Nebius and DataOne Vineland AI Data Center Campus

Street address 3963 South Lincoln Avenue, Vineland, NJ 08361; Block 7503, Lots 1.01 and 35.01, about 106.59 acres; Northeast Precast site at 4081 South Lincoln Avenue adjacent, Cumberland County verified address Exact, at the address [1] Clean Air Act Notice of Intent to Sue DataOne USA LLC, DataOne Vineland LLC, Nebius Inc. and Northeast Precast LLC

Overview, regulatory gates and specifications

DataOne USA LLC, DataOne Vineland LLC and Nebius Inc. are building a 300 MW AI data center campus at 3963 South Lincoln Avenue (Block 7503, Lots 1.01 and 35.01, about 106.59 acres; 3.1 million square feet planned, 2,647,628 square feet on the approved site plan) in Vineland, Cumberland County, New Jersey. City of Vineland stop construction order was issued August 10, 2026 (notice, page 26). The first 16 of 62 engines were operating by October 13, 2025 and the Phase III engines by June 23, 2026. The Planning Board voted August 17, 2026 on the amended phase two site plan, changing the power supply on a phase already under construction, and issued its Notice of Determination September 12, 2026 (PBA-24-00022). New Jersey DEP issued an Administrative Order (EA ID PEA260001-75894) with a $1.07 million penalty on September 22, 2026 and Sustain SJ, represented by Earthjustice, sent a Clean Air Act notice of intent to sue on October 21, 2026. [5] DataOne said the engines are temporary [29]

1. Land & Parcel
106.59 acres on file
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Incentive review
4. Utility Grid Queue
300 MW disclosed
5. Air & Water Permits
Not yet on file
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand [4]
300 MW
the developer's figure

Equivalent to ~249,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 14% of Hoover Dam nameplate capacity (2,080 MW).

Electric utility: 62 natural gas engines, 1,231 fuel cells and 25 boilers; Potential to emit from the 62 engines: more than 250 tons a year of regulated pollutants, over 100 tons CO, 25 tons NOx, 25 tons VOC, 10 tons formaldehyde (Earthjustice calculation, not a measurement).

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
106.59 acres
what a permit allows

2 planned or operational data hall buildings.

Location: 3963 South Lincoln Avenue, Vineland, NJ 08361; Block 7503, Lots 1.01 and 35.01, about 106.59 acres; Northeast Precast site at 4081 South Lincoln Avenue adjacent.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
300 MW developer figure Equivalent to the continuous electricity demand of about 249,000 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 3 percent of New York City's summer peak demand in 2024.
[4] nebius.com
Water usage
Not disclosed
Land area
106.59 acres permitted
[1] earthjustice.org
Buildings
2 buildings operator page
[1] earthjustice.org
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
DataOne as stated by the source
Who would use it
Nebius Group, Microsoft as the source names them
[12] newjerseyglobe.com
Where its power comes from
62 natural gas engines, 1,231 fuel cells and 25 boilers; Potential to emit from the 62 engines: more than 250 tons a year of regulated pollutants, over 100 tons CO, 25 tons NOx, 25 tons VOC, 10 tons formaldehyde (Earthjustice calculation, not a measurement) as stated by the source
[1] earthjustice.org
Not disclosed
Jobs once it runs, Tax each year
The math behind the comparison
  1. Nebius and DataOne Vineland AI Data Center Campus, capacity: 300 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 300 ÷ 10,245 = 0.03 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

DataOne

DataOne

DID Recorded statement at SNJ Today (October 24, 2026) [29]
SAID DataOne said the engines are temporary (October 24, 2026) [29]

KR Sridhar

Founder and CEO · Bloom Energy

DID Recorded statement at Bloom Energy Q3 2026 earnings call (October 23, 2026)
SAID We were able to get planning board approvals for our fuel cells within 3 months of signing the contract. Two months after these approvals, we have the first block of power ready for customer use (October 23, 2026) blockspace.media (opens in a new tab)

Matt Williams

board chair · Sustain SJ

DID Recorded statement at Earthjustice release (October 21, 2026) [27]
SAID Matt Williams, Sustain SJ board chair, said the process has lacked transparency since construction began and community members were sidelined (October 21, 2026) [27]

