1 statement (grouped by a company head)

  • John Arnold, Arnold Ventures Co founder and Co Chair, discussed why data centers have become a lightning rod topic ahead of midterm elections.

    October 1, 2026 · Texas · cnbc.com national outlet (Paraphrased; said in the source itself)

Archie Collins

Tampa Electric Co. chief executive · 1 statement (grouped by the head of a utility)

  • TECO received constant calls from data center companies interested in the area

    September 30, 2026 · Florida · Tampa Bay Times local outlet (Paraphrased; said in the source itself)

Kristen O'Neill

CEO of Turin Management · 1 statement (grouped by a company head)

  • Turin Management, which owns the old Remington site in Ilion, stated it is exploring both manufacturing and data center options but emphasized no data center end user is currently committed to the site.

    September 29, 2026 · New York · spectrumlocalnews.com local outlet (Paraphrased; said in the source itself)

Lisa Grow

Idaho Power President and CEO · 1 statement (grouped by the head of a utility)

  • Lisa Grow says the pace and scale of Idaho's growth is unprecedented and Idaho Power must adapt and innovate to keep up with growth statewide and manage resources to keep costs down.

    September 25, 2026 · Idaho · Idaho Business Review local outlet · the record (Paraphrased; said in the source itself)

Clay Magouyrk

co-CEO at Oracle · 1 statement (grouped by the head of a company)

  • Clay Magouyrk, co CEO at Oracle, stated neither Project Jupiter sites will have impact on FY 2027 revenue or earnings guidance

    September 24, 2026 · New Mexico · SuaraGarut.ID local outlet · the record (Paraphrased; said in the source itself)

    Also reported by 1 source: americanbazaaronline.com local outlet

Aaron Starks

CEO and president of 47G · 1 statement (grouped by a company head)

  • Aaron Starks said the four major areas of AI capability are chips, data centers, electricity and talent

    September 23, 2026 · Utah · Deseret News local outlet · the record (Paraphrased; said in the source itself)

Andy Power

Digital Realty CEO · 1 statement (grouped by the head of a company)

  • Digital Realty CEO Andy Power said the project will strengthen intercontinental connectivity across the company's Los Angeles campus and create a more scalable environment for customers connecting across regions.

    September 23, 2026 · California · fiercewireless.com local outlet · the record (Paraphrased; said in the source itself)

Calvin Butler

Exelon CEO · 1 statement (grouped by the head of a utility)

  • Calvin Butler, Exelon CEO, said political backlash to data center development is owed to lack of communication and community buy in

    September 23, 2026 · New York · RTO Insider trade press (Paraphrased; said in the source itself)

Craig Thompson

Co-founder, Allegiance Search · 1 statement (grouped by a company head)

  • Craig Thompson argues that on top of powered land and capital, developers need public support, as community opposition is creating delays and uncertainty.

    September 23, 2026 · Texas · Construction Dive local outlet (Paraphrased; content date; reported from elsewhere)

Milton Ault III

Executive Chairman, Hyperscale Data · 1 statement (grouped by the head of a company)

  • Hyperscale Data is separating bitcoin mining operations in Montana from Michigan AI data center operations.

    September 22, 2026 · Michigan · Pulse 2.0 local outlet (Paraphrased; said in the source itself)

Matt Landek

President and CEO of L5 Mission Critical · 1 statement (grouped by a company head)

  • Matt Landek, most recently was the Global President of JLL's Data Center and Critical Environments, lead a workforce of 2,500 employees across 340 data centers across the globe

    September 21, 2026 · Illinois · REJournals local outlet (Paraphrased; said in the source itself)

Sam Uden

co-founder and managing director, Net Zero California · 1 statement (grouped by a company head)

  • Sam Uden, co founder and managing director at Net Zero California, said state lawmakers have met the moment with robust set of protections.

