Google proposed a data center campus along Morris Thomas Road and Midway Road in Hermantown, St. Louis County, Minnesota. [2] Filings on the record specify 3 planned or operational buildings. [1] In March, Minnesota Power signed an agreement with Google to supply power to the proposed Hermantown data center. [6]
How much power it needs, how much water it would use and who would use it have not been disclosed.
Connected government officials, corporate entities, utilities and local rules on the public record.
The treaties are the supreme law of the land, despite what I heard here today(October 31, 2026) twincities.com (opens in a new tab)
I don't think we should have this data center here or any place close to here(October 31, 2026) twincities.com (opens in a new tab)
It was really moving to see people so passionate about their communities, about their environment, about the public process. And it was really moving to see them practice their right to free speech and practice their right to peacefully protest.(October 27, 2026) mprnews.org (opens in a new tab)
Scott Jensen, Republican candidate for Minnesota State Auditor, warned that Google data center in Hermantown will alter Duluth's landscape and regional ecosystem through water demand, grid challenges, and St. Louis River runoff impacts(September 28, 2026) duluthnewstribune.com (opens in a new tab)
View all 10 statements on the record in Minnesota →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Hermantown Data Center.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 3 buildings | agency filing [1] datacenters.google | |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
In March, Minnesota Power signed an agreement with Google to supply power to the proposed Hermantown data center.
(source date; the content gives no date of its own)
A $2 billion Google data center is proposed in Hermantown, Minnesota in the northeast part of the state.
(source date; the content gives no date of its own)
In March 2026, Minnesota Power signed an agreement with Google to supply power to the proposed Hermantown data center
(source date; the content gives no date of its own)
A $2 billion Google data center is proposed in Hermantown, Minnesota
· Status: proposed (content date)
Google proposed a data center in Hermantown, northeast Minnesota, which it subsequently scaled back in scope while conducting community outreach events; the Duluth Chamber of Commerce endorsed the project.
Held unplaced under the record's rules (October 13, 2026): the entry's words are about North Dakota, and this record is in Minnesota. Kept off the record, never deleted; it can be restored.
Held unplaced under the record's rules (October 13, 2026): the entry's words are about North Dakota, and this record is in Minnesota. Kept off the record, never deleted; it can be restored.
Held unplaced under the record's rules (October 13, 2026): the entry's words are about North Dakota, and this record is in Minnesota. Kept off the record, never deleted; it can be restored.
Held unplaced under the record's rules (October 13, 2026): the entry's words are about North Dakota, and this record is in Minnesota. Kept off the record, never deleted; it can be restored.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: the tier the record already gives enr.com. The link did not change.
Every correction on the record is on the corrections page.
Verified data center records in Minnesota within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Ark Data Centers Duluth Data Center Duluth, St. Louis County | 3 mi | Running | Ark Data Centers | 3 MW |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Google is the developer. No construction contractor is named on the record yet.
Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is proposed, since September 2, 2026. The newest entry, reported September 3, 2026: In March, Minnesota Power signed an agreement with Google to supply power to the proposed Hermantown data center. [6]
Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.
Official operator or facility campus page verified in 50 state website discovery pass.
6 sources on file.
This site is in the MRO West (MROW) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Google Hermantown Data Center. Last verified November 6, 2026. https://datacenterrecord.org/projects/google-hermantown-data-center-mn. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Google Hermantown Data Center
Data Center Record, "Google Hermantown Data Center", https://datacenterrecord.org/projects/google-hermantown-data-center-mn. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.