Nebius and DataOne Vineland AI Data Center Campus, in order
What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.
14 events, January 1, 2025 to October 21, 2026. Also on the record, under the month each belongs to: 14 statements, 17 figures from other sources and 26 dates when source pages were read and verified. The facts, newest first: the record; the place: New Jersey.
A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.
Stages
2025 5 events
-
(the year its own sentence names; filed under Aug 28, 2026)
Entry
DataOne broke ground in 2025 [16]
-
(the year its own sentence names; filed under Sep 12, 2026)
Entry
DataOne Campus construction began in 2025 [5]
-
(the year its own sentence names; filed under Sep 22, 2026)
Entry
Construction on the $17 billion South Jersey project backed by Microsoft began in early 2025 [11]
-
(content date)
being built
First 16 engines reported operating by this date [1]
-
(the month its own sentence names; no day is given; filed under Sep 22, 2026)
Entry
Generators were not present at previous inspection in December 2025 but were installed by July 29, 2026 site inspection [11]
2026 9 events
-
(the month its own sentence names; no day is given; filed under Aug 28, 2026)
Entry
DataOne withdrew gas engine permit application in May 2026 [16]
-
Also in June 2026: 1 date when a source page was read and verified
-
(content date)
Entry
Phase III engines reported operating by this date [1]
-
-
(the day its own sentence names; filed under Sep 23, 2026)
Entry
DataOne received two stop work orders from City of Vineland on August 6 and August 10 for construction permit violations [15]
-
(source date; the content gives no date of its own)
approved
Planning Board approved power supply changes to the phase two site plan, which was already under construction; reported August 18. [23]
-
(source date; the content gives no date of its own)
being built
DataOne facility is partly completed and operates at least 45 of 62 generators [16]
-
Also in August 2026: 2 statements, 1 figure from another source and 3 dates when source pages were read and verified
-
(said in the source itself)
Statement · Nebius executives
Nebius executives said the fuel cell power solution would have no significant impact on the project development timeline finance.yahoo.com (opens in a new tab) national outlet
-
(said in the source itself)
Statement · Nick Amicucci, Evercore ISI analyst
Nick Amicucci, Evercore ISI analyst, reiterated bullish view on Bloom Energy, with $350 price target finance.yahoo.com (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Figure · finance.yahoo.com
1,065,000,000 USD: Bloom Energy reported Q2 2026 revenue surged 165.5% year over year to $1.065 billion and raised full year guidance to $3.9-4.2 billion finance.yahoo.com (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Entry
Thermal drone footage from late June shows 25 of the unpermitted gas generators operating [16]
-
(source date; the content gives no date of its own)
Entry
First unpermitted generators appear to have been turned on in October according to maintenance logs [16]
-
(source date; the content gives no date of its own)
Entry
DataOne originally submitted permit application for more than 30 Bergen gas burning engines [16]
-
-
(content date)
Entry
Vineland Planning Board issued its Notice of Determination approving DataOne's amended preliminary and final major site plan for phase two (application PBA-24-00022); the vote was August 17, 2026 [3]
-
(content date)
Entry
New Jersey DEP issued an Administrative Order and Notice of Civil Administrative Penalty Assessment (EA ID PEA260001-75894) against DataOne for operating 62 natural gas engines without a preconstruction permit or operating certificate, with a $1.07 million penalty and 45 days to apply for minor source permits [2]
-
Also in September 2026: 5 statements, 16 figures from other sources and 21 dates when source pages were read and verified
-
(source date; the content gives no date of its own)
Entry
DataOne Campus sits roughly one mile from two schools [5]
-
(source date; the content gives no date of its own)
Entry
DataOne Campus sits approximately 40 miles from Philadelphia [5]
-
(source date; the content gives no date of its own)
Entry
DataOne Campus is planned as New Jersey's largest AI data center under $17 billion agreement with Microsoft [5]
-
(source date; the content gives no date of its own)
Entry
DataOne Campus in Vineland accused of running 45 gas generators without permits [5]
-
(said in the source itself)
Statement · Bruce Buckheit, former EPA chief of air enforcement
Bruce Buckheit, former EPA chief of air enforcement, said the situation appears to break federal law communitynews.org (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry
Facility sits in a protected wellhead area with groundwater contamination risk [6]
-
(source date; the content gives no date of its own)