    September 21, 2026 · California · KESQ local outlet (Paraphrased; said in the source itself)

Bob Ridgley

Ridgley farm owner · 1 statement (grouped by a company head)

  • Data center projects have already been greenlit around mid Missouri, including Montgomery and Callaway Counties, with one project in construction within a mile of Ridgley's farm.

    September 16, 2026 · Missouri · KRCG local outlet (Paraphrased; said in the source itself)

Gerard Gibert

entrepreneur and technologist · 1 statement (grouped by a company head)

  • Gerard Gibert, entrepreneur and co founder of Venture Technologies (founded 1986, sold 2019), addresses AI and data center concerns

    September 16, 2026 · Mississippi · SuperTalk Mississippi Media local outlet (Paraphrased; said in the source itself)

Jeff Uphues

DC BLOX CEO · 1 statement (grouped by the head of a company)

  • Jeff Uphues, DC BLOX CEO, stated Pridemore's track record will be instrumental in advancing energy strategy initiatives

    September 16, 2026 · Georgia · Atlanta News First local outlet (Paraphrased; said in the source itself)

Andrew Power

CEO of Digital Realty · 1 statement (grouped by the head of a company)

  • Andrew Power said pledges by Anthropic, OpenAI and xAI for a slowdown in AI development do not mean pencils down for AI and the real estate that supports it

    September 15, 2026 · Virginia · CNBC national outlet (Paraphrased; said in the source itself)

Lexi Clendenen

MTNO Board Chair · 1 statement (grouped by a company head)

  • Marshall Terrace Neighborhood Organization and other groups are drafting a resolution against data centers

    September 15, 2026 · Minnesota · kare11.com national outlet (Paraphrased; said in the source itself)

Jamie Banks

founder and president of Quiet Communities · 1 statement (grouped by a company head)

  • Jamie Banks, founder and president of Quiet Communities, stated that noise pollution is linked to cardiovascular disease, sleep disruption, stress and cognitive impairment.

    September 14, 2026 · Georgia · GlobeNewswire local outlet (Paraphrased; said in the source itself)

Bill Gates

Microsoft co-founder · 1 statement (grouped by the head of a company)

  • Bill Gates warns AI and data centers could become the worst source of injustice without solutions addressing community concerns about energy and water

    September 11, 2026 · Alabama · The American Prospect local outlet (Paraphrased; said in the source itself)

John Johnson

Patmos founder · 1 statement (grouped by the head of a company)

  • Patmos founder John Johnson told neighbors at a community meeting that generators will have mufflers and the loudest equipment will stay inside, with the site quieter than the old Walmart.

    September 11, 2026 · Alabama · WBRC local outlet · the record (Paraphrased; said in the source itself)

Keshaun Pearson

co-founder of Memphis Community Against Pollution · 1 statement (grouped by a company head)

  • Memphis community reports cancer rate 4.1 times the national average near xAI data center

    September 11, 2026 · Tennessee · WSMV local outlet · the record (Paraphrased; said in the source itself)

Wes Cummins

Applied Digital chairman and CEO · 1 statement (grouped by the head of a company)

Becky Valcq

Alliant Energy President of Wisconsin operations · 1 statement (grouped by the head of a utility)

  • Becky Valcq, President of Alliant Energy's Wisconsin electric company and Vice President of Energy Delivery, spoke at an educational session about data centers

    September 10, 2026 · Wisconsin · The Sheboygan Press local outlet (Paraphrased; said in the source itself)

Jason Singer

co-managing member of Plainsmen Holdings · 1 statement (grouped by a company head)

  • Jason Singer, co managing member of Plainsmen Holdings, said the project addresses common concerns about data center power and water use

    September 9, 2026 · Oklahoma · KOKH local outlet (Paraphrased; said in the source itself)

Dave Schaeffer

CEO Cogent Communications · 1 statement (grouped by a company head)

  • There is insufficient fiber supply despite advances in transmission capacity, with hyperscalers building two or three smaller data centers in a 30-35 mile circumference instead of one in major metros

