SpaceXAI Memphis data centers
SpaceXAI is expanding data center operations in Memphis, with Elon Musk confirming a fourth facility and the company adding another center in Whitehaven while removing gas turbines deemed illegal. It is reported, as reported August 20, 2026. Lawsuit filed in August 2026 seeks $30 million in damages, $20 million of which is punitive (reported September 18, 2026).
How much power it needs, how much water it would use and who would use it have not been disclosed.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Land
- Not disclosed
- Power it would draw
- Not disclosed
- Water
- Not disclosed
- Who leads it
- SpaceXAI
- as stated by the source
- Who would use it
- Not disclosed
- Jobs once it runs
- Not disclosed
- Tax each year
- Not disclosed
- Where its power comes from
- gas turbines
- as stated by the source [6]
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | Not disclosed | |||
| How much water it would use | Not disclosed | |||
| How loud it would be | Not disclosed | |||
| Jobs once it runs | Not disclosed | |||
| Tax it would pay each year | Not disclosed |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | SpaceXAI | as stated by the source | September 25, 2026 | |
| Who is constructing it | Not disclosed | |||
| How much land | Not disclosed | |||
| Where its power comes from | gas turbines | as stated by the source | [6] independent.co.uk | September 25, 2026 |
| Grid connection | Not disclosed | |||
| How it is cooled | Not disclosed |
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water useA state water right filing or a water supply agreement.
- Who would use itA lease announcement or a tenant named in a filing.
- Power the campus would drawA utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
- Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.
What was decided
Acts of Shelby County and Memphis about data centers, on the record with their source. A rule about the area is not a decision about this record.
| Date | Who | Decision | Source |
|---|---|---|---|
| Memphis | Memphis imposed data center moratorium while SpaceXAI continues expansion in Mississippi less than a mile away | dailymemphian.com | |
| Memphis | Three Memphis City Council members J.B. Smiley Jr., Yolanda Cooper Sutton, and Jana Swearengen Washington proposing 12 month moratorium on data center development | thecentersquare.com | |
| Memphis | xAI required government officials to sign NDAs during development of the Colossus facility near Memphis, Tennessee | newsweek.com | |
| Memphis | Memphis City Council ordinance for temporary moratorium on data center permits passed first reading on August 18. | yahoo.com | |
| Memphis | Memphis City Council proposed a temporary moratorium on new data center development | radionwtn.com |
What happened
-
(source date; the content gives no date of its own)
SpaceXAI agreed to timeline for removal of turbines with Mississippi Department of Environmental Quality, all turbines to be removed by July 2027. [6]
-
(source date; the content gives no date of its own)
Operations at Colossus II came online in January 2026. [6]
-
(source date; the content gives no date of its own)
Colossus I opened in 2024. [6]
-
(source date; the content gives no date of its own)
Lawsuit filed in August 2026 seeks $30 million in damages, $20 million of which is punitive. [6]
-
(source date; the content gives no date of its own)
Vicent died in Florida in February, months after the fall. [6]
-
(source date; the content gives no date of its own)
Worker Alexis Vicent fell from a mezzanine at Colossus II in August 2025. [6]
-
(source date; the content gives no date of its own)
Residents filed a lawsuit challenging the noise pollution from the data center [9]
-
(source date; the content gives no date of its own)
Elon Musk announced the xAI campus could expand to 10 times its current capacity [9]
3 earlier entries
-
(source date; the content gives no date of its own)
xAI promised to replace the gas turbines in one year with quieter permanent ones as of July 2026 [9]
-
(source date; the content gives no date of its own)
xAI's hyperscale data center in Memphis opened in 2024 [2]
-
· reported (source date; the content gives no date of its own)
TVA Board approved over 100 megawatts of firm power for SpaceXAI Memphis operations. [7]
The full SpaceXAI Memphis data centers timeline, in order
8 corrections to this record
Every correction, with its reason
-
· the summary of a record items row
the record's rules: the sentence was the source's wording or carried a number not in the card's facts; written again from the article The old and new text.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.
-
· the kind of source of a history entry
Tier after resolution (2026-09-21). The source on file is radionwtn.com, the publisher's own page. The item reached the record through Google News: "data center" Tennessee, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of sources. DECISIONS section 7. The speaker, the claim, the date and the url are unchanged. The day's label corrections.
-
· the kind of source of a history entry
Tier after resolution (2026-09-21). The source on file is radionwtn.com, the publisher's own page. The item reached the record through Google News: "data center" Tennessee, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of sources. DECISIONS section 7. The speaker, the claim, the date and the url are unchanged. The day's label corrections.
Every correction on the record is on the corrections page.
What was said
Memphis community reports cancer rate 4.1 times the national average near xAI data center
The site
Where in Shelby County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.
Tap a pin for the data center, the parcel for its record
- This record: Proposed, ringed
- data center
- Dashed edge: the exact site is not in the public record
- Smaller pins: 5 other published records in Tennessee
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
- Where
- Memphis, Shelby County, Tennessee
- How exactly it is located
- County level, the county seat
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- Nearest records are not computed for a record placed at a county seat.
Questions about this project
4 questions answered from the record
Who is building SpaceXAI Memphis data centers?
-
SpaceXAI is the developer. No construction contractor is named on the record yet.
How much power and water does SpaceXAI Memphis data centers say it needs?
-
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
Where does SpaceXAI Memphis data centers stand today?
-
It is reported, as reported August 20, 2026. The newest entry, reported September 18, 2026: SpaceXAI agreed to timeline for removal of turbines with Mississippi Department of Environmental Quality, all turbines to be removed by July 2027. [6]
What has Memphis or Shelby County decided about it?
-
Memphis (rated restrictive): Memphis imposed data center moratorium while SpaceXAI continues expansion in Mississippi less than a mile away (reported September 21, 2026, source); and Memphis: Three Memphis City Council members J.B. Smiley Jr., Yolanda Cooper Sutton, and Jana Swearengen Washington proposing 12 month moratorium on data center development (reported September 8, 2026, source). 5 events are on the county's rows; a rule about the area is not a decision about this record.
Sources
Reporting
- Musk confirms fourth SpaceXAI data center in Memphis, company starts removing 'illegal' gas turbines - Data Center Dynamics, Data Center Dynamics, July 31, 2026, trade press
- NAACP, Stand Up Nashville hold data center town hall with experts from across the country - WSMV, WSMV, September 11, 2026, local outlet
- Elon Musk's Memphis AI empire is the epicenter of the data center backlash - CNBC, CNBC, July 16, 2026, local outlet
- Memphis AI data center fuels pollution fight in Black neighborhood - France 24, France 24, August 11, 2026, local outlet
- Memphis weighs data center moratorium in city Musk’s xAI calls ‘home’ - eenews.net, eenews.net, August 20, 2026, local outlet
- Elon Musk’s data center sued for $30 million by family of worker killed at site - The Independent, The Independent, September 18, 2026, local outlet
- TVA vote impacts data centers as Memphis residents raise environmental concerns - localmemphis.com, localmemphis.com, August 20, 2026, local outlet
- Congressional Candidate Molder Supports Memphis Data Center Moratorium - Radio NWTN, Radio NWTN, August 18, 2026, local outlet
- Residents file lawsuit challenging noise pollution from Elon Musk's data center, Connecticut Public, September 17, 2026, local outlet
- SpaceXAI adds another data center in Memphis; Whitehaven residents react - WREG.com, WREG.com, July 31, 2026, local outlet
10 sources on file.
Cite this record
Data Center Record, "SpaceXAI Memphis data centers", https://datacenterrecord.org/projects/spacexai-memphis-data-centers-tn, last verified September 25, 2026.
Cite this page
Data Center Record, "SpaceXAI Memphis data centers", https://datacenterrecord.org/projects/spacexai-memphis-data-centers-tn. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Slug
- spacexai-memphis-data-centers-tn
- Status value
- rumored
- Stage
- Proposed
- Tier
- skeleton
- Tags
- court, skeleton
- Place id
- us/tn/shelby-county/memphis
- Coordinates
- 35.14611, -90.05194
- Location precision
- county
- Location source
- County seat (Memphis), Wikidata, placed at county level
- Coordinate source
- wikidata county seat
- Location source number
- Not disclosed
- Location last verified
- September 16, 2026
- EPA registry id
- Not disclosed
- Use type values
- not_disclosed
- Tenancy value
- not_disclosed
- Cooling type value
- not_disclosed
- Capacity basis
- not_disclosed
- Water basis
- not_disclosed, gallons_per_day
- Acreage basis
- Not disclosed
- Interconnection value
- not_disclosed
- Capacity, if disclosed
- Not disclosed
- Rating of the county's rows
- Restrictive
- Published
- 2026-09-05
- Last verified
- 2026-09-25