Entry
Cooling requires more than 400 fans [6]
-
(said in the source itself)
Statement · Andrew G., homeowner
Andrew G. noticed his daughter's windows vibrating in September 2025 from data center noise New Jersey 101.5 (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · New Jersey 101.5
17,000,000,000 dollars: DataOne facility value near 17 billion dollars New Jersey 101.5 (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Entry
DataOne is transitioning to low emission fuel cells as the permanent power source [19]
-
(source date; the content gives no date of its own)
Entry
DataOne installed and operated 62 large natural gas power generators without required state permits [19]
-
(source date; the content gives no date of its own)
Entry
First phase of the site is expected to open later this year [11]
-
(source date; the content gives no date of its own)
Entry
Natural gas power generating equipment was observed during an inspection on July 29 but was not observed during the DEP's previous site inspection in December 2025. [10]
-
(source date; the content gives no date of its own)
Entry
Generators are temporary with transition to fuel cells for permanent power supply [13]
-
(source date; the content gives no date of its own)
Entry
DEP found 62 stationary generators with 1,982 kilowatt capacity each during July 29 inspection without required permits [13]
-
(source date; the content gives no date of its own)
Entry
Construction expected complete in late December according to company website [8]
-
(source date; the content gives no date of its own)
Entry
DEP inspection July 29 discovered 62 1,982 kilowatt generators not present in December inspection [8]
-
(source date; the content gives no date of its own)
Entry
Construction expected to be done in late December 2026 [12]
-
(source date; the content gives no date of its own)
Entry
DEP inspectors found 62 1,982 kilowatt generators during July 29 visit that were not present in December 2025 inspection [12]
-
(source date; the content gives no date of its own)
Entry
New Jersey DEP found DataOne facility operated 62 large natural gas generators without required air permits [17]
-
(source date; the content gives no date of its own)
Entry
New Jersey DEP found 62 natural gas generators with 1,982 kilowatt capacity each operating without required permits during July 29 inspection [20]
-
(said in the source itself)
Statement · Jaclyn Rhoads, Pinelands Alliance Executive Director
Environmental advocates including Pinelands Alliance renewed calls for a statewide moratorium on data center construction New Jersey 101.5 (opens in a new tab) local outlet
-
(content date; reported from elsewhere)
Statement · Mikie Sherrill, Governor
Gov. Mikie Sherrill called the fine the largest enforcement action against a data center in New Jersey's history. NBC10 Philadelphia (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Inquirer.com
1,982 kilowatts: Each of the 62 generators has a capacity of 1,982 kilowatts Inquirer.com (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Gothamist
350 MW: DataONE data center in Vineland designed to draw up to 350 megawatts of power Gothamist (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Newsweek
37 kilowatts: Generator capacity threshold for state permits is 37 kilowatts Newsweek (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Entry
NJDEP inspection on July 29 found gas generators that were not present during December 2025 inspection [15]
-
(source date; the content gives no date of its own)
Entry
DataOne Vineland data center approved capacity 300 megawatts, currently projects 350 megawatts on website [15]
-
(source date; the content gives no date of its own)
Entry
DataOne expanded its Cumberland County Vineland facility last winter 2026, making it the state's largest operating data center. [18]
-
(said in the source itself)
Statement · Ed Potosnak, New Jersey Department of Environmental Protection Commissioner
Ed Potosnak, NJDEP Commissioner, called this the largest action ever taken against a data center in New Jersey NJBIZ (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · Cape May County Herald
1,982 kW: DEP imposed $1 million fine after July inspection revealed 62 unpermitted natural gas powered 1,982 kilowatt generators Cape May County Herald (opens in a new tab) news outlet
-
(source date; the content gives no date of its own)
Figure · NBC10 Philadelphia
1,070,000 dollars: New Jersey Department of Environmental Protection fined DataOne 1.07 million dollars NBC10 Philadelphia (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · NJBIZ
1,070,000 dollars: NJDEP fined DataOne 1.07 million dollars for installing 62 gas generators without required air permits NJBIZ (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · NJBIZ
