● Being Built Reported May 23, 2026 · 9 Buildings

Meta Louisiana data center

Street address 1500 Highway 80 East, Franklin Farms Mega Site, Holly Ridge, LA 71269, Richland Parish verified address Exact, at the address [1] County seat (Rayville), Wikidata, placed at county level

Overview, regulatory gates and specifications

Meta expanded its data center investment in Richland Parish, Louisiana to $50 billion, with the project reported to be creating jobs and opportunity in the parish. [36] Filings on the record specify 9 planned or operational buildings. [42] Meta construction at Richland Parish began increase in worker numbers in December 2024 [42]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Incentive review
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Campus is under construction; building inspections, utility energization and air permits are monitored.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [46]
9 buildings
Disclosed building count

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 1500 Highway 80 East, Franklin Farms Mega Site, Holly Ridge, LA 71269.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Water usage
Not disclosed
Land area
Not disclosed
Buildings
9 buildings operator page
[46] datacenters.atmeta.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Meta as stated by the source
[46] datacenters.atmeta.com
Official project website
meta.com (opens in a new tab) verified October 28, 2026
meta.com (opens in a new tab)
Archived promotional websites
meta.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Michael Crenshaw

Economic analyst

DID Recorded statement at Northeast Louisiana Economic Summit (October 22, 2026)
SAID And we all knew the 50 billion investment number, but what you can see is that it well exceeds any other data center. (October 22, 2026) knoe.com (opens in a new tab)

Loren C. Scott

President · Loren C. Scott and Associates

DID Recorded statement at Northeast Louisiana Economic Summit (October 22, 2026)
SAID In the case of Meta, there's 1,000 high-paying permanent jobs. You're way better off than you were, but you're not going to be as well off as you were during construction. A whole lot more jobs involved in building the plant than in operating it. (October 22, 2026) knoe.com (opens in a new tab)

Michael McEwen

Coastal reporter

DID Recorded statement at Red River Radio (October 12, 2026)
SAID Meta and Entergy fought to keep the peak power demand figure private (October 12, 2026) redriverradio.org (opens in a new tab)

Phillip May

Entergy CEO

DID Recorded statement at Red River Radio (October 12, 2026)
SAID Entergy CEO Phillip May said revealing the power demand information could expose them to business harms (October 12, 2026) redriverradio.org (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Meta
UTILITIES
Electric utility: Not disclosed

View all 61 statements on the record in Louisiana →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Meta Louisiana data center.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 9 buildings Site filing [46] datacenters.atmeta.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    Meta construction at Richland Parish began increase in worker numbers in December 2024

    [42] thecentersquare.com

  2. (source date; the content gives no date of its own)

    Meta announced Hyperion AI data center in northeast Louisiana

    [38] businessinsider.com

  3. (source date; the content gives no date of its own)

    Work continues on the Meta Richland Parish Data Center near Rayville as of August 3, 2026

    [37] nola.com

  4. (source date; the content gives no date of its own)

    Meta is described as having its largest project at Richland Parish, and one of the biggest in the world

    [50] wwno.org

  5. (source date; the content gives no date of its own)

    The programs were created since late 2024, when Meta broke ground on the Richland Parish data center

    [50] wwno.org

  6. (source date; the content gives no date of its own)

    Louisiana Delta Community College created new four week data center technician program

    [50] wwno.org

  7. (source date; the content gives no date of its own)

    Meta announced Richland Parish data center less than seven months after HB 827 passage in 2024

    [54] thecentersquare.com

  8. (source date; the content gives no date of its own)

    The data center is known as Hyperion

    [68] americanpress.com

36 earlier entries
  1. (source date; the content gives no date of its own)

    The data center will occupy five square miles and is scheduled to be fully operational in 2036.

    [41] nola.com

  2. (source date; the content gives no date of its own)

    Meta is expanding its investment at Hyperion to $50 billion from $10 billion, announced in July.

