Reported Built from one source

Nebius AI Data Center (Vineland)

Vineland city council approved a DataOne expansion for a Nebius AI data center, and the planning board separately approved an adjustment to Phase 2, though the city also issued a stop work order to parts of the facility and accused it of operating natural gas generators without a permit. It is reported, as reported September 12, 2026.

Last verified · 23 sources, 0 primary · A skeleton record: built from one source, not yet reviewed in depth by a person. · How to read this page

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Land
107 acres
third party estimate [9]
Power it would draw
300 MW
third party estimate [9]
Water
20,000,000 gallons a year
third party estimate [15]
Who leads it
DataOne
as stated by the source
Who would use it
Nebius Group / Microsoft
as the source names them [12]
Jobs once it runs
Not disclosed
Tax each year
Not disclosed
Where its power comes from
natural gas generators
as stated by the source [16]
Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 300 MW third party estimate [9] app.com September 25, 2026
How much water it would use 20,000,000 gallons a year third party estimate [15] njbiz.com September 25, 2026
How loud it would be Not disclosed
Jobs once it runs Not disclosed
Tax it would pay each year Not disclosed

The record's fields

FieldValueWho says soSourceLast verified
Who is building it DataOne as stated by the source September 25, 2026
Who is constructing it Not disclosed
How much land 107 acres third party estimate [9] app.com September 25, 2026
Where its power comes from natural gas generators as stated by the source [16] timesofindia.indiatimes.com September 25, 2026
Grid connection Not disclosed
How it is cooled Not disclosed

How much power it needs, also reported: 1,982 kilowatts, 2026 (Inquirer.com: Each of the 62 generators has a capacity of 1,982 kilowatts, The Times of India: Each DataOne generator had a rated capacity of 1,982 kilowatts.); 123 MW, 2026 (NJBIZ: 62 Caterpillar G3516H gas generators, each producing 1982 kilowatts, total capacity about 123 megawatts, TechRadar: 62 natural gas generators with collective 123 megawatt capacity installed without permits at DataOne Vineland facility.); 350 MW, 2026 (Gothamist: DataONE data center in Vineland designed to draw up to 350 megawatts of power); 122.9 MW, 2026 (The Times of India: The 62 DataOne generators represented approximately 122.9 megawatts of nameplate generation capacity.); 37 kilowatts, 2026 (Newsweek: Generator capacity threshold for state permits is 37 kilowatts) .

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Cumberland County and Vineland about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Vineland DataOne installed 62 gas generators without required air pollution permits nbcphiladelphia.com
Vineland A data center facility in Vineland, New Jersey was found to have more than five dozen unpermitted natural gas generators and fined more than $1 million by New Jersey Governor Mikie Sherrill. audacy.com
Vineland Residents have complained for months about water and electricity use, air quality and other issues at the DataOne site; a lawsuit was filed in June over noise. njspotlightnews.org
Vineland State environmental regulators fined DataOne in Vineland 1.07 million dollars for operating 62 unpermitted natural gas generators following a July 29 inspection. njspotlightnews.org
Vineland New Jersey Department of Environmental Protection fined DataOne more than 1 million dollars for operating 62 natural gas powered generators without a permit at the Vineland data center. whyy.org
Vineland Vineland Planning Board voted 8-1 to approve the project's second phase nj1015.com
5 earlier decisions on the county's rows
DateWhoDecisionSource
Vineland Cumberland County Department of Public Health cited DataOne for violating noise ordinances in March latitudemedia.com
Vineland Local residents filed lawsuit in New Jersey state court over noise pollution from data center latitudemedia.com
Vineland No permits issued nor any permit applications under review for power generators at DataOne latitudemedia.com
Vineland New Jersey Department of Environmental Protection noticed generators during site inspection on July 29 latitudemedia.com
Vineland At least 45 gas powered generators operating without permits as of late August 2026 latitudemedia.com

What happened

  1. (source date; the content gives no date of its own)

    New Jersey Department of Environmental Protection inspected DataOne facility in Vineland on July 29, 2026 and found 62 stationary natural gas generators operating without required preconstruction permits and operating certificates. [16]

  2. (source date; the content gives no date of its own)

    DataOne received two stop work orders from City of Vineland on August 6 and August 10 for construction permit violations [15]

  3. (source date; the content gives no date of its own)

    NJDEP inspection on July 29 found gas generators that were not present during December 2025 inspection [15]

