DeepGreen proposed an underwater AI data center off the coast of Eastport, scaled down to 15 MW and a 27.1 acre active infrastructure footprint with 16 turbines in Phase I, and filed a 48 month preliminary permit application with FERC in February 2026, though Eastport enacted a 180 day moratorium on the project in August 2026. [1] DeepGreen Western Passage SPV LLC applied to FERC in February for 48 month preliminary permit [2]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Utility interconnection queue filings monitored.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Parcel boundaries and municipal zoning tracked.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Connected government officials, corporate entities, utilities and local rules on the public record.
Jack Shapiro, NRCM Climate & Clean Energy Director, said 'No big development project deserves a free pass, especially here in Maine where we value our clean water, healthy forests, abundant wildlife, and way of life rooted in the outdoors.'(September 28, 2026) nrcm.org (opens in a new tab)
Developer Louis Wolfson said preliminary permit is a license to study, not a license to construct(September 7, 2026) [2]
City Council expressed unanimous opposition to underwater AI data center construction in Eastport waters(September 7, 2026) [2]
Dwayne Tomah, historian from Sipayik Passamaquoddy community, stated the project represents a national backlash against data center facilities(August 11, 2026) [7]
View all 6 statements on the record in Maine →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for DeepGreen Western Passage Underwater AI Data Center.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 15 MW | Disclosed filing [1] themainemonitor.org | |
| Site Footprint (Acres) | |||
| Data Hall Buildings | |||
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Official recording of Eastport City Council in Eastport, ME: Eastport, ME, City Council Meeting Underwater AI Data Center August 5, 2026.
"ordinance prohibiting largecale data centers. The second being the ordinance requiring voter approval for commercial and industrial development. We will do these one at a time in that order. Before I get too far away from everything, I got to clarify some things. The signup sheet for attending the meeting is in the lobby. Please make sure you sign that if you have not. The"
"ordinance that we're referencing, the ordinance prohibiting largecale data centers. What this petition does and why it matters. This petition is narrowly focused and very clear. It prohibits largecale data centers including underwater data centers in Eastport. The ordinance defines a data center as any"
"community working together as a whole. I don't know whether I'm I'm being heard enough. Some people are saying I got to be a little louder. I'm okay. Okay, I'll start over. I believe this community working together as a whole can go forward to grow economically without sacrificing our wealth of"
Using this data in a report? Support the record.
NEWS CENTER Maine report on Eastport City Council and community proceedings in Eastport, ME: Eastport residents raise concerns over underwater AI data center (June 5, 2026).
"Underneath its waters, the project would place computing infrastructure in Passamaquaddi Bay powered by tidal energy and cooled by the surrounding seawater. This is not something we need or want. And I don't know what we'll get from it, but for some Eastport residents like Sue Ellen Hendricks, the proposal is sending a wave of concerns about the potential impacts on marine life that she says is essential to this coastal town's identity. The temperature of the pods themselves will heat up the water, and that will kill the lobsters"
"In response, some residents are urging the Eastport City Council to formally oppose the project and to consider a temporary moratorium until more environmental review is completed. If we could put a moratorium on it, they might start losing investors. You know, the longer it takes, the less people are inclined to , back , it. It cannot happen in a vulnerable place like this, a vulnerable ecosystem. And a vulnerable economy."
"can reduce energy demands compared to traditional data centers, riding in part. The long term goal is to generate excess electricity that can be fed back to benefit the local community, all while operating a green system designed to leave zero permanent footprint at the end of its life cycle while at the same time providing high paying jobs and economic benefits to the surrounding communities. While the city council rejected the moratorium, town manager Brian Schth says it's because the project is in an early study phase,"
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
Filing (source date; the content gives no date of its own)
FERC accepted DeepGreen permit application for filing in August
(source date; the content gives no date of its own)
DeepGreen Western Passage SPV LLC applied to FERC in February for 48 month preliminary permit
(source date; the content gives no date of its own)
Louis Wolfson applied in February to FERC for a 48 month preliminary permit
Filing (source date; the content gives no date of its own)
FERC accepted DeepGreen Western Passage SPV LLC's preliminary permit application in August
(source date; the content gives no date of its own)
DeepGreen Western Passage applied to FERC in February 2026 for a permit to explore putting a data center underwater in Johnson Cove, Passamaquoddy Bay
(source date; the content gives no date of its own)
DeepGreen Western Passage SPV LLC applied for a 48 month preliminary permit with the Federal Energy Regulatory Commission for a tidal powered underwater AI data center
· Status: proposed (content date)
DeepGreen proposed a subsea tidal cooled AI data center deployment in Western Passage off Eastport, Washington County, Maine.
(source date; the content gives no date of its own)
Needham developer proposes underwater AI data centers off Maine coast
the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
Verified data center records in Maine within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Eastport Underwater Data Center Eastport, Washington County | Less than 1 mi | Proposed |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
DeepGreen is the developer. No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is proposed, since July 15, 2026. The newest entry, reported September 7, 2026: FERC accepted DeepGreen permit application for filing in August [2].
23 sources on file.
This site is in the NPCC New England (NEWE) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. DeepGreen Western Passage Underwater AI Data Center. Last verified September 17, 2026. https://datacenterrecord.org/projects/deepgreen-western-passage-underwater-ai-data-center-eastport-me. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about DeepGreen Western Passage Underwater AI Data Center
Data Center Record, "DeepGreen Western Passage Underwater AI Data Center", https://datacenterrecord.org/projects/deepgreen-western-passage-underwater-ai-data-center-eastport-me. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.