● Proposed Campus Reported April 22, 2026

Ridgeland Data Center

Location Ridgeland, Madison County, Mississippi county centroid County level, the county seat

Overview, regulatory gates and specifications

A data center proposed in Ridgeland faces opposition from Mississippi energy companies. [1] Ridgeland data center project faces opposition from Mississippi energy companies [1]

Verified Site & Permit Summary
Verified address
Ridgeland, Madison County, Mississippi county centroid
Operator / developer
Not disclosed in filing
Permit / registry ID
Mississippi Today on file [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Not disclosed
Who leads it, Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Not disclosed
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Ridgeland Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Who is behind it A land record, a zoning application or a company's own announcement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. · Status: rumored (source date; the content gives no date of its own)

    Ridgeland data center project faces opposition from Mississippi energy companies

    [1] mississippitoday.org

Every event in order

1 correction to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Mississippi

Verified data center records in Mississippi within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Amazon Canton Data Centers Canton, Madison County ~3 mi Being built Amazon 4 buildings
Jackson Lake Hico Data Center Jackson, Hinds County ~23 mi Proposed
Amazon Clinton Data Center Clinton, Hinds County ~27 mi Running Amazon 2 buildings

Blank cell: not disclosed by any source on file.

Common questions about Ridgeland Data Center

Answered directly from the verified filings and local actions on this page.

Who is building Ridgeland Data Center?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does Ridgeland Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Ridgeland Data Center stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Ridgeland data center faces Mississippi energy giants’ opposition - Mississippi Today (opens in a new tab), Mississippi Today, April 22, 2026, local outlet
  2. Ridgeland data center faces Mississippi energy giants’ opposition - Mississippi Today (opens in a new tab), Mississippi Today, April 22, 2026, local outlet

2 sources on file.

Regional grid context

This site is in the SERC Mississippi Valley (SRMV) regional power market.

Sources and data

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Ridgeland Data Center", https://datacenterrecord.org/projects/ridgeland-data-center-ms, last verified September 17, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Ridgeland Data Center", https://datacenterrecord.org/projects/ridgeland-data-center-ms. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
32.6119, -90.0317
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (Canton), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Published
September 5, 2026
Last verified
September 17, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Ridgeland Data Center · 2 sources, 1 entry · basis and source tier on every row · verified September 17, 2026

Download CSV JSON