    [41] nola.com

  3. (source date; the content gives no date of its own)

    The commission's final decision on the seven new gas plants is scheduled for December 16, 2026

    [51] thelensnola.org

  4. (source date; the content gives no date of its own)

    Meta's data center in Richland Parish requires a total of 10 new gas plants, including three already approved last year

    [51] thelensnola.org

  5. (source date; the content gives no date of its own)

    Entergy Louisiana filed an application in April 2026 for seven additional gas fired power plants to serve Meta's data center expansion

    [51] thelensnola.org

  6. (source date; the content gives no date of its own)

    Interior buildout already underway in first buildings

    [57] turnerconstruction.com

  7. (source date; the content gives no date of its own)

    Meta expanded Richland Parish data center from originally announced 2 gigawatts to 5 gigawatts of IT capacity

    [57] turnerconstruction.com

  8. (source date; the content gives no date of its own)

    Entergy Louisiana will build seven new gas fired power plants to support the data center

    [36] 247wallst.com

  9. (source date; the content gives no date of its own)

    Permanent headcount of 1,000 jobs arrives after a decade of construction

    [36] 247wallst.com

  10. (source date; the content gives no date of its own)

    Full buildout of both phases not expected until around 2036

    [36] 247wallst.com

  11. (source date; the content gives no date of its own)

    Meta announced plans to expand Hyperion with seven additional power generating units

    [56] lailluminator.com

  12. (source date; the content gives no date of its own)

    Meta has contracted with Entergy Louisiana to build three natural gas powered turbines initially

    [56] lailluminator.com

  13. (source date; the content gives no date of its own)

    Both Hyperion and newer Evest artificial intelligence data centers could be among the largest in the world

    [61] wwno.org

  14. (source date; the content gives no date of its own)

    Meta and Entergy plan to build 10 new gas power plants to power the data center facilities

    [61] wwno.org

  15. (source date; the content gives no date of its own)

    Three natural gas powered turbines are being built by Entergy to initially power the data center

    [62] lailluminator.com

  16. (source date; the content gives no date of its own)

    Meta announced it intends to expand Hyperion with seven power generating units

    [62] lailluminator.com

  17. (source date; the content gives no date of its own)

    Meta announced it will nearly double expected size of its Hyperion campus in Northeast Louisiana

    [63] lailluminator.com

  18. (source date; the content gives no date of its own)

    Entergy Louisiana filed application in April 2026 to build seven additional gas fired power plants for Meta data center expansion

    [64] blog.ucs.org

  19. (source date; the content gives no date of its own)

    The Louisiana Public Service Commission's final decision on the new gas plants is scheduled for December 16, 2026.

    [51] thelensnola.org

  20. (source date; the content gives no date of its own)

    Entergy Louisiana filed an application in April 2026 to build seven additional gas fired power plants for Meta's data center expansion.

    [51] thelensnola.org

  21. (source date; the content gives no date of its own)

    Meta's data center expansion in Richland Parish, Louisiana requires seven additional gas plants, each rated at 754 megawatts, on top of three already approved.

    [51] thelensnola.org

  22. (source date; the content gives no date of its own)

    Meta announced the Richland Parish data center project in 2024

    [43] wafb.com

  23. (source date; the content gives no date of its own)

    Meta is building a large data center in Louisiana

    [44] nytimes.com

  24. (source date; the content gives no date of its own)

    Meta negotiated a secret Louisiana data center deal and got everything it wanted

    [45] nytimes.com

  25. (source date; the content gives no date of its own)

    Construction timeline extended by expansion to up to 10 years

    [71] shreveporttimes.com

  26. (source date; the content gives no date of its own)

    Meta expanded data center investment from $10 billion to $50 billion

    [71] shreveporttimes.com

  27. · being built (source date; the content gives no date of its own)

    The Richland Parish site broke ground in December 2024

    [72] netchoice.org

  28. (source date; the content gives no date of its own)

    Meta announced this month that it is expanding its Richland Parish data center to 5 gigawatts of compute capacity

    [72] netchoice.org

  29. (source date; the content gives no date of its own)

    Full 5 GW Hyperion project expected to be complete around 2032

    [48] cnbc.com

  30. (source date; the content gives no date of its own)

    Hyperion project should reach 2 GW by 2030

    [48] cnbc.com

  31. (source date; the content gives no date of its own)

    Meta Hyperion data center in Richland Parish planned as 5 GW facility

    [48] cnbc.com

  32. (source date; the content gives no date of its own)

    The data center is home to Hyperion, Meta's most powerful cluster for training AI

    [4] meta.com

  33. (source date; the content gives no date of its own)

    Meta expanding Richland Parish data center to 5 gigawatts of compute capacity

    [70] knoe.com

  34. (source date; the content gives no date of its own)

    Hyperion construction expected to continue until 2030

    [73] shreveportbossieradvocate.com

  35. (source date; the content gives no date of its own)

    The data center will be fueled by 10 newly constructed natural gas plants

    · Meta · Reported May 23, 2026 · Privacy enhanced player · loads on click

    [77] youtube.com

  36. (source date; the content gives no date of its own)

    Meta is building its largest AI data center in Richland Parish, Louisiana

    · Meta · Reported May 23, 2026 · Privacy enhanced player · loads on click

    [77] youtube.com

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Meta lists Meta Richland Parish Data Center at Richland Parish, Louisiana on its own page of data center locations, read September 14, 2026.

    [3] datacenters.atmeta.com

124 corrections to this record

Every correction, with its reason
  1. · County (Richland to Richland Parish)

    Louisiana's county equivalents are parishes, as the Census Bureau names them; the record stored Richland, which the pages printed as Richland County, and its page sat apart from the parish's own.

  2. · Citation

    Cites the later report of the same claim by the same speaker (said again on September 2, 2026; the record's rules, October 10, 2026).

  3. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  4. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  5. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  6. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  7. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  8. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  9. · Project summary

    the record's rules: the sentence copied its source, was about its headline or carried a number the card's facts do not; written again from the card's facts, on the editor's word

  10. · Project summary

    the record's rules: the sentence was the source's wording or carried a number not in the card's facts; written again from the article

  11. · Speaker role

    Speaker read again from the statement's source line, "Gov. Jeff Landry": the title in front of the name (Governor) is the role, not part of the name.

  12. · Speaker

    Speaker read again from the statement's source line, "Gov. Jeff Landry": the title in front of the name (Governor) is the role, not part of the name.

  13. · Speaker role

    Speaker read again from the statement's source line, "Gov. Jeff Landry": the title in front of the name (Governor) is the role, not part of the name.

  14. · Speaker

    Speaker read again from the statement's source line, "Gov. Jeff Landry": the title in front of the name (Governor) is the role, not part of the name.

  15. · Speaker role

    Speaker read again from the statement's source line, "Rep. Edmond Jordan, Louisiana Legislative Black Caucus chairman": the title in front of the name (Representative) is the role, not part of the name.

See all 118 corrections for this record (103 more) →

Every correction on the record is on the corrections page.

Nearest data centers in Louisiana

No other verified data center record in Louisiana is located within 60 miles of this site. Browse all data centers in Louisiana.

Comparisons

5 metrics with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Capacity at full buildout