  4. (source date; the content gives no date of its own)

    DataOne Vineland data center approved capacity 300 megawatts, currently projects 350 megawatts on website [15]

  5. (source date; the content gives no date of its own)

    DataOne expanded its Cumberland County Vineland facility last winter 2026, making it the state's largest operating data center. [5]

  6. (source date; the content gives no date of its own)

    DataOne was fined 1.07 million dollars for violations of the New Jersey Air Pollution Control Act on September 23, 2026. [5]

  7. (source date; the content gives no date of its own)

    Generators are temporary with transition to fuel cells for permanent power supply [13]

  8. (source date; the content gives no date of its own)

    DEP found 62 stationary generators with 1,982 kilowatt capacity each during July 29 inspection without required permits [13]

21 earlier entries
  1. (source date; the content gives no date of its own)

    DEP ordered DataOne to obtain permits within 45 days or cease operations [8]

  2. (source date; the content gives no date of its own)

    Construction expected complete in late December according to company website [8]

  3. (source date; the content gives no date of its own)

    DEP inspection July 29 discovered 62 1,982 kilowatt generators not present in December inspection [8]

  4. (source date; the content gives no date of its own)

    Construction expected to be done in late December 2026 [12]

  5. (source date; the content gives no date of its own)

    DEP inspectors found 62 1,982 kilowatt generators during July 29 visit that were not present in December 2025 inspection [12]

  6. (source date; the content gives no date of its own)

    New Jersey DEP found DataOne facility operated 62 large natural gas generators without required air permits [4]

  7. (source date; the content gives no date of its own)

    New Jersey DEP found 62 natural gas generators with 1,982 kilowatt capacity each operating without required permits during July 29 inspection [7]

  8. (source date; the content gives no date of its own)

    DataOne is transitioning to low emission fuel cells as the permanent power source [6]

  9. (source date; the content gives no date of its own)

    DataOne installed and operated 62 large natural gas power generators without required state permits [6]

  10. (source date; the content gives no date of its own)

    First phase of the site is expected to open later this year [11]

  11. (source date; the content gives no date of its own)

    Construction on the $17 billion South Jersey project backed by Microsoft began in early 2025 [11]

  12. (source date; the content gives no date of its own)

    Generators were not present at previous inspection in December 2025 but were installed by July 29, 2026 site inspection [11]

  13. (source date; the content gives no date of its own)

    Natural gas power generating equipment was observed during an inspection on July 29 but was not observed during the DEP's previous site inspection in December 2025. [10]

  14. (source date; the content gives no date of its own)

    Facility sits in a protected wellhead area with groundwater contamination risk [2]

  15. (source date; the content gives no date of its own)

    Cooling requires more than 400 fans [2]

  16. (source date; the content gives no date of its own)

    DataOne Vineland facility spans 2.6 million square feet [2]

  17. (source date; the content gives no date of its own)

    DataOne Campus sits roughly one mile from two schools [1]

  18. (source date; the content gives no date of its own)

    DataOne Campus sits approximately 40 miles from Philadelphia [1]

  19. (source date; the content gives no date of its own)

    DataOne Campus construction began in 2025 [1]

  20. (source date; the content gives no date of its own)

    DataOne Campus is planned as New Jersey's largest AI data center under 17 billion dollar agreement with Microsoft [1]

  21. · reported (source date; the content gives no date of its own)

    DataOne Campus in Vineland accused of running 45 gas generators without permits [1]

The full Nebius AI Data Center (Vineland) timeline, in order

13 corrections to this record

Every correction, with its reason
  1. · the site acres of a projects row

    The site read 2.6 acres. Two approvals wrote square feet as acres over the 107 acres an Asbury Park Press article of September 22, 2026 gave (2.6 million square feet and 2,600,000 square feet are a floor area). Restored to 107 acres from that article. The old and new text.

  2. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  3. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  4. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  5. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  6. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  7. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

  8. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  9. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  10. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  11. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  12. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

  13. · the draft of a status history row

    Published on a project that was still a draft skeleton and still short of the record's skeleton minimum rule; returned to draft on 2026-09-17 pending the project meeting the rule or a person's approval. The old and new text.

Every correction on the record is on the corrections page.

