Census GEOID: 28089 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 primary and 11 reporting sources

● Being Built Reported June 11, 2026 · 4 Buildings

Amazon Canton Data Centers

Street address 1001 Highway 22 West, Madison County Mega Site, Canton, MS 39046 verified address Exact, at the address [1] County seat (Canton), Wikidata, placed at county level

Overview, regulatory gates and specifications

Amazon operates multiple data centers in Canton, Madison County, and is involved in a tax valuation dispute with the county while also planning a $25 billion expansion in Mississippi creating 2,000 jobs. [2] Filings on the record specify 4 planned or operational buildings. [8] Amazon Web Services is constructing its hyperscale data center campuses in Canton, Madison County, Mississippi. [2]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Incentive review
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
EPA air permit on file
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [8]
4 buildings
Disclosed building count

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 1001 Highway 22 West, Madison County Mega Site, Canton, MS 39046.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
4 buildings operator page
[8] aboutamazon.com
Backup generators
Not disclosed
Capital investment
$69 million developer figure
[2] clarionledger.com
Who leads it
Amazon as stated by the source
[8] aboutamazon.com
Archived promotional websites
aboutamazon.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Entergy

Public Record Speaker

DID Recorded statement at PR Newswire (August 27, 2026) [4]
SAID Data centers pay 100% of their own grid connection and usage costs plus create additional benefits like tax revenues, jobs, and bill assistance contributions (August 27, 2026) [4]

Drew Marsh

chair and CEO, Entergy

DID Recorded statement at PR Newswire (August 27, 2026) [4]
SAID Drew Marsh, Entergy chair and CEO, said large customers like data centers help pick up grid maintenance costs existing customers would otherwise bear alone (August 27, 2026) [4]

Amazon

Public Record Speaker

DID Recorded statement at www.facebook.com (April 17, 2026)
SAID Amazon press release about Ridgeland and Canton projects states commitment to building data centers responsibly in Mississippi (April 17, 2026) facebook.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Amazon
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Amazon Canton Data Centers.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 4 buildings Site filing [8] aboutamazon.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: being built (content date)

    Amazon Web Services is constructing its hyperscale data center campuses in Canton, Madison County, Mississippi.

    [2] clarionledger.com

  2. (source date; the content gives no date of its own)

    Amazon established a workforce partnership for its Mississippi data centers

    [11] mississippitoday.org

Every event in order

15 corrections to this record

Every correction, with its reason
  1. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  9. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  10. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  11. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  12. · Source tier

    Tier after resolution (September 21, 2026). The source on file is clarionledger.com, the publisher's own page. The item reached the record through Google News: "data center" Mississippi, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.

  13. · Source tier

    Tier after resolution (September 21, 2026). The source on file is clarionledger.com, the publisher's own page. The item reached the record through Google News: "data center" Mississippi, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.

Every correction on the record is on the corrections page.

Nearest data centers in Mississippi

Verified data center records in Mississippi within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Ridgeland Data Center Ridgeland, Madison County ~3 mi Proposed
Jackson Lake Hico Data Center Jackson, Hinds County ~22 mi Proposed
Amazon Clinton Data Center Clinton, Hinds County 24 mi Running Amazon 2 buildings

Blank cell: not disclosed by any source on file.

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Tax each year

3 figures, 2 sources
230,000,000 USD Reported

The Clarion-Ledger, Sep 3, 2026

Show each source's words
  • 292,000,000 USD, DeSoto County News: Amazon Web Services challenged the Madison County tax assessor's valuation, claiming the county valued each data center at $292 million but the company said each is only worth $69 million
  • 292,000,000 USD, The Clarion-Ledger: Madison County Tax Assessor valued Amazon's five data center buildings at approximately $292 million each, totaling $1.46 billion
  • 230,000,000 USD, The Clarion-Ledger: County expected to receive approximately $230 million from Amazon in tax revenue over six years under fee in lieu agreement
  • 35,000,000 USD, DeSoto County News: By 2038, Canton schools could receive upwards of $35 million annually once the fee agreement ends and Amazon pays full property taxes

Common questions about Amazon Canton Data Centers

Answered directly from the verified filings and local actions on this page.

Who is building Amazon Canton Data Centers?

Amazon is the developer, aboutamazon.com (opens in a new tab). No construction contractor is named on the record yet.

Who will use Amazon Canton Data Centers?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Amazon Canton Data Centers say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Amazon Canton Data Centers stand today?
What is still unknown about Amazon Canton Data Centers?

Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. US EPA ECHO and Mississippi Department of Environmental Quality Permit & Parcel Record (1001 Highway 22 West, Madison County Mega Site, Canton, MS 39046) (opens in a new tab), U.S. Environmental Protection Agency and Mississippi Department of Environmental Quality, November 6, 2026

Reporting

  1. Amazon fights Madison County to lower data center fees - The Clarion-Ledger (opens in a new tab), The Clarion-Ledger, September 3, 2026, local outlet
  2. Madison County, Amazon spar over data center tax values - WLBT (opens in a new tab), WLBT, August 18, 2026, local outlet
  3. Entergy customers begin seeing benefits from data center agreements, Fair Share Plus pledge keeps money in customers' pockets - PR Newswire (opens in a new tab), PR Newswire, August 27, 2026, press release
  4. Madison County Denies Amazon’s Valuation Appeal for Canton Data Centers, Preserving Millions in Tax Revenue - Mississippi Free Press (opens in a new tab), Mississippi Free Press, August 19, 2026, local outlet
  5. Where do Amazon’s data centers in Mississippi stand? - Mississippi Today (opens in a new tab), Mississippi Today, June 9, 2026, local outlet
  6. Entergy says Amazon's $25 billion MS expansion is helping your power bill - The Clarion-Ledger (opens in a new tab), The Clarion-Ledger, August 27, 2026, local outlet
  7. Amazon plans to invest $25 billion in Mississippi data centers, create 2,000 jobs - About Amazon (opens in a new tab), About Amazon, April 9, 2026, news outlet
  8. ‘When Amazon comes to town.’ Clinton and company host ribbon cutting for new data center - Mississippi Today (opens in a new tab), Mississippi Today, June 9, 2026, local outlet
  9. ‘Exciting day in Mississippi’: Ribbon-cutting marks opening of Clinton data center - WLBT (opens in a new tab), WLBT, June 9, 2026, local outlet
  10. A new workforce partnership, Amazon’s data centers: Mississippi Marketplace - Mississippi Today (opens in a new tab), Mississippi Today, June 11, 2026, local outlet
  11. Amazon fights Madison County to lower data center fees - The Clarion Ledger (opens in a new tab), The Clarion-Ledger, September 3, 2026, local outlet

12 sources on file.

Regional grid context

This site is in the SERC Mississippi Valley (SRMV) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Amazon Canton Data Centers", https://datacenterrecord.org/projects/amazon-canton-data-centers-ms, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Amazon Canton Data Centers", https://datacenterrecord.org/projects/amazon-canton-data-centers-ms. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
32.6085, -90.0895
How the location is known
Location from the site's street address.
Location source
County seat (Canton), Wikidata, placed at county level
Coordinate source
US EPA ECHO FRS and municipal parcel records
Location last verified
November 6, 2026
Published
September 5, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows