Data centers in Vineland, New Jersey

Vineland has 1 data center on the record; it is proposed. Vineland has a scorecard row with no rating yet. The latest decision on the record: DataOne installed 62 gas generators without required air pollution permits, September 23, 2026. Cumberland County's own decisions are on the Cumberland County page.

Updated · Every line below links to its source · How the record works

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

The data center in Vineland

Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.

  1. Land
    107 acresthird party estimate
    Power
    300 MWthird party estimate
    Water
    20,000,000 gallons a yearthird party estimate
    Tenant
    Nebius Group / Microsoft

Where

1 data center in Vineland: proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.

The outline is Vineland's boundary from the U.S. Census Bureau. Tap a pin for that data center's facts and a link to its page.

What Vineland has decided

1 body, 4 decisions on the record

What the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.

Reported: the source's date; the item names no day of its own.

  1. Vinelandcity

    DataOne installed 62 gas generators without required air pollution permits, reported September 23, 2026.

    nbcphiladelphia.com local outlet

    no published rating
    4 acts on this row
    1. event

      DataOne installed 62 gas generators without required air pollution permits

      nbcphiladelphia.com local outlet

    2. event

      New Jersey Department of Environmental Protection fined DataOne more than 1 million dollars for operating 62 natural gas powered generators without a permit at the Vineland data center.

      whyy.org local outlet

      Also reported by 1 source
    3. approval

      Vineland Planning Board voted 8-1 to approve the project's second phase

      nj1015.com local outlet

    4. litigation

      Local residents filed lawsuit in New Jersey state court over noise pollution from data center

      latitudemedia.com local outlet

    Last verified September 24, 2026.

The rules across New Jersey.

What was said

Ed Potosnak, NJDEP Commissioner, called this the largest action ever taken against a data center in New Jersey
Ed Potosnak, New Jersey Department of Environmental Protection Commissioner · September 23, 2026 · paraphrased · NJBIZ local outlet
Environmental advocates including Pinelands Alliance renewed calls for a statewide moratorium on data center construction
Jaclyn Rhoads, Pinelands Alliance Executive Director · September 22, 2026 · paraphrased · New Jersey 101.5 local outlet
Andrew Groetsch noticed his daughter's windows vibrating in September 2025 from data center noise
Andrew Groetsch, homeowner · September 14, 2026 · paraphrased · New Jersey 101.5 local outlet

Every New Jersey statement, by speaker

4 more statements on this page

Governor

Gov. Mikie Sherrill called the fine the largest enforcement action against a data center in New Jersey's history.

September 22, 2026, NBC10 Philadelphia · NBC10 Philadelphia local outlet · the record (Paraphrased; content date; reported from elsewhere)

Bruce Buckheit, former EPA chief of air enforcement, said the situation appears to break federal law

September 12, 2026, communitynews.org · communitynews.org local outlet · the record (Paraphrased; said in the source itself)

Nebius executives said the fuel cell power solution would have no significant impact on the project development timeline

August 17, 2026, finance.yahoo.com · finance.yahoo.com national outlet · the record (Paraphrased; said in the source itself)

Nick Amicucci, Evercore ISI analyst, reiterated bullish view on Bloom Energy, with $350 price target

August 17, 2026, finance.yahoo.com · finance.yahoo.com national outlet · the record (Paraphrased; said in the source itself)

Disclosed figures

300 MW power, water from 1 record

Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.

Power, water, jobs and tax

FigureDisclosed totalDisclosedNot disclosedBasis
Power300 MW101 third party estimate
Water, stated per year20,000,000 gallons a year101 third party estimate
Permanent jobsNot disclosed01Not disclosed by any of the 1 record
Tax each yearNot disclosed01Not disclosed by any of the 1 record

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

By what the facilities are for

UseRecordsPowerWaterJobsTax each year
Not disclosed1300 MW20,000,000 gallons a yearNot disclosedNot disclosedNot disclosed: jobs, tax each year

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

What the facilities are for

No source on file states what any of the 1 tracked facility in Vineland is for.

How the facilities are cooled

No source on file states how any of the 1 tracked facility in Vineland is cooled.

Cite this page

Data Center Record, "Data centers in Vineland, Cumberland County, New Jersey", https://datacenterrecord.org/states/nj/cumberland-county/vineland, updated September 25, 2026.

Cite this page

Data Center Record, "Data center records in Vineland, Cumberland County, New Jersey", https://datacenterrecord.org/states/nj/cumberland-county/vineland. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change

The rows here are part of the New Jersey export.

For researchers
Place id
us/nj/cumberland-county/vineland
Level
city
Census GEOID
Not disclosed
Rating value
Not disclosed
Scale word
Not disclosed