What was said

Ed Potosnak, NJDEP Commissioner, called this the largest action ever taken against a data center in New Jersey
Ed Potosnak, New Jersey Department of Environmental Protection Commissioner · September 23, 2026 · paraphrased · NJBIZ local outlet
Environmental advocates including Pinelands Alliance renewed calls for a statewide moratorium on data center construction
Jaclyn Rhoads, Pinelands Alliance Executive Director · September 22, 2026 · paraphrased · New Jersey 101.5 local outlet

Every statement about data centers in New Jersey, by speaker

5 more statements on this page

Governor

Gov. Mikie Sherrill called the fine the largest enforcement action against a data center in New Jersey's history.

September 22, 2026, NBC10 Philadelphia · NBC10 Philadelphia local outlet · the record (Paraphrased; content date; reported from elsewhere)

homeowner

Andrew Groetsch noticed his daughter's windows vibrating in September 2025 from data center noise

September 14, 2026, New Jersey 101.5 · New Jersey 101.5 local outlet · the record (Paraphrased; said in the source itself)

Bruce Buckheit, former EPA chief of air enforcement, said the situation appears to break federal law

September 12, 2026, communitynews.org · communitynews.org local outlet · the record (Paraphrased; said in the source itself)

Nebius executives said the fuel cell power solution would have no significant impact on the project development timeline

August 17, 2026, finance.yahoo.com · finance.yahoo.com national outlet · the record (Paraphrased; said in the source itself)

Nick Amicucci, Evercore ISI analyst, reiterated bullish view on Bloom Energy, with $350 price target

August 17, 2026, finance.yahoo.com · finance.yahoo.com national outlet · the record (Paraphrased; said in the source itself)

The site

Where in Cumberland County is not in the public record. The pin marks the county seat, not a building, and the outline is the county.

  • This record: Proposed, ringed
  • data center
  • Dashed edge: the exact site is not in the public record
  • Smaller pins: 12 other published records in New Jersey
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

Where
Vineland, Cumberland County, New Jersey
How exactly it is located
County level, the county seat
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
Nearest records are not computed for a record placed at a county seat.

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, the record's own or the document's first, each with who gave it, its date and its basis.

Capacity at full buildout

6 figures, 7 sources
300 MWThird party estimate

app.com, Sep 22, 2026

37 kilowattsReported

Newsweek, Sep 22, 2026

Show each source's words
  • 1,982 kilowatts, Inquirer.com: Each of the 62 generators has a capacity of 1,982 kilowatts
  • 1,982 kilowatts, The Times of India: Each DataOne generator had a rated capacity of 1,982 kilowatts.
  • 350 MW, Gothamist: DataONE data center in Vineland designed to draw up to 350 megawatts of power
  • 123 MW, NJBIZ: 62 Caterpillar G3516H gas generators, each producing 1982 kilowatts, total capacity about 123 megawatts
  • 123 MW, TechRadar: 62 natural gas generators with collective 123 megawatt capacity installed without permits at DataOne Vineland facility.
  • 122.9 MW, The Times of India: The 62 DataOne generators represented approximately 122.9 megawatts of nameplate generation capacity.
  • 37 kilowatts, Newsweek: Generator capacity threshold for state permits is 37 kilowatts

Questions about this project

7 questions answered from the record

Answered from the rows on this page.

How big is Nebius AI Data Center (Vineland)?

The record has 2 measures of its size: 300 MW (third party estimate, source) and 107 acres (third party estimate, source). Each figure names who gave it and links to the source.

Who is building Nebius AI Data Center (Vineland)?

DataOne is the developer. No construction contractor is named on the record yet.

Who will use Nebius AI Data Center (Vineland)?

The named tenant is Nebius Group / Microsoft. No promise to the community is on the record.

How much power and water does Nebius AI Data Center (Vineland) say it needs?

Power: 300 MW (third party estimate, source). Water: 20,000,000 gallons a year (third party estimate, source).

What has Vineland or Cumberland County decided about it?

Vineland: DataOne installed 62 gas generators without required air pollution permits (reported September 23, 2026, source); and Vineland: A data center facility in Vineland, New Jersey was found to have more than five dozen unpermitted natural gas generators and fined more than $1 million by New Jersey Governor Mikie Sherrill. (reported September 23, 2026, source). 11 events are on the county's rows; a rule about the area is not a decision about this record.

What is still unknown about Nebius AI Data Center (Vineland)?