6 figures, 9 sources
7.5 GW Reported

YouTube, May 23, 2026

Show each source's words
  • 7.5 GW, YouTube: The data center will consume 7.5 gigawatts of power
  • 5 GW, WAFB: The site will carry 5 gigawatts of compute space
  • 5 GW, The Equation - Union of Concerned Scientists: Meta data center peak computing electricity demand expected to grow to about 5,000 megawatts
  • 5 GW, WWNO: Meta's power request exceeds 5 gigawatts, the largest in state history
  • 5 GW, Louisiana Illuminator: Hyperion data center will require 5 gigawatts of power
  • 5 GW, Yahoo Finance: At least 5 gigawatts of IT capacity
  • 5 GW, Associated Construction Publications: Expanded campus will deliver 5 gigawatts of IT capacity across nearly 10 million square feet
  • 4,500 MW, Red River Radio: Meta data center in Richland Parish has peak power demand of 4,500 megawatts
  • 2.5 GW, Yahoo Finance: Meta committed to fund up to 2.5 gigawatts of clean and renewable energy
  • 754 MW, The Equation - Union of Concerned Scientists: Each of ten new gas plants rated at 754 megawatts of power
  • 754 MW, blog.ucs.org: Seven new gas plants for Meta data center, each 754 megawatts, totaling 7,540 megawatts,enough to power New Orleans annual peak demand six times over.
  • 540 MW, The Equation - Union of Concerned Scientists: Seven thousand 540 megawatts enough to power entire city of New Orleans annual peak demand six times over

Project footprint

2 figures, 2 sources
4,000 acres Reported

Yahoo Finance, Aug 14, 2026

3,600 acres Reported

WWNO, Sep 4, 2026

Show each source's words
  • 4,000 acres, Yahoo Finance: Hyperion will span nearly 10 million square feet across roughly 4,000 acres
  • 3,600 acres, WWNO: The facility covers more than 3,600 acres

Construction jobs

3 figures, 3 sources
7,500 jobs Document's figure

Meta Store, Jul 13, 2026

7,500 jobs Reported

Yahoo Finance, Aug 14, 2026

Show each source's words
  • 7,500 jobs, Meta Store: 7,500 jobs at peak construction and 1,000 operational roles
  • 7,500 jobs, Yahoo Finance: 7,500 temporary construction jobs at peak
  • 5,000 jobs, shreveportbossieradvocate.com: Meta Hyperion data center construction expected to bring 5,000 jobs at peak

Permanent jobs

7 figures, 10 sources
1,900 jobs Reported

Yahoo Finance, Aug 14, 2026

500 jobs Reported

YouTube, May 23, 2026

300 jobs Reported

YouTube, May 23, 2026

Show each source's words
  • 8,000 to 10,000 workers, NOLA.com: Local officials estimate 8,000 to 10,000 workers are laboring to build the data center.
  • 8,000 to 10,000 workers, americanpress.com: Local officials believe the influx of investment and workers swells the parish's population by about 8,000, or nearly 50%, each workday
  • 7,500 jobs, WAFB: The facility is expected to create 7,500 construction jobs and 1,000 permanent positions
  • 7,500 jobs, The Center Square: Construction at peak could support 7,500 workers; completed facility about 1,000 operational jobs
  • 1,900 jobs, Yahoo Finance: 1,900 additional indirect jobs in surrounding regional economy
  • 1,500 jobs, KNOE: The region could need up to 1,500 data center technicians
  • 1,000 jobs, ConstructConnect News: Campus will support 1,000 operational roles once complete
  • 1,000 jobs, NetChoice: The campus is expected to support more than 1,000 permanent roles
  • 1,000 jobs, Louisiana Illuminator: Meta announced 1,000 permanent jobs for Hyperion campus
  • 1,000 jobs, Yahoo Finance: 1,000 permanent on site operational jobs when fully built
  • 500 jobs, YouTube: Meta targeted 500 jobs for full tax incentives
  • 300 jobs, YouTube: Meta promised 300 jobs at 150 percent of the average annual state salary

