Governor
Gov. Mikie Sherrill called the fine the largest enforcement action against a data center in New Jersey's history.
Cumberland County has 1 data center on the record; it is proposed. No county rule about data centers is on the record for Cumberland County itself; 1 body inside it has a scorecard row. The latest decision on the record: DataOne installed 62 gas generators without required air pollution permits (Vineland), September 23, 2026.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
Each row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Vineland, Cumberland County · DataOne
Latest, reported September 24, 2026: New Jersey Department of Environmental Protection inspected DataOne facility in Vineland on July 29, 2026 and found 62 stationary natural gas generators operating without required preconstruction permits and operating certificates. timesofindia.indiatimes.com local outlet
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
1 data center in Cumberland County: proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
| City | Projects | Rules |
|---|---|---|
| Vineland | 1 | 1 |
What the county and the cities in it have done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
DataOne installed 62 gas generators without required air pollution permits, reported September 23, 2026.
DataOne installed 62 gas generators without required air pollution permits
New Jersey Department of Environmental Protection fined DataOne more than 1 million dollars for operating 62 natural gas powered generators without a permit at the Vineland data center.
Vineland Planning Board voted 8-1 to approve the project's second phase
Local residents filed lawsuit in New Jersey state court over noise pollution from data center
· Vineland
Scorecard event: DataOne installed 62 gas generators without required air pollution permits nbcphiladelphia.com local outlet
· Vineland
Scorecard event: New Jersey Department of Environmental Protection fined DataOne more than 1 million dollars for operating 62 natural gas powered generators without a permit at the Vineland data center. whyy.org local outlet
· Vineland
Approval: Vineland Planning Board voted 8-1 to approve the project's second phase nj1015.com local outlet
· Nebius AI Data Center (Vineland)
Now reported: DataOne Campus in Vineland accused of running 45 gas generators without permits communitynews.org local outlet
· Vineland
Litigation: Local residents filed lawsuit in New Jersey state court over noise pollution from data center latitudemedia.com local outlet
Ed Potosnak, NJDEP Commissioner, called this the largest action ever taken against a data center in New Jersey
Environmental advocates including Pinelands Alliance renewed calls for a statewide moratorium on data center construction
Andrew Groetsch noticed his daughter's windows vibrating in September 2025 from data center noise
Every New Jersey statement, by speaker
Governor
Gov. Mikie Sherrill called the fine the largest enforcement action against a data center in New Jersey's history.
Bruce Buckheit, former EPA chief of air enforcement, said the situation appears to break federal law
Nebius executives said the fuel cell power solution would have no significant impact on the project development timeline
Nick Amicucci, Evercore ISI analyst, reiterated bullish view on Bloom Energy, with $350 price target
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | 300 MW | 1 | 0 | 1 third party estimate | |
| Water, stated per year | 20,000,000 gallons a year | 1 | 0 | 1 third party estimate | |
| Permanent jobs | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record | |
| Tax each year | Not disclosed | 0 | 1 | Not disclosed by any of the 1 record |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 1 | 300 MW | 20,000,000 gallons a year | Not disclosed | Not disclosed | Not disclosed: jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states what any of the 1 tracked facility in Cumberland County is for.
No source on file states how any of the 1 tracked facility in Cumberland County is cooled.
Data Center Record, "Data centers in Cumberland County, New Jersey", https://datacenterrecord.org/states/nj/cumberland-county, updated September 25, 2026.
Data Center Record, "Data center records in Cumberland County, New Jersey", https://datacenterrecord.org/states/nj/cumberland-county. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the New Jersey export.