Casandia Bellevue

senior associate attorney · Earthjustice

DID Recorded statement at Earthjustice release (October 21, 2026) [27]
SAID Regulatory compliance is not optional, and DataOne must be accountable to the surrounding community and to the Clean Air Act for its violations. (October 21, 2026) [27]

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: DataOne
UTILITIES
Electric utility: 62 natural gas engines, 1,231 fuel cells and 25 boilers; Potential to emit from the 62 engines: more than 250 tons a year of regulated pollutants, over 100 tons CO, 25 tons NOx, 25 tons VOC, 10 tons formaldehyde (Earthjustice calculation, not a measurement)

View all 14 statements on the record in New Jersey →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Nebius and DataOne Vineland AI Data Center Campus.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 300 MW the developer's figure [4] nebius.com
Site Footprint (Acres) 106.59 acres 106.59 acres what a permit allows [1] earthjustice.org
Data Hall Buildings 2 buildings 3.1 million square feet planned (notice, page 2); the approved site plan is 2,647,628 square feet (page 3); City of Vineland stop construction order issued August 10, 2026 (notice, page 26), 62 engines operating since October 13, 2025, phase two approved September 12, 2026 [1] earthjustice.org
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    DataOne said the engines are temporary

    [29] snjtoday.com

  2. (content date)

    Sustain SJ, represented by Earthjustice, sent DataOne USA LLC, DataOne Vineland LLC, Nebius Inc. and Northeast Precast LLC a notice of intent to sue under Section 304 of the Clean Air Act over 62 unpermitted gas engines, 1,231 fuel cells and 25 boilers at 3963 and 4081 South Lincoln Avenue; suit may follow after a 60 day notice period in the District of New Jersey

    [1] earthjustice.org, also [27] earthjustice.org, also [28] whyy.org, also [29] snjtoday.com

  3. (content date)

    Sustain SJ filed suit in New Jersey Superior Court challenging Vineland's approval of the DataOne site plan on stormwater and planning board authority grounds

    [30] sjclimate.news

  4. (content date)

    DataOne requested an administrative hearing and a stay of the DEP determination that it must obtain permits and certificates for the engines by November 6, 2026, calling the penalty disproportionate

    [1] earthjustice.org

  5. (source date; the content gives no date of its own)

    DataOne received two stop work orders from City of Vineland on August 6 and August 10 for construction permit violations

    [15] njbiz.com

  6. (source date; the content gives no date of its own)

    NJDEP inspection on July 29 found gas generators that were not present during December 2025 inspection

    [15] njbiz.com

  7. (source date; the content gives no date of its own)

    DataOne Vineland data center approved capacity 300 megawatts, currently projects 350 megawatts on website

    [15] njbiz.com

  8. (source date; the content gives no date of its own)

    DataOne expanded its Cumberland County Vineland facility last winter 2026, making it the state's largest operating data center.

    [18] nj1015.com

32 earlier entries
  1. Filing (content date)

    New Jersey DEP issued an Administrative Order and Notice of Civil Administrative Penalty Assessment (EA ID PEA260001-75894) against DataOne for operating 62 natural gas engines without a preconstruction permit or operating certificate, with a $1.07 million penalty and 45 days to apply for minor source permits

    [2] dep.nj.gov

  2. (source date; the content gives no date of its own)

    Generators are temporary with transition to fuel cells for permanent power supply

    [13] newjersey.news12.com

  3. (source date; the content gives no date of its own)

    DEP found 62 stationary generators with 1,982 kilowatt capacity each during July 29 inspection without required permits

    [13] newjersey.news12.com

  4. (source date; the content gives no date of its own)

    Construction expected complete in late December according to company website

    [8] newjerseymonitor.com

  5. (source date; the content gives no date of its own)

    DEP inspection July 29 discovered 62 1,982 kilowatt generators not present in December inspection

    [8] newjerseymonitor.com

  6. (source date; the content gives no date of its own)

    Construction expected to be done in late December 2026

    [12] newjerseyglobe.com

  7. (source date; the content gives no date of its own)

    DEP inspectors found 62 1,982 kilowatt generators during July 29 visit that were not present in December 2025 inspection

    [12] newjerseyglobe.com

  8. (source date; the content gives no date of its own)

    New Jersey DEP found DataOne facility operated 62 large natural gas generators without required air permits

    [17] news.bgov.com

  9. (source date; the content gives no date of its own)

    New Jersey DEP found 62 natural gas generators with 1,982 kilowatt capacity each operating without required permits during July 29 inspection