123 MW: 62 Caterpillar G3516H gas generators, each producing 1982 kilowatts, total capacity about 123 megawatts NJBIZ (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · ROI-NJ
1,982 kW: Generators were 1,982 kilowatt stationary reciprocating engines ROI-NJ (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · ROI-NJ
62 count: 62 large natural gas power generators were installed and operating without required DEP permits ROI-NJ (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · NJ Spotlight News
1,982 kilowatts per engine: Each of the 62 stationary reciprocating generators at the DataOne site can generate 1,982 kilowatts of electricity, enough to power about 1,600 homes under normal conditions. NJ Spotlight News (opens in a new tab) local outlet
-
(source date; the content gives no date of its own)
Figure · 6abc Philadelphia
1,070,000 USD: Vineland data center fined $1.07 million for air pollution violations 6abc Philadelphia (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Figure · The Times of India
122.9 MW: The 62 DataOne generators represented approximately 122.9 megawatts of nameplate generation capacity. The Times of India (opens in a new tab) international outlet
-
(source date; the content gives no date of its own)
Figure · The Times of India
1,982 kilowatts: Each DataOne generator had a rated capacity of 1,982 kilowatts. The Times of India (opens in a new tab) international outlet
-
(source date; the content gives no date of its own)
Figure · TechRadar
62 generators: 62 natural gas generators on DataOne Vineland campus lacked preconstruction permits and operating certificates required under New Jersey Air Pollution Control Act. TechRadar (opens in a new tab) national outlet
-
(source date; the content gives no date of its own)
Figure · TechRadar
123 MW: 62 natural gas generators with collective 123 megawatt capacity installed without permits at DataOne Vineland facility. TechRadar (opens in a new tab) national outlet
-
-
(content date)
Entry
DataOne requested an administrative hearing and a stay of the DEP determination that it must obtain permits and certificates for the engines by November 6, 2026, calling the penalty disproportionate [1]
-
(content date)
Entry
Sustain SJ filed suit in New Jersey Superior Court challenging Vineland's approval of the DataOne site plan on stormwater and planning board authority grounds [30]
-
(content date)
Entry
Sustain SJ, represented by Earthjustice, sent DataOne USA LLC, DataOne Vineland LLC, Nebius Inc. and Northeast Precast LLC a notice of intent to sue under Section 304 of the Clean Air Act over 62 unpermitted gas engines, 1,231 fuel cells and 25 boilers at 3963 and 4081 South Lincoln Avenue; suit may follow after a 60 day notice period in the District of New Jersey [1]
-
Also in October 2026: 7 statements and 1 date when a source page was read and verified
-
(content date; reported from elsewhere)
Statement · Tiffany L., Resident
What health problems might I face in the future? Because I've been exposed to all of that. My kids have been exposed to it
floodlightnews.org (opens in a new tab) news outlet -
(content date; reported from elsewhere)
Statement · Xiaomeng Jin, Assistant Professor
Our best estimate is that the generators emitted about 140 tons of NOx
floodlightnews.org (opens in a new tab) news outlet -
(content date; reported from elsewhere)
Statement · Matt Williams, board chair
Matt Williams, Sustain SJ board chair, said the process has lacked transparency since construction began and community members were sidelined Earthjustice (opens in a new tab) news outlet
-
(content date; reported from elsewhere)
Statement · Casandia Bellevue, senior associate attorney
Regulatory compliance is not optional, and DataOne must be accountable to the surrounding community and to the Clean Air Act for its violations.
Earthjustice (opens in a new tab) news outlet -
(content date; reported from elsewhere)
Statement · KR Sridhar, Founder and CEO
We were able to get planning board approvals for our fuel cells within 3 months of signing the contract. Two months after these approvals, we have the first block of power ready for customer use
Blockspace Media / Yahoo Finance (opens in a new tab) news outlet -
(content date; reported from elsewhere)
Statement · KR Sridhar, Founder and CEO
We will not be the bottleneck to them turning on their data center their entire 300 megawatts
Blockspace Media / Yahoo Finance (opens in a new tab) news outlet -
(source date; the content gives no date of its own)
Entry
DataOne said the engines are temporary [29]
-
(said in the source itself)
Statement · DataOne
DataOne said the engines are temporary SNJ Today (opens in a new tab) news outlet
-
On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.
For researchers
- Stage
- being built
- Events on the timeline
- 14
- Under the months
- 57
- Stage changes
- 3
- Decisions
- 0
- Statements
- 14
- Figures
- 17
- Entries and decisions under the months
- 26