● Proposed Campus Reported May 14, 2026

DeepGreen Western Passage Underwater AI Data Center

Location Eastport, Washington County, Maine county centroid County level, the county seat

Overview, regulatory gates and specifications

DeepGreen proposed an underwater AI data center off the coast of Eastport, scaled down to 15 MW and a 27.1 acre active infrastructure footprint with 16 turbines in Phase I, and filed a 48 month preliminary permit application with FERC in February 2026, though Eastport enacted a 180 day moratorium on the project in August 2026. [1] DeepGreen Western Passage SPV LLC applied to FERC in February for 48 month preliminary permit [2]

1. Land & Parcel
Location tracked
2. Local Zoning
Not yet on file
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
15 MW disclosed
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings
Not disclosed
Acreage not stated in public filings yet

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Parcel boundaries and municipal zoning tracked.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
Not disclosed
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
DeepGreen as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Jack Shapiro

NRCM Climate & Clean Energy Director

DID Recorded statement at Natural Resources Council of Maine (September 28, 2026)
SAID Jack Shapiro, NRCM Climate & Clean Energy Director, said 'No big development project deserves a free pass, especially here in Maine where we value our clean water, healthy forests, abundant wildlife, and way of life rooted in the outdoors.' (September 28, 2026) nrcm.org (opens in a new tab)

Louis Wolfson

managing member of DeepGreen Holdings LLC

DID Recorded statement at newscentermaine.com (September 7, 2026) [2]
SAID Developer Louis Wolfson said preliminary permit is a license to study, not a license to construct (September 7, 2026) [2]

Eastport City Council

Public Record Speaker

DID Recorded statement at newscentermaine.com (September 7, 2026) [2]
SAID City Council expressed unanimous opposition to underwater AI data center construction in Eastport waters (September 7, 2026) [2]

Dwayne Tomah

Passamaquoddy community historian

DID Recorded statement at Bangor Daily News (August 11, 2026) [7]
SAID Dwayne Tomah, historian from Sipayik Passamaquoddy community, stated the project represents a national backlash against data center facilities (August 11, 2026) [7]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: DeepGreen
UTILITIES
Electric utility: Not disclosed

View all 6 statements on the record in Maine →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for DeepGreen Western Passage Underwater AI Data Center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 15 MW Disclosed filing [1] themainemonitor.org
Site Footprint (Acres)
Data Hall Buildings
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 5, 2026 Eastport, ME Eastport, ME, City Council Meeting Underwater AI Data Center August 5, 2026. Eastport City Council 3 clips

Official recording of Eastport City Council in Eastport, ME: Eastport, ME, City Council Meeting Underwater AI Data Center August 5, 2026.

  1. Eastport City Council Officials and Speakers Elected Official transcribed from the official recording
    "ordinance prohibiting largecale data centers. The second being the ordinance requiring voter approval for commercial and industrial development. We will do these one at a time in that order. Before I get too far away from everything, I got to clarify some things. The signup sheet for attending the meeting is in the lobby. Please make sure you sign that if you have not. The"
  2. Resident public comment Resident Public Comment transcribed from the official recording
    "ordinance that we're referencing, the ordinance prohibiting largecale data centers. What this petition does and why it matters. This petition is narrowly focused and very clear. It prohibits largecale data centers including underwater data centers in Eastport. The ordinance defines a data center as any"
  3. Eastport City Council Member Elected Official transcribed from the official recording
    "community working together as a whole. I don't know whether I'm I'm being heard enough. Some people are saying I got to be a little louder. I'm okay. Okay, I'll start over. I believe this community working together as a whole can go forward to grow economically without sacrificing our wealth of"
June 5, 2026 Eastport, ME Eastport residents raise concerns over underwater AI data center Eastport City Council 3 clips

NEWS CENTER Maine report on Eastport City Council and community proceedings in Eastport, ME: Eastport residents raise concerns over underwater AI data center (June 5, 2026).