    [20] newsweek.com

  10. (source date; the content gives no date of its own)

    DataOne is transitioning to low emission fuel cells as the permanent power source

    [19] inquirer.com

  11. (source date; the content gives no date of its own)

    DataOne installed and operated 62 large natural gas power generators without required state permits

    [19] inquirer.com

  12. (source date; the content gives no date of its own)

    First phase of the site is expected to open later this year

    [11] gothamist.com

  13. (source date; the content gives no date of its own)

    Construction on the $17 billion South Jersey project backed by Microsoft began in early 2025

    [11] gothamist.com

  14. (source date; the content gives no date of its own)

    Generators were not present at previous inspection in December 2025 but were installed by July 29, 2026 site inspection

    [11] gothamist.com

  15. (source date; the content gives no date of its own)

    Natural gas power generating equipment was observed during an inspection on July 29 but was not observed during the DEP's previous site inspection in December 2025.

    [10] whyy.org

  16. (source date; the content gives no date of its own)

    Facility sits in a protected wellhead area with groundwater contamination risk

    [6] nj1015.com

  17. (source date; the content gives no date of its own)

    Cooling requires more than 400 fans

    [6] nj1015.com

  18. (content date)

    Vineland Planning Board issued its Notice of Determination approving DataOne's amended preliminary and final major site plan for phase two (application PBA-24-00022); the vote was August 17, 2026

    [3] vinelandcity.org

  19. (source date; the content gives no date of its own)

    DataOne Campus sits roughly one mile from two schools

    [5] communitynews.org

  20. (source date; the content gives no date of its own)

    DataOne Campus sits approximately 40 miles from Philadelphia

    [5] communitynews.org

  21. (source date; the content gives no date of its own)

    DataOne Campus construction began in 2025

    [5] communitynews.org

  22. (source date; the content gives no date of its own)

    DataOne Campus is planned as New Jersey's largest AI data center under $17 billion agreement with Microsoft

    [5] communitynews.org

  23. (source date; the content gives no date of its own)

    DataOne Campus in Vineland accused of running 45 gas generators without permits

    [5] communitynews.org

  24. (source date; the content gives no date of its own)

    Thermal drone footage from late June shows 25 of the unpermitted gas generators operating

    [16] latitudemedia.com

  25. (source date; the content gives no date of its own)

    First unpermitted generators appear to have been turned on in October according to maintenance logs

    [16] latitudemedia.com

  26. Filing (source date; the content gives no date of its own)

    DataOne withdrew gas engine permit application in May 2026

    [16] latitudemedia.com

  27. Filing (source date; the content gives no date of its own)

    DataOne originally submitted permit application for more than 30 Bergen gas burning engines

    [16] latitudemedia.com

  28. (source date; the content gives no date of its own)

    DataOne broke ground in 2025

    [16] latitudemedia.com

  29. · being built (source date; the content gives no date of its own)

    DataOne facility is partly completed and operates at least 45 of 62 generators

    [16] latitudemedia.com

  30. · approved (source date; the content gives no date of its own)

    Planning Board approved power supply changes to the phase two site plan, which was already under construction; reported August 18.

    [23] nbcphiladelphia.com, also [24] nj.com, also [22] blockspace.media

  31. (content date)

    Phase III engines reported operating by this date

    [1] earthjustice.org

  32. · being built (content date)

    First 16 engines reported operating by this date

    [1] earthjustice.org, also [16] latitudemedia.com

Every event in order

18 corrections to this record

Every correction, with its reason
  1. · Timeline entry

    Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.

  2. · Publication status

    Superseded: the entry's primary source was dep.nj.gov/boss/, which does not report the August 17, 2026 Planning Board vote, and a published entry's source cannot change. The same fact is on the record again with NBC Philadelphia as its source.

  3. · Timeline entry

    The August 18 entry attributed the approval to the city council. The city council did not vote on it; the Planning Board approved power supply changes to the phase two site plan on August 17, 2026 (NBC Philadelphia, with its published correction).

  4. · Project summary

    The prior summary gave the Notice of Determination date as the approval date. The Planning Board voted August 17, 2026 and issued its notice September 12, 2026.

  5. · Project summary

    The prior summary gave one start date for all 62 engines. The Sustain SJ notice of intent to sue (page 2) says the first 16 engines were operating by October 13, 2025 and the Phase III engines by June 23, 2026.

