Sources on this page
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Last verified: · 4 primary and 26 reporting sources
DataOne USA LLC, DataOne Vineland LLC and Nebius Inc. are building a 300 MW AI data center campus at 3963 South Lincoln Avenue (Block 7503, Lots 1.01 and 35.01, about 106.59 acres; 3.1 million square feet planned, 2,647,628 square feet on the approved site plan) in Vineland, Cumberland County, New Jersey. City of Vineland stop construction order was issued August 10, 2026 (notice, page 26). The first 16 of 62 engines were operating by October 13, 2025 and the Phase III engines by June 23, 2026. The Planning Board voted August 17, 2026 on the amended phase two site plan, changing the power supply on a phase already under construction, and issued its Notice of Determination September 12, 2026 (PBA-24-00022). New Jersey DEP issued an Administrative Order (EA ID PEA260001-75894) with a $1.07 million penalty on September 22, 2026 and Sustain SJ, represented by Earthjustice, sent a Clean Air Act notice of intent to sue on October 21, 2026. [5] DataOne said the engines are temporary [29]
Equivalent to ~249,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 14% of Hoover Dam nameplate capacity (2,080 MW).
Electric utility: 62 natural gas engines, 1,231 fuel cells and 25 boilers; Potential to emit from the 62 engines: more than 250 tons a year of regulated pollutants, over 100 tons CO, 25 tons NOx, 25 tons VOC, 10 tons formaldehyde (Earthjustice calculation, not a measurement).
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
2 planned or operational data hall buildings.
Location: 3963 South Lincoln Avenue, Vineland, NJ 08361; Block 7503, Lots 1.01 and 35.01, about 106.59 acres; Northeast Precast site at 4081 South Lincoln Avenue adjacent.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Sources:
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
DataOne said the engines are temporary(October 24, 2026) [29]
We were able to get planning board approvals for our fuel cells within 3 months of signing the contract. Two months after these approvals, we have the first block of power ready for customer use(October 23, 2026) blockspace.media (opens in a new tab)
Matt Williams, Sustain SJ board chair, said the process has lacked transparency since construction began and community members were sidelined(October 21, 2026) [27]
Regulatory compliance is not optional, and DataOne must be accountable to the surrounding community and to the Clean Air Act for its violations.(October 21, 2026) [27]
View all 14 statements on the record in New Jersey →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Nebius and DataOne Vineland AI Data Center Campus.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 300 MW | the developer's figure [4] nebius.com | |
| Site Footprint (Acres) | 106.59 acres | 106.59 acres | what a permit allows [1] earthjustice.org |
| Data Hall Buildings | 2 buildings | 3.1 million square feet planned (notice, page 2); the approved site plan is 2,647,628 square feet (page 3); City of Vineland stop construction order issued August 10, 2026 (notice, page 26), 62 engines operating since October 13, 2025, phase two approved September 12, 2026 [1] earthjustice.org | |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
DataOne said the engines are temporary
(content date)
Sustain SJ, represented by Earthjustice, sent DataOne USA LLC, DataOne Vineland LLC, Nebius Inc. and Northeast Precast LLC a notice of intent to sue under Section 304 of the Clean Air Act over 62 unpermitted gas engines, 1,231 fuel cells and 25 boilers at 3963 and 4081 South Lincoln Avenue; suit may follow after a 60 day notice period in the District of New Jersey
[1] earthjustice.org, also [27] earthjustice.org, also [28] whyy.org, also [29] snjtoday.com
(content date)
Sustain SJ filed suit in New Jersey Superior Court challenging Vineland's approval of the DataOne site plan on stormwater and planning board authority grounds
(content date)
DataOne requested an administrative hearing and a stay of the DEP determination that it must obtain permits and certificates for the engines by November 6, 2026, calling the penalty disproportionate
(source date; the content gives no date of its own)
DataOne received two stop work orders from City of Vineland on August 6 and August 10 for construction permit violations
(source date; the content gives no date of its own)
NJDEP inspection on July 29 found gas generators that were not present during December 2025 inspection
(source date; the content gives no date of its own)
DataOne Vineland data center approved capacity 300 megawatts, currently projects 350 megawatts on website
(source date; the content gives no date of its own)
DataOne expanded its Cumberland County Vineland facility last winter 2026, making it the state's largest operating data center.