  1. NEWS CENTER Maine Broadcast Report Broadcast Report transcribed from local broadcast report
    "Underneath its waters, the project would place computing infrastructure in Passamaquaddi Bay powered by tidal energy and cooled by the surrounding seawater. This is not something we need or want. And I don't know what we'll get from it, but for some Eastport residents like Sue Ellen Hendricks, the proposal is sending a wave of concerns about the potential impacts on marine life that she says is essential to this coastal town's identity. The temperature of the pods themselves will heat up the water, and that will kill the lobsters"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "In response, some residents are urging the Eastport City Council to formally oppose the project and to consider a temporary moratorium until more environmental review is completed. If we could put a moratorium on it, they might start losing investors. You know, the longer it takes, the less people are inclined to , back , it. It cannot happen in a vulnerable place like this, a vulnerable ecosystem. And a vulnerable economy."
  3. NEWS CENTER Maine Broadcast Report Broadcast Report transcribed from local broadcast report
    "can reduce energy demands compared to traditional data centers, riding in part. The long term goal is to generate excess electricity that can be fed back to benefit the local community, all while operating a green system designed to leave zero permanent footprint at the end of its life cycle while at the same time providing high paying jobs and economic benefits to the surrounding communities. While the city council rejected the moratorium, town manager Brian Schth says it's because the project is in an early study phase,"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. Filing (source date; the content gives no date of its own)

    FERC accepted DeepGreen permit application for filing in August

    [2] yahoo.com

  2. (source date; the content gives no date of its own)

    DeepGreen Western Passage SPV LLC applied to FERC in February for 48 month preliminary permit

    [2] yahoo.com

  3. (source date; the content gives no date of its own)

    Louis Wolfson applied in February to FERC for a 48 month preliminary permit

    [1] themainemonitor.org

  4. Filing (source date; the content gives no date of its own)

    FERC accepted DeepGreen Western Passage SPV LLC's preliminary permit application in August

    [1] themainemonitor.org

  5. (source date; the content gives no date of its own)

    DeepGreen Western Passage applied to FERC in February 2026 for a permit to explore putting a data center underwater in Johnson Cove, Passamaquoddy Bay

    [7] bangordailynews.com

  6. (source date; the content gives no date of its own)

    DeepGreen Western Passage SPV LLC applied for a 48 month preliminary permit with the Federal Energy Regulatory Commission for a tidal powered underwater AI data center

    [8] themainemonitor.org

  7. · Status: proposed (content date)

    DeepGreen proposed a subsea tidal cooled AI data center deployment in Western Passage off Eastport, Washington County, Maine.

    [3] themainemonitor.org

  8. (source date; the content gives no date of its own)

    Needham developer proposes underwater AI data centers off Maine coast

    [4] needhamobserver.com

Every event in order

34 corrections to this record

Every correction, with its reason
  1. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  9. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  10. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  11. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  12. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  13. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  14. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  15. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

See all 19 corrections for this record (4 more) →

Every correction on the record is on the corrections page.

Nearest data centers in Maine

Verified data center records in Maine within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Eastport Underwater Data Center Eastport, Washington County Less than 1 mi Proposed

Blank cell: not disclosed by any source on file.

Common questions about DeepGreen Western Passage Underwater AI Data Center

Answered directly from the verified filings and local actions on this page.

Who is building DeepGreen Western Passage Underwater AI Data Center?

DeepGreen is the developer. No construction contractor is named on the record yet.

How much power and water does DeepGreen Western Passage Underwater AI Data Center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does DeepGreen Western Passage Underwater AI Data Center stand today?

It is proposed, since July 15, 2026. The newest entry, reported September 7, 2026: FERC accepted DeepGreen permit application for filing in August [2].