    September 8, 2026 · Texas · fierce-network.com local outlet (Paraphrased; said in the source itself)

Jennifer Hawks Bland

CEO NewYorkBIO · 1 statement (grouped by a company head)

  • NewYorkBIO calls for Governor Hochul veto and refined approach distinguishing commercial data centers from research facilities

    September 7, 2026 · New York · Buffalo News local outlet (Paraphrased; said in the source itself)

Annalisa Bloodworth

chief executive, Oglethorpe Power Corp. · 1 statement (grouped by the head of a utility)

  • Annalisa Bloodworth, chief executive of Oglethorpe Power Corp., described the EPA rule as deeply flawed and the most irrational environmental regulation she has personally encountered

    September 6, 2026 · National · Yahoo local outlet (Paraphrased; said in the source itself)

Todd Brickhouse

CEO and general manager, Basin Electric Power Cooperative · 1 statement (grouped by the head of a utility)

  • Todd Brickhouse of Basin Electric Power Cooperative said renewables account for 30 percent of Basin's portfolio, but data centers' very high load factor made backup heavy systems less appealing

    September 6, 2026 · National · Yahoo local outlet (Paraphrased; said in the source itself)

Demis Hassabis

Google DeepMind · 1 statement (grouped by the head of a company)

  • Demis Hassabis stated achieving human level AI would unleash ten times the impact of the Industrial Revolution.

    September 3, 2026 · North Carolina · ETV Bharat local outlet (Paraphrased; said in the source itself)

Doug McGowen

MLGW President and CEO · 1 statement (grouped by a company head)

  • MLGW customers have seen no electric rate increase due to data centers in Memphis operated by SpaceXAI and other companies

    September 3, 2026 · Arkansas · WREG.com national outlet · the record (Paraphrased; said in the source itself)

Josh Skelton

Minnesota Power CEO · 1 statement (grouped by the head of a utility)

  • Josh Skelton, Minnesota Power CEO, said the modernization provides flexibility when extreme weather hits, system conditions change quickly, or energy is needed in a different place than expected.

    September 3, 2026 · Minnesota · Engineering News-Record local outlet · the record (Paraphrased; said in the source itself)

Edmond Jordan

Representative, Louisiana Legislative Black Caucus chairman · 1 statement (grouped by a company head)

  • Rep. Edmond Jordan, chairman of Louisiana Legislative Black Caucus, rejected characterization that his 2024 vote represented endorsement of data centers

    September 2, 2026 · Louisiana · thecentersquare.com local outlet · the record (Paraphrased; said in the source itself)

Olivier Le Peuch

SLB Chief Executive Officer · 1 statement (grouped by a company head)

  • Olivier Le Peuch, SLB CEO, stated that artificial intelligence is driving the most significant infrastructure investment cycle and called the transaction precipitous to the company's ambition to become an industrial technology partner to the data center industry

    September 1, 2026 · Texas · thetexan.news local outlet (Paraphrased; said in the source itself)

Scott Gromer

Mesa Power Solutions CEO · 1 statement (grouped by a company head)

  • Mesa Power Solutions CEO Scott Gromer said projects like this attract Wyoming companies and Wyoming workers with jobs and supply chain staying in Wyoming

    August 31, 2026 · Wyoming · Oil City News local outlet · the record (Paraphrased; content date; reported from elsewhere)

Swati Dandekar

chairman Bright Future Iowa · 1 statement (grouped by a company head)

  • Swati Dandekar, chairman of Bright Future Iowa and former Iowa Utilities Board member, states that Iowa should manage data center development with clear rules and community benefits like Google's Council Bluffs Wi Fi investment and Microsoft's Quincy water infrastructure partnership.