Not disclosed by any source on file: how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Vineland AI Data Center Accused of Running Dozens of Unpermitted Gas Generators - communitynews.org, communitynews.org, September 12, 2026, local outlet
  2. "You sold us out!" Vineland residents keep fighting anyway. - New Jersey 101.5, New Jersey 101.5, September 14, 2026, local outlet
  3. Bloom Energy Shares Rise as Nebius AI Data Centre Partnership Boosts Power Demand Outlook, finance.yahoo.com, August 17, 2026, local outlet
  4. Microsoft Data Centers Hit With Fines in New Jersey, Virginia - Bloomberg Government News, Bloomberg Government News, September 22, 2026, local outlet
  5. NJ is hitting a massive data center in South Jersey with a million dollar fine. Is it enough? - nj1015.com, nj1015.com, September 23, 2026, local outlet
  6. Vineland AI data center hit with a $1 million fine - Inquirer.com, Inquirer.com, September 22, 2026, local outlet
  7. New Jersey Data Center Fined More Than $1M Over Air Pollution Violation - Newsweek, Newsweek, September 22, 2026, local outlet
  8. NJ slaps Vineland data center with $1M fine for unpermitted generators - New Jersey Monitor, New Jersey Monitor, September 22, 2026, local outlet
  9. NJ fines Vineland AI data center $1M over natural gas generators - app.com, app.com, September 22, 2026, local outlet
  10. Vineland data center fined more than $1 million for operating natural gas generators without a permit, WHYY, September 22, 2026, local outlet
  11. NJ fines data center $1 million for illegally powering facility with gas generators, Gothamist, September 22, 2026, local outlet
  12. Sherrill administration hits Vineland data center with record $1.07 million fine - New Jersey Globe, New Jersey Globe, September 22, 2026, local outlet
11 more sources
  1. NJ hits Vineland data center with $1.07M penalty over 62 natural gas generators - News12 | Long Island, News12 | Long Island, September 22, 2026, local outlet
  2. NJ regulators fine data center for gas generators that lack permits, NJ Spotlight News, September 23, 2026, local outlet
  3. NJ data center DataOne fined $1.07M for air violations - NJBIZ, NJBIZ, September 23, 2026, local outlet
  4. New Jersey inspectors found 62 large natural gas generators running without required permits at a massive - The Times of India, The Times of India, September 24, 2026, local outlet
  5. New Jersey's largest planned AI data center accused of running 45 unpermitted generators - Yahoo, Yahoo, September 12, 2026, local outlet
  6. Vineland, New Jersey city council approves DataOne expansion for Nebius AI data center - Blockspace Media, Blockspace Media, August 18, 2026, local outlet
  7. Vineland planning board votes to approve adjustment to Phase 2 of data center - NBC10 Philadelphia, NBC10 Philadelphia, August 18, 2026, local outlet
  8. ‘You sold us out!’ N.J. town approves next phase of massive AI data center as residents erupt - nj.com, nj.com, August 18, 2026, local outlet
  9. City of Vineland, N.J. issues stop-work order to parts of data center - WHYY, WHYY, August 14, 2026, local outlet
  10. Vineland data center accused of operating natural gas generators without permit - WHYY, WHYY, August 28, 2026, local outlet
  11. One of the East Coast’s largest data centers has been accused of ‘violating federal law’ - Latitude Media, Latitude Media, August 28, 2026, local outlet

23 sources on file.

Cite this record

Data Center Record, "Nebius AI Data Center (Vineland)", https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj, last verified September 25, 2026.

Last verified , first recorded . Every correction is logged on the corrections page and under What happened.

Cite this page

Data Center Record, "Nebius AI Data Center (Vineland)", https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Slug
nebius-ai-data-center-vineland-nj
Status value
rumored
Stage
Proposed
Tier
skeleton
Tags
skeleton
Place id
us/nj/cumberland-county/vineland
Coordinates
39.4275, -75.228
Location precision
county
Location source
County seat (Bridgeton), Wikidata, placed at county level
Coordinate source
wikidata county seat
Location source number
Not disclosed
Location last verified
September 16, 2026
EPA registry id
Not disclosed
Use type values
not_disclosed
Tenancy value
not_disclosed
Cooling type value
not_disclosed
Capacity basis
third_party_estimate
Water basis
third_party_estimate, gallons_per_year, not_stated
Acreage basis
third_party_estimate
Interconnection value
not_disclosed
Capacity, if disclosed
300 MW, third party estimate
Rating of the county's rows
Not disclosed
Published
2026-09-05
Last verified
2026-09-25