  6. · Site acreage (2.6 acres to 107 acres)

    The site read 2.6 acres. Two approvals wrote square feet as acres over the 107 acres an Asbury Park Press article of September 22, 2026 gave (2.6 million square feet and 2,600,000 square feet are a floor area). Restored to 107 acres from that article.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  9. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  10. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  11. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  12. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in New Jersey

No other verified data center record in New Jersey is located within 60 miles of this site. Browse all data centers in New Jersey.

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Capacity at full buildout

6 figures, 7 sources
300 MW Developer's figure

Nebius, Oct 21, 2026

37 kilowatts Reported

Newsweek, Sep 22, 2026

Show each source's words
  • 1,982 kilowatts, Inquirer.com: Each of the 62 generators has a capacity of 1,982 kilowatts
  • 1,982 kilowatts, The Times of India: Each DataOne generator had a rated capacity of 1,982 kilowatts.
  • 350 MW, Gothamist: DataONE data center in Vineland designed to draw up to 350 megawatts of power
  • 123 MW, NJBIZ: 62 Caterpillar G3516H gas generators, each producing 1982 kilowatts, total capacity about 123 megawatts
  • 123 MW, TechRadar: 62 natural gas generators with collective 123 megawatt capacity installed without permits at DataOne Vineland facility.
  • 122.9 MW, The Times of India: The 62 DataOne generators represented approximately 122.9 megawatts of nameplate generation capacity.
  • 37 kilowatts, Newsweek: Generator capacity threshold for state permits is 37 kilowatts

Common questions about Nebius and DataOne Vineland AI Data Center Campus

Answered directly from the verified filings and local actions on this page.

Who is building Nebius and DataOne Vineland AI Data Center Campus?

DataOne is the developer. No construction contractor is named on the record yet.

Who will use Nebius and DataOne Vineland AI Data Center Campus?

The named tenants are Nebius Group, Microsoft. No promise to the community is on the record.

How much power and water does Nebius and DataOne Vineland AI Data Center Campus say it needs?

Power: 300 MW (the developer's figure, nebius.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does Nebius and DataOne Vineland AI Data Center Campus stand today?

It is being built, since September 12, 2026. The newest entry, reported October 24, 2026: DataOne said the engines are temporary [29].

What is still unknown about Nebius and DataOne Vineland AI Data Center Campus?

Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. Clean Air Act Notice of Intent to Sue DataOne USA LLC, DataOne Vineland LLC, Nebius Inc. and Northeast Precast LLC (opens in a new tab), Earthjustice / Sustain SJ, October 21, 2026
  2. NJDEP Administrative Order and Notice of Civil Administrative Penalty Assessment EA ID PEA260001-75894 (opens in a new tab), New Jersey Department of Environmental Protection, September 22, 2026
  3. City of Vineland Planning Board Notice of Determination, Application PBA-24-00022 (opens in a new tab), City of Vineland Planning Board, September 12, 2026
  4. Nebius Vineland New Jersey Data Center Project Page (300 MW) (opens in a new tab), Nebius, October 21, 2026