    August 30, 2026 · Iowa · thegazette.com local outlet (Paraphrased; said in the source itself)

Kim Greene

Georgia Power CEO · 1 statement (grouped by the head of a utility)

  • Georgia Power CEO Kim Greene said growth is not pushing electric rates up in Georgia

    August 28, 2026 · Georgia · WJCL local outlet · the record (Paraphrased; content date; reported from elsewhere)

    Also reported by 1 source: washingtonreporter.news query feed

Haley Fisackerly

Entergy Mississippi president and CEO · 1 statement (grouped by the head of a utility)

  • Haley Fisackerly, Entergy Mississippi president and CEO, said data center revenues are providing benefits by covering costs of power plant replacement and grid improvements

    August 27, 2026 · Mississippi · Entergy local outlet (Paraphrased; said in the source itself)

Nick Etschied

LightHouse CEO · 1 statement (grouped by a company head)

  • LightHouse CEO Nick Etschied stated the company has invested more than $28 million in the project

    August 25, 2026 · South Carolina · WYFF local outlet · the record (Paraphrased; said in the source itself)

Igor Stamenkovic

CEO · 1 statement (grouped by a company head)

  • CEO Igor Stamenkovic said the larger facility will increase the company's ability to manufacture and test complete power systems domestically while creating additional jobs

    August 24, 2026 · Colorado · citybiz local outlet · the record (Paraphrased; said in the source itself)

Michael Flanagan

CFO and Igor Stamenkovic, CEO · 1 statement (grouped by a company head)

  • The facility doubled SENS's footprint from two years ago

    August 24, 2026 · Colorado · citybiz local outlet · the record (Paraphrased; said in the source itself)

Jon Hawkins

Representative, R-Pleasant Grove, chair, Economic Development and Workforce Services Interim Committee · 1 statement (grouped by a company head)

  • Rep. Jon Hawkins, R Pleasant Grove, chair of the Economic Development and Workforce Services Interim Committee, stated that lawmakers have received probably hundreds of emails on data centers and that it is a big concern

    August 20, 2026 · Utah · Utah News Dispatch local outlet · the record (Paraphrased; said in the source itself)

Phillip May

Entergy Louisiana President and CEO · 1 statement (grouped by the head of a utility)

  • Phillip May, Entergy Louisiana President and CEO, stated other customers will be protected from rate increases due to Meta paying full infrastructure costs

    August 14, 2026 · Louisiana · Yahoo Finance local outlet · the record (Paraphrased; said in the source itself)

Kyle Green

Representative, House Democratic Caucus chairman · 1 statement (grouped by a company head)

Andrew Marsh

Entergy Corp. CEO · 1 statement (grouped by the head of a utility)

  • Andrew Marsh, Entergy Corp. CEO, says the partnership drives economic development and builds communities

    October 2, 2025 · Arkansas · YouTube video · the record (Paraphrased; said in the source itself)

Ian McClarty

President, Phoenix NAP · 1 statement (grouped by a company head)

  • The recent surge in demand for data centers is driven by artificial intelligence

    August 20, 2025 · Arizona · YouTube video · the record (Paraphrased; said in the source itself)

Jim Trout

CEO · 1 statement (grouped by a company head)

  • Jim Trout is CEO with experience as president of CRG West and Senior VP at Digital Realty Trust

    June 1, 2024 · California · Data Center Knowledge trade press · the record (Paraphrased; said in the source itself)

Raul K. Martynek

DataBank CEO · 1 statement (grouped by the head of a company)

  • DataBank CEO Raul K. Martynek said the purchase aligns with DataBank's strategy of owning the largest edge data center footprint in the United States.

    April 2, 2024 · Nevada · EdgeIR local outlet · the record (Paraphrased; said in the source itself)

The group comes from the words the source gives for the speaker: the name, the title and the organization. It is a reading aid, not a fact about anyone; how the groups are read.

This page as data CSVJSON
Cite this page

Data Center Record, "Statements about data centers: Chief executives", https://datacenterrecord.org/statements/chief-executives. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Group value
chief-executives
Statements
154
Speakers, one key per name
73
Placed by the stored speaker type or no rule
0