Tax each year

8 figures, 10 sources
126,000,000 USD Reported

WAFB, Jul 29, 2026

Show each source's words
  • 126,000,000 USD, WAFB: Sales tax collections in the region climbed from $85 million to $126 million in the first quarter of 2026
  • 36,500,000 USD, shreveportbossieradvocate.com: Richland Parish School Board collected $36.5 million this fiscal year, with $16.2 million attributed to one cent tax
  • 22,400,000 USD, shreveportbossieradvocate.com: Meta Hyperion data center construction generated $22.4 million in first sales tax payment to Richland Parish
  • 22,000,000 USD, NOLA.com: Meta dropped more than $22 million in tax payments into Richland Parish
  • 50,935 USD, shreveportbossieradvocate.com: Richland Parish teachers got $50,935 bonuses in 2026 from sales tax revenue attributed to Meta Hyperion data center construction
  • 50,935 USD, The Center Square: Richland Parish teachers received $50,935 in June 2026 distribution for full share certified employees, up from $10,200 in 2025, from local sales tax surge tied to data center construction
  • 50,900 dollars, Shreveport Times: Vested, certified teachers in Richland Parish receiving sales tax bonus checks of $50,900 due to Meta data center construction
  • 50,000 USD, louisianaradionetwork.com: Teachers in Richland Parish receiving bonuses of up to $50,000 due to Meta data center tax revenues
  • 50,000 USD, NetChoice: Rising tax revenue tied to the data center has allowed the school district to pay its teachers annual bonuses up to $50,000, a 400% increase from the year before
  • 50,000 USD, NOLA.com: Teachers in Richland Parish will receive an extra $50,000 in bonuses thanks to sales tax boom from Meta.
  • 50,000 USD, Mid Florida Newspapers: Richland Parish, Louisiana generated tax revenue that funded $50,000 teacher bonuses from data centers
  • 50,000 USD, The Philadelphia Inquirer: Development of a data center in Richland Parish generated bonuses of up to $50,000 for local teachers as a result of increased tax collections.
  • 17,000 dollars, Shreveport Times: Other teachers and staff receiving sales tax bonuses of more than $17,000

Common questions about Meta Louisiana data center

Answered directly from the verified filings and local actions on this page.

Who is building Meta Louisiana data center?

Meta is the developer, datacenters.atmeta.com (opens in a new tab). No construction contractor is named on the record yet.

Who will use Meta Louisiana data center?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Meta Louisiana data center say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Meta Louisiana data center stand today?
What is still unknown about Meta Louisiana data center?

Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. Meta Data Center in Louisiana - LED - Louisiana Economic Development (.gov) (opens in a new tab), Louisiana Economic Development (.gov), July 13, 2026
  2. Meta Data Center in Louisiana - LED - Louisiana Economic Development - LED (.gov) (opens in a new tab), Louisiana Economic Development - LED (.gov), July 13, 2026
  3. Meta: Our U.S. data center fleet (opens in a new tab), Meta, September 14, 2026
  4. Investing in Richland Parish (opens in a new tab), Meta Store, July 13, 2026

