The Colorado Springs Planning Commission and City Council approved development plans for Raeden's two building Project Taurus data center campus at Peak Innovation Park near the Colorado Springs Airport in El Paso County, Colorado. [4] Project Taurus received conditional approval in August 2026 from planning commission [11]
U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.
Utility interconnection queue filings monitored.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 2520 Aviation Way, Colorado Springs, CO 80916.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Connected government officials, corporate entities, utilities and local rules on the public record.
Lynette Crow Iverson, Colorado Springs City Council President, signed a Civility Pledge.(September 30, 2026) gazette.com (opens in a new tab)
Mayor Yemi Mobolade signed a Civility Pledge.(September 30, 2026) gazette.com (opens in a new tab)
Jason Green, CEO of Raeden, said council did a poor job keeping the crowd civil and questioned why the mayor was not in attendance.(September 23, 2026) cpr.org (opens in a new tab)
A special hearing on Project Taurus was marked by tumult, resulting in police tasing a man and arresting other attendees.(September 23, 2026) cpr.org (opens in a new tab)
View all 30 statements on the record in Colorado →
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Raeden Project Taurus Data Center Campus.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | |||
| Site Footprint (Acres) | |||
| Data Hall Buildings | 2 buildings | permit filing [1] gazette.com | |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
9NEWS report on Colorado Springs Planning Commission and community proceedings in Colorado Springs, CO: Proposed data center in Colorado Springs meets public opposition (July 24, 2026).
"It's not based in fact or science. This isn't just about data centers. This is about the kids. This is about cops. This is about trails, open space and parks. And this is about roads. Colorado Springs Planning Commission signed off on the data center project last night. It is not a done deal though. If enough residents appeal the decision, Colorado Springs City Council will have to weigh in."
"And this is about roads. Colorado Springs Planning Commission signed off on the data center project last night. It is not a done deal though. If enough residents appeal the decision, Colorado Springs City Council will have to weigh in."
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
Project Taurus received conditional approval in August 2026 from planning commission
(source date; the content gives no date of its own)
New hearing scheduled for after April 2027 election
(source date; the content gives no date of its own)
New hearing set for after April 2027 election
(source date; the content gives no date of its own)
City planning department approved Raeden's Project Taurus application in June 2026
(source date; the content gives no date of its own)
Planning Commission approved Raeden's Project Taurus application in June 2026
(source date; the content gives no date of its own)
Project Taurus decision postponed until April 13, 2027, one week after municipal election.
(source date; the content gives no date of its own)
Colorado Springs City Council voted 7 to 2 to postpone decision on Project Taurus.
(source date; the content gives no date of its own)
Four people arrested at Colorado Springs City Council meeting on Project Taurus proposal on September 17, 2026 after altercation with police
(source date; the content gives no date of its own)
Colorado Springs City Council voted 7 to 2 to postpone final decision on Project Taurus until April 13, 2027
(source date; the content gives no date of its own)
Raeden plans to build a 30 foot sound wall to help reduce noise from Project Taurus
(source date; the content gives no date of its own)
Project Taurus data center would use a closed loop cooling system to help with water usage
(source date; the content gives no date of its own)
Project Taurus requires closed loop water cooling system
[10] koaa.com, also KOAA News 5 (opens in a new tab) local outlet
(source date; the content gives no date of its own)
Project Taurus redevelopment plan was approved by city planning
(source date; the content gives no date of its own)
City expects more than 100 spoken comments and significant public attendance
(source date; the content gives no date of its own)
Project Taurus is in a 25 year old building designed for industrial use
(source date; the content gives no date of its own)
City Council is slated to hear a final appeal on Project Taurus on September 17
(source date; the content gives no date of its own)
Full capacity of the system is 100 megawatts
(source date; the content gives no date of its own)
Colorado Springs Utilities has infrastructure in place to provide 72 megawatts to the facility
(source date; the content gives no date of its own)
Project Taurus would consume 50 megawatts of power continuously during the first year
(source date; the content gives no date of its own)
Planning Commission added restrictions to Project Taurus including capping power usage and requiring disclosure of utility use for first 10 years of operation.
(source date; the content gives no date of its own)
City Council will hear appeals to Project Taurus during a special meeting on September 17 at the Pikes Peak Center for the Performing Arts.
(source date; the content gives no date of its own)
Project Taurus concerns guided the six point standards
Filing (content date)
Colorado Springs City Council scheduled a final hearing for Project Taurus, a controversial proposed data center, after appeals were denied by the Planning Commission and the project moved ahead.
(source date; the content gives no date of its own)
Appeals to the approval are due before 5pm on June 22, 2026
(source date; the content gives no date of its own)
Raeden is the developer of Project Taurus
(source date; the content gives no date of its own)
Project Taurus covers approximately 22 acres at 1565 High Tech Way in Colorado Springs
· approved (source date; the content gives no date of its own)
Project Taurus received approval from Colorado Springs Planning Department on June 11, 2026
Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.
Normalize vote tallies ('X to Y') and dollar figures ('$X million/billion') to house style.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
Tier after resolution (September 21, 2026). The source on file is cpr.org, the publisher's own page. The item reached the record through Google News: "data center" Colorado, which the record carries at tier 1, and the approve copied the feed's tier onto this row. The tier now comes from the outlet, which the record already carries at tier 4 on 1 row of monitoring_sources. The speaker, the claim, the date and the url are unchanged.
Every correction on the record is on the corrections page.
Verified data center records in Colorado within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| T5 Colorado Springs Data Center Colorado Springs, El Paso County | 4 mi | Running | T5 Data Centers | 16 MW |
| QTS Colorado Springs Data Center Colorado Springs, El Paso County | 11 mi | Running | QTS Data Centers | 16 MW |
| Novva Data Centers Colorado Springs Campus Colorado Springs, El Paso County | 15 mi | Running | Novva Data Centers | 36 MW |
| Parker Highfield Parkway Data Center Campus Parker, Douglas County | 52 mi | Proposed | Compark / Highfield Data Center Developer | 2 buildings |
| OneNeck IT Solutions Englewood Data Center Douglas County | 52 mi | Running | OneNeck IT Solutions | 6 MW |
| Flexential Englewood Compark Data Center (DEN02) Parker, Douglas County | 52 mi | Running | Flexential | 14 MW |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Raeden is the developer, yahoo.com (opens in a new tab). No construction contractor is named on the record yet.
Power: not disclosed by any source on file. Water: not disclosed by any source on file.
It is approved, as reported June 15, 2026. The newest entry, reported September 21, 2026: Project Taurus received conditional approval in August 2026 from planning commission [11].
27 sources on file.
This site is in the WECC Rockies (RMPA) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Raeden Project Taurus Data Center Campus. Last verified November 6, 2026. https://datacenterrecord.org/projects/project-taurus-colorado-springs-co. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Raeden Project Taurus Data Center Campus
Data Center Record, "Raeden Project Taurus Data Center Campus", https://datacenterrecord.org/projects/project-taurus-colorado-springs-co. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.