Filing (content date)
New Jersey DEP issued an Administrative Order and Notice of Civil Administrative Penalty Assessment (EA ID PEA260001-75894) against DataOne for operating 62 natural gas engines without a preconstruction permit or operating certificate, with a $1.07 million penalty and 45 days to apply for minor source permits
(source date; the content gives no date of its own)
Generators are temporary with transition to fuel cells for permanent power supply
(source date; the content gives no date of its own)
DEP found 62 stationary generators with 1,982 kilowatt capacity each during July 29 inspection without required permits
(source date; the content gives no date of its own)
Construction expected complete in late December according to company website
(source date; the content gives no date of its own)
DEP inspection July 29 discovered 62 1,982 kilowatt generators not present in December inspection
(source date; the content gives no date of its own)
Construction expected to be done in late December 2026
(source date; the content gives no date of its own)
DEP inspectors found 62 1,982 kilowatt generators during July 29 visit that were not present in December 2025 inspection
(source date; the content gives no date of its own)
New Jersey DEP found DataOne facility operated 62 large natural gas generators without required air permits
(source date; the content gives no date of its own)
New Jersey DEP found 62 natural gas generators with 1,982 kilowatt capacity each operating without required permits during July 29 inspection
(source date; the content gives no date of its own)
DataOne is transitioning to low emission fuel cells as the permanent power source
(source date; the content gives no date of its own)
DataOne installed and operated 62 large natural gas power generators without required state permits
(source date; the content gives no date of its own)
First phase of the site is expected to open later this year
(source date; the content gives no date of its own)
Construction on the $17 billion South Jersey project backed by Microsoft began in early 2025
(source date; the content gives no date of its own)
Generators were not present at previous inspection in December 2025 but were installed by July 29, 2026 site inspection
(source date; the content gives no date of its own)
Natural gas power generating equipment was observed during an inspection on July 29 but was not observed during the DEP's previous site inspection in December 2025.
(source date; the content gives no date of its own)
Facility sits in a protected wellhead area with groundwater contamination risk
(source date; the content gives no date of its own)
Cooling requires more than 400 fans
(content date)
Vineland Planning Board issued its Notice of Determination approving DataOne's amended preliminary and final major site plan for phase two (application PBA-24-00022); the vote was August 17, 2026
(source date; the content gives no date of its own)
DataOne Campus sits roughly one mile from two schools
(source date; the content gives no date of its own)
DataOne Campus sits approximately 40 miles from Philadelphia
(source date; the content gives no date of its own)
DataOne Campus construction began in 2025
(source date; the content gives no date of its own)
DataOne Campus is planned as New Jersey's largest AI data center under $17 billion agreement with Microsoft
(source date; the content gives no date of its own)
DataOne Campus in Vineland accused of running 45 gas generators without permits
(source date; the content gives no date of its own)
Thermal drone footage from late June shows 25 of the unpermitted gas generators operating
(source date; the content gives no date of its own)
First unpermitted generators appear to have been turned on in October according to maintenance logs
Filing (source date; the content gives no date of its own)
DataOne withdrew gas engine permit application in May 2026
Filing (source date; the content gives no date of its own)
DataOne originally submitted permit application for more than 30 Bergen gas burning engines
(source date; the content gives no date of its own)
DataOne broke ground in 2025
· being built (source date; the content gives no date of its own)
DataOne facility is partly completed and operates at least 45 of 62 generators
· approved (source date; the content gives no date of its own)
Planning Board approved power supply changes to the phase two site plan, which was already under construction; reported August 18.
[23] nbcphiladelphia.com, also [24] nj.com, also [22] blockspace.media
(content date)
Phase III engines reported operating by this date
· being built (content date)
First 16 engines reported operating by this date
Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.
Superseded: the entry's primary source was dep.nj.gov/boss/, which does not report the August 17, 2026 Planning Board vote, and a published entry's source cannot change. The same fact is on the record again with NBC Philadelphia as its source.
The August 18 entry attributed the approval to the city council. The city council did not vote on it; the Planning Board approved power supply changes to the phase two site plan on August 17, 2026 (NBC Philadelphia, with its published correction).
The prior summary gave the Notice of Determination date as the approval date. The Planning Board voted August 17, 2026 and issued its notice September 12, 2026.
The prior summary gave one start date for all 62 engines. The Sustain SJ notice of intent to sue (page 2) says the first 16 engines were operating by October 13, 2025 and the Phase III engines by June 23, 2026.
· Site acreage (2.6 acres to 107 acres)
The site read 2.6 acres. Two approvals wrote square feet as acres over the 107 acres an Asbury Park Press article of September 22, 2026 gave (2.6 million square feet and 2,600,000 square feet are a floor area). Restored to 107 acres from that article.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Every correction on the record is on the corrections page.
No other verified data center record in New Jersey is located within 60 miles of this site. Browse all data centers in New Jersey.
Inquirer.com, Sep 22, 2026; The Times of India, Sep 24, 2026 (opens in a new tab)
NJBIZ, Sep 23, 2026; TechRadar, Sep 25, 2026 (opens in a new tab)
Answered directly from the verified filings and local actions on this page.
DataOne is the developer. No construction contractor is named on the record yet.
The named tenants are Nebius Group, Microsoft. No promise to the community is on the record.
Power: 300 MW (the developer's figure, nebius.com (opens in a new tab)). Water: not disclosed by any source on file.
It is being built, since September 12, 2026. The newest entry, reported October 24, 2026: DataOne said the engines are temporary [29].
Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
30 sources on file.
This site is in the RFC East (RFCE) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Nebius and DataOne Vineland AI Data Center Campus. Last verified October 25, 2026. https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Nebius and DataOne Vineland AI Data Center Campus
Data Center Record, "Nebius and DataOne Vineland AI Data Center Campus", https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.