Reporting

  1. Congresswoman Julia Letlow responds to Meta’s $50 billion Richland Parish expansion - KTVE – myarklamiss.com – Your ArkLaMiss News Source (opens in a new tab), KTVE – myarklamiss.com – Your ArkLaMiss News Source, July 13, 2026, news outlet
  2. Meta's Louisiana Data Center Is Making Rural America Part of the AI Race - Memeburn (opens in a new tab), Memeburn, July 16, 2026, news outlet
  3. Meta expands Richland Parish data center, now $50-billion project - hannapub.com (opens in a new tab), hannapub.com, July 13, 2026, news outlet
  4. Gov. Jeff Landry backs Meta's $50 billion data center expansion alongside Trump in D.C. - WDSU (opens in a new tab), WDSU, July 23, 2026, local outlet
  5. Concerns grow along with size of Meta data center - louisianaradionetwork.com (opens in a new tab), louisianaradionetwork.com, July 16, 2026, local outlet
  6. Gov. Jeff Landry cheers Meta expansion as local leaders, residents react - nola.com (opens in a new tab), nola.com, July 13, 2026, local outlet
  7. PSC votes against requiring Meta to reveal more about data center - WWLTV.com (opens in a new tab), WWLTV.com, August 12, 2026, local outlet
  8. Meta more than doubles size of Louisiana AI data center in massive $50 billion expansion - WAFB (opens in a new tab), WAFB, July 13, 2026, local outlet
  9. How big will the Richland Parish data center be? Meta will expand AI center - Shreveport Times (opens in a new tab), Shreveport Times, July 13, 2026, local outlet
  10. Meta expands Louisiana Hyperion data center to 5 gigawatts - finance.yahoo.com (opens in a new tab), finance.yahoo.com, July 27, 2026, national outlet
  11. Meta Will Invest Over $50B To Expand North Louisiana Data Center Campus - Business Facilities (opens in a new tab), Business Facilities, July 13, 2026, news outlet
  12. Meta plans $40 billion expansion of Louisiana AI data center, more than doubling its size - NOLA.com (opens in a new tab), NOLA.com, July 13, 2026, local outlet
61 more sources
  1. Meta to spend an additional $40B to expand colossal Louisiana data center - businessreport.com (opens in a new tab), businessreport.com, July 13, 2026, local outlet
  2. New York Times investigates Meta's data center deal in Louisiana - Axios (opens in a new tab), Axios, July 28, 2026, national outlet
  3. North Louisiana Meta data center to become largest center in history - WDSU (opens in a new tab), WDSU, July 13, 2026, local outlet
  4. Meta expands Louisiana data center to 5 gigawatts, investment crosses $50 billion - Reuters (opens in a new tab), Reuters, July 13, 2026, national outlet
  5. Meta expands plans for Richland Parish data center while investing in the local community - WBRZ (opens in a new tab), WBRZ, July 12, 2026, local outlet
  6. Meta data center in Richland Parish brings jobs, tax growth to northeast Louisiana - KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab), KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE, July 29, 2026, local outlet
  7. Gov. Jeff Landry discusses Meta's investment into Louisiana through data center in Richland Parish - wbrz.com (opens in a new tab), wbrz.com, July 12, 2026, local outlet
  8. Meta expands Louisiana Hyperion data center to 5GW and $50 billion - Yahoo Finance (opens in a new tab), Yahoo Finance, July 13, 2026, national outlet
  9. The power play behind Hyperion, Mark Zuckerberg’s colossal data center being built in rural Louisiana - Sherwood News (opens in a new tab), Sherwood News, December 15, 2025, news outlet
  10. Entergy keeps Meta data center load forecasts confidential - The Center Square (opens in a new tab), The Center Square, June 30, 2026, news outlet
  11. Entergy seeks more big projects in 2026 as Louisiana load surges - New Orleans CityBusiness (opens in a new tab), New Orleans CityBusiness, January 5, 2026, news outlet
  12. Louisiana AI Project to Grow to 5 GW - rtoinsider.com (opens in a new tab), rtoinsider.com, July 14, 2026, news outlet
  13. Williams expands northwest Louisiana Haynesville Shale as data centers drive demand - The Shreveport-Bossier City Advocate (opens in a new tab), The Shreveport-Bossier City Advocate, August 7, 2026, local outlet
  14. Groups Warn that La. Ratepayers Could be Saddled with Buildout for Meta’s Hyperion - RTO Insider (opens in a new tab), RTO Insider, August 9, 2026, news outlet
  15. Entergy receives regulatory approval for investments to support Meta's Louisiana data center - Reuters (opens in a new tab), Reuters, August 20, 2025, national outlet