Reporting

  1. Vineland AI Data Center Accused of Running Dozens of Unpermitted Gas Generators - communitynews.org (opens in a new tab), communitynews.org, September 12, 2026, local outlet
  2. "You sold us out!" Vineland residents keep fighting anyway. - New Jersey 101.5 (opens in a new tab), New Jersey 101.5, September 14, 2026, local outlet
  3. Bloom Energy Shares Rise as Nebius AI Data Centre Partnership Boosts Power Demand Outlook (opens in a new tab), finance.yahoo.com, August 17, 2026, national outlet
  4. NJ slaps Vineland data center with $1M fine for unpermitted generators - New Jersey Monitor (opens in a new tab), New Jersey Monitor, September 22, 2026, local outlet
  5. NJ fines Vineland AI data center $1M over natural gas generators - app.com (opens in a new tab), app.com, September 22, 2026, news outlet
  6. Vineland data center fined more than $1 million for operating natural gas generators without a permit (opens in a new tab), WHYY, September 22, 2026, local outlet
  7. NJ fines data center $1 million for illegally powering facility with gas generators (opens in a new tab), Gothamist, September 22, 2026, local outlet
  8. Sherrill administration hits Vineland data center with record $1.07 million fine - New Jersey Globe (opens in a new tab), New Jersey Globe, September 22, 2026, local outlet
  9. NJ hits Vineland data center with $1.07M penalty over 62 natural gas generators - News12 | Long Island (opens in a new tab), News12 | Long Island, September 22, 2026, local outlet
  10. NJ regulators fine data center for gas generators that lack permits (opens in a new tab), NJ Spotlight News, September 23, 2026, local outlet
  11. NJ data center DataOne fined $1.07M for air violations - NJBIZ (opens in a new tab), NJBIZ, September 23, 2026, local outlet
  12. One of the East Coast’s largest data centers has been accused of ‘violating federal law’ - Latitude Media (opens in a new tab), Latitude Media, August 28, 2026, news outlet
14 more sources
  1. Microsoft Data Centers Hit With Fines in New Jersey, Virginia - Bloomberg Government News (opens in a new tab), Bloomberg Government News, September 22, 2026, news outlet
  2. NJ is hitting a massive data center in South Jersey with a million dollar fine. Is it enough? - nj1015.com (opens in a new tab), nj1015.com, September 23, 2026, local outlet
  3. Vineland AI data center hit with a $1 million fine - Inquirer.com (opens in a new tab), Inquirer.com, September 22, 2026, local outlet
  4. New Jersey Data Center Fined More Than $1M Over Air Pollution Violation - Newsweek (opens in a new tab), Newsweek, September 22, 2026, national outlet
  5. New Jersey's largest planned AI data center accused of running 45 unpermitted generators - Yahoo (opens in a new tab), Yahoo, September 12, 2026, national outlet
  6. Vineland, New Jersey city council approves DataOne expansion for Nebius AI data center - Blockspace Media (opens in a new tab), Blockspace Media, August 18, 2026, news outlet
  7. Vineland planning board votes to approve adjustment to Phase 2 of data center - NBC10 Philadelphia (opens in a new tab), NBC10 Philadelphia, August 18, 2026, local outlet
  8. ‘You sold us out!’ N.J. town approves next phase of massive AI data center as residents erupt - nj.com (opens in a new tab), nj.com, August 18, 2026, local outlet
  9. City of Vineland, N.J. issues stop-work order to parts of data center - WHYY (opens in a new tab), WHYY, August 14, 2026, local outlet
  10. Vineland data center accused of operating natural gas generators without permit - WHYY (opens in a new tab), WHYY, August 28, 2026, local outlet
  11. Community Advocates Plan to Sue Data Center Company Over Illegal Air Pollution in New Jersey (opens in a new tab), Earthjustice, October 21, 2026, news outlet
  12. Vineland residents plan to sue data center over unpermitted natural gas engines (opens in a new tab), WHYY, October 23, 2026, local outlet
  13. Vineland Residents Move to Sue Data Center Over 62 Gas Generators and Missing Permits (opens in a new tab), SNJ Today, October 24, 2026, news outlet
  14. Sustain SJ sues Vineland over DataOne approval, challenging stormwater plans and planning board authority (opens in a new tab), NJ Spotlight News / South Jersey Climate News, October 16, 2026, news outlet

30 sources on file.

Regional grid context

This site is in the RFC East (RFCE) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Nebius and DataOne Vineland AI Data Center Campus", https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj, last verified October 25, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Nebius and DataOne Vineland AI Data Center Campus", https://datacenterrecord.org/projects/nebius-ai-data-center-vineland-nj. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
reviewed in depth
Tags
In court, Reviewed in depth
Coordinates
39.4685, -74.9842
How the location is known
Location from the site's street address.
Location source
https://earthjustice.org/document/sustain-south-jersey-notice-of-intent-to-sue-dataone-for-clean-air-act-violations
Coordinate source
City of Vineland Planning Board PBA-24-00022 / NJDEP EA ID PEA260001-75894 (3963 South Lincoln Avenue, Block 7503, Lots 1.01 and 35.01)
Location last verified
September 16, 2026
How capacity was disclosed
the developer's figure
How acreage was disclosed
what a permit allows
Capacity, if disclosed
300 MW, the developer's figure
Published
September 5, 2026
Last verified
October 25, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, Interconnection, Rating of the county's rows

Researcher view · Nebius and DataOne Vineland AI Data Center Campus · 30 sources, 40 entries · basis and source tier on every row · verified October 25, 2026