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Residents seek formal role in federal review as Eastport considers ban on underwater data center - The Maine Monitor (opens in a new tab), The Maine Monitor, September 4, 2026, local outlet
  2. Residents seek formal role in federal review as Eastport considers ban on underwater data center - newscentermaine.com (opens in a new tab), newscentermaine.com, September 7, 2026, national outlet
  3. Eastport Council unanimously adopts moratorium on DeepGreen underwater data center proposal - The Maine Monitor (opens in a new tab), The Maine Monitor, August 13, 2026, local outlet
  4. Needham developer proposes underwater AI data centers off Maine coast - Needham Observer (opens in a new tab), Needham Observer, May 14, 2026, news outlet
  5. planet maine vol. 36: Eastport’s data center resistance - mainepublic.org (opens in a new tab), mainepublic.org, August 26, 2026, local outlet
  6. Proposed data center inches closer to reality - newscentermaine.com (opens in a new tab), newscentermaine.com, September 1, 2026, local outlet
  7. Eastport united in opposition to underwater data center proposal - Bangor Daily News (opens in a new tab), Bangor Daily News, August 11, 2026, local outlet
  8. Ordinance requiring voter approval for data centers called 'unlawful’ - The Maine Monitor (opens in a new tab), The Maine Monitor, August 10, 2026, local outlet
  9. Federal regulators accept preliminary permit for underwater data center off Eastport - Bangor Daily News (opens in a new tab), Bangor Daily News, August 24, 2026, local outlet
  10. Eastport residents seek formal role in federal review of proposed underwater data center (opens in a new tab), Bangor Daily News, September 8, 2026, local outlet
  11. Proposed underwater AI data center advances in federal review, raising concerns in Eastport - newscentermaine.com (opens in a new tab), newscentermaine.com, August 31, 2026, local outlet
  12. Eastport AI data center proposal advances amid local concerns - newscentermaine.com (opens in a new tab), newscentermaine.com, September 1, 2026, local outlet
11 more sources
  1. Eastport underwater AI data center moves forward in federal review - newscentermaine.com (opens in a new tab), newscentermaine.com, September 1, 2026, local outlet
  2. Advisory group asking for public input on future of data centers in Maine - Maine Morning Star (opens in a new tab), Maine Morning Star, August 25, 2026, local outlet
  3. Eastport divided over proposed underwater data center - newscentermaine.com (opens in a new tab), newscentermaine.com, September 1, 2026, local outlet
  4. Eastport community is divided over proposed underwater data center - newscentermaine.com (opens in a new tab), newscentermaine.com, September 1, 2026, local outlet
  5. Proposed Eastport underwater AI data center off coast one step closer - newscentermaine.com (opens in a new tab), newscentermaine.com, August 31, 2026, local outlet
  6. Ordinance that would prohibit DeepGreen data-center project in Eastport scheduled for hearing in August - The Maine Monitor (opens in a new tab), The Maine Monitor, July 17, 2026, local outlet
  7. Coalition of Eastport residents submits petition to prohibit large data center project - The Maine Monitor (opens in a new tab), The Maine Monitor, June 26, 2026, local outlet
  8. Proposed Eastport underwater AI data center advances - WABI (opens in a new tab), WABI, August 21, 2026, local outlet
  9. The One Town That Wants a Data Center - The Atlantic (opens in a new tab), The Atlantic, August 3, 2026, national outlet
  10. Proposed Eastport underwater AI data center advances - WABI (opens in a new tab), WABI, August 21, 2026, local outlet
  11. A week after Eastport banned data centers for 180 days, federal regulators accepted the underwater AI project’s application - NationofChange (opens in a new tab), NationofChange, August 25, 2026, national outlet

23 sources on file.

Regional grid context

This site is in the NPCC New England (NEWE) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "DeepGreen Western Passage Underwater AI Data Center", https://datacenterrecord.org/projects/deepgreen-western-passage-underwater-ai-data-center-eastport-me, last verified September 17, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "DeepGreen Western Passage Underwater AI Data Center", https://datacenterrecord.org/projects/deepgreen-western-passage-underwater-ai-data-center-eastport-me. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
44.68333, -67.46667
How the location is known
Location is the county seat; exact site not disclosed.
Location source
County seat (Machias), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location last verified
September 16, 2026
Capacity, if disclosed
15 MW, not disclosed
Published
September 5, 2026
Last verified
September 17, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · DeepGreen Western Passage Underwater AI Data Center · 23 sources, 8 entries · basis and source tier on every row · verified September 17, 2026