  16. Entergy Louisiana gains regulatory approval for massive Meta power project - Louisiana Illuminator (opens in a new tab), Louisiana Illuminator, August 20, 2025, local outlet
  17. How big will the Richland Parish data center be? Meta will expand AI center - Yahoo Finance (opens in a new tab), Yahoo Finance, July 13, 2026, national outlet
  18. Gov. Jeff Landry hails expansion of Meta’s massive data center in Louisiana - NOLA.com (opens in a new tab), NOLA.com, July 13, 2026, local outlet
  19. Meta expanding Richland Parish data center to 5 gigawatts, one of the largest in history - WAFB (opens in a new tab), WAFB, July 14, 2026, local outlet
  20. Zuckerberg’s $250 Billion Louisiana Data Center Will Create Just 1,000 Jobs. That’s $250 Million Spent Per Job - Yahoo Finance (opens in a new tab), Yahoo Finance, August 14, 2026, national outlet
  21. Letters: As data center discussed for Livingston Parish, questions remain - NOLA.com (opens in a new tab), NOLA.com, September 10, 2026, local outlet
  22. I own a house rental business near a future Meta AI data center. Construction workers make up most of our tenants. - Business Insider (opens in a new tab), Business Insider, September 13, 2026, national outlet
  23. Meta expands controversial Louisiana AI data center investment to $50 billion - The Tulane Hullabaloo (opens in a new tab), The Tulane Hullabaloo, August 24, 2026, news outlet
  24. Meta builds a $50 billion dollar data center in Richland Parish, Louisiana - loyolamaroon.com (opens in a new tab), loyolamaroon.com, August 22, 2026, news outlet
  25. From RV camps to packed hotels, Meta data center project has LA parish bursting at the seams - NOLA.com (opens in a new tab), NOLA.com, August 21, 2026, local outlet
  26. $50,000 teacher checks have Louisiana parishes asking for data centers - The Center Square (opens in a new tab), The Center Square, September 17, 2026, national outlet
  27. Meta data center in Richland Parish brings jobs, tax growth to northeast Louisiana - WAFB (opens in a new tab), WAFB, July 29, 2026, local outlet
  28. 5 Things to Know About Meta’s Giant Data Center in Louisiana - The New York Times (opens in a new tab), The New York Times, July 28, 2026, national outlet
  29. How Meta Got Everything It Wanted in a Secret Louisiana Data Center Deal - The New York Times (opens in a new tab), The New York Times, July 27, 2026, national outlet
  30. Deepening our investment in Richland Parish, Louisiana - Meta Data Centers (opens in a new tab), Meta Data Centers, July 13, 2026, news outlet
  31. Teachers and Local Businesses Win as Meta Expands Louisiana Data Center - Meta Store (opens in a new tab), Meta Store, July 13, 2026, social media
  32. Meta's Louisiana data center investment to reach $50 billion, aided by generous tax incentives - CNBC (opens in a new tab), CNBC, July 13, 2026, national outlet
  33. Meta data center in northeast LA transforms local government: ‘Coming into the modern world’ - NOLA.com (opens in a new tab), NOLA.com, August 31, 2026, local outlet
  34. This community college is training Louisiana residents for jobs at Meta's data center - WWNO (opens in a new tab), WWNO, September 4, 2026, local outlet
  35. Meta hides data center info as it pushes more risks to Entergy’s customers - thelensnola.org (opens in a new tab), thelensnola.org, August 18, 2026, local outlet
  36. Louisiana regulators kill effort to subpoena details of Meta data center - E&E News by POLITICO (opens in a new tab), E&E News by POLITICO, August 13, 2026, news outlet
  37. Meta won’t have to turn over job, electric information after Louisiana regulators override judge - NOLA.com (opens in a new tab), NOLA.com, August 12, 2026, local outlet
  38. Louisiana Democrats helped bring Meta to the state. Some regret their votes - thecentersquare.com (opens in a new tab), thecentersquare.com, September 2, 2026, national outlet
  39. Meta’s data center will be the biggest in the U.S., but no one knows who they’re hiring - thelensnola.org (opens in a new tab), thelensnola.org, August 31, 2026, local outlet
  40. Meta can keep its data center details private, PSC decides - Louisiana Illuminator (opens in a new tab), Louisiana Illuminator, August 13, 2026, local outlet
  41. Expanded Meta Data Center Creates More Jobs and Opportunity in Richland Parish, Louisiana - Associated Construction Publications (opens in a new tab), Associated Construction Publications, August 18, 2026, news outlet
  42. Meta prevails as Louisiana regulators block disclosure of data center expansion records - Baton Rouge Business Report (opens in a new tab), Baton Rouge Business Report, August 12, 2026, local outlet
  43. Is a data center coming to Moss Bluff? Here’s what we know. - theadvocate.com (opens in a new tab), theadvocate.com, August 12, 2026, local outlet
  44. Regulators allow Meta to keep data center records secret - WAFB (opens in a new tab), WAFB, August 12, 2026, local outlet
  45. Louisiana PSC kills ruling that would force Meta to turn over key data center information - WWNO (opens in a new tab), WWNO, August 12, 2026, local outlet
  46. Meta wants to keep Hyperion data center details protected - Louisiana Illuminator (opens in a new tab), Louisiana Illuminator, August 11, 2026, local outlet
  47. Public Service Commission can demand transparency for Meta’s data center expansion - Louisiana Illuminator (opens in a new tab), Louisiana Illuminator, August 11, 2026, local outlet
  48. Meta Hides Data Center Info As it Pushes More Risks to Entergy’s Customers - The Equation - Union of Concerned Scientists (opens in a new tab), The Equation - Union of Concerned Scientists, August 10, 2026, news outlet
  49. As Meta data center expands, advocates push harder for transparency - Louisiana Illuminator (opens in a new tab), Louisiana Illuminator, August 5, 2026, local outlet
  50. Expanded Meta Data Center Creates More Jobs and Opportunity in Richland Parish, Louisiana - Associated Construction Publications (opens in a new tab), Associated Construction Publications, August 18, 2026, news outlet
  51. Meta hides data center info as it pushes more risks to Entergy’s customers - thelensnola.org (opens in a new tab), thelensnola.org, August 18, 2026, local outlet
  52. Editorial: Meta changing life in Richland Parish (opens in a new tab), americanpress.com, September 2, 2026, local outlet
  53. Meta data center in Richland Parish brings jobs, tax growth to northeast Louisiana (opens in a new tab), WAFB, July 29, 2026, local outlet
  54. Meta expanding Richland Parish data center to 5 gigawatts, one of the largest in history (opens in a new tab), KNOE, July 13, 2026, local outlet
  55. Louisiana Meta data center generates staggering sales tax growth (opens in a new tab), Shreveport Times, July 21, 2026, local outlet
  56. Digital Infrastructure as the Backbone of the Future: How Meta's Louisiana Data Center Expansion is Delivering Life Changing Returns (opens in a new tab), NetChoice, July 20, 2026, news outlet
  57. Meta data center tax infusion means $50,000 bonus checks for these Louisiana teachers - The Shreveport Bossier City Advocate (opens in a new tab), shreveportbossieradvocate.com, June 13, 2026, local outlet
  58. This community college is training Louisiana residents for jobs at Meta's data center - WWNO (opens in a new tab), WWNO, September 4, 2026, local outlet
  59. From RV camps to packed hotels, Meta data center project has LA parish bursting at the seams - NOLA.com (opens in a new tab), NOLA.com, August 21, 2026, local outlet
  60. Meta's Louisiana data center investment to reach $50 billion, aided by generous tax incentives (opens in a new tab), CNBC, July 13, 2026, national outlet
  61. Meta’s $200 Billion Bet on a Remote Data Center (opens in a new tab), YouTube, May 23, 2026, video

77 sources on file.

Regional grid context

This site is in the SERC Mississippi Valley (SRMV) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Meta Louisiana data center", https://datacenterrecord.org/projects/meta-louisiana-data-center-richland-la, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Meta Louisiana data center", https://datacenterrecord.org/projects/meta-louisiana-data-center-richland-la. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
32.4685, -91.6925
How the location is known
Location from the site's street address.
Location source
Parish seat (Rayville), Wikidata, placed at parish level
Coordinate source
US EPA ECHO FRS and municipal parcel records
Location last verified
November 6, 2026
Published
September 5, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the parish's rows

Researcher view · Meta Louisiana data center · 77 sources, 45 entries · basis and source tier on every row · verified November 6, 2026

Download CSV JSON