● Running First recorded September 14, 2026 · 2 Buildings

Novva Data Centers Colorado Springs Campus

Street address 650 Sybilla Lane, Colorado Springs, CO 80921, El Paso County verified address Exact, at the address [1] EPA ECHO detailed facility report: Novva Colorado, Data Center Co Springs

Overview, regulatory gates and specifications

Novva Data Centers operates its two building, 36 MW Colorado Springs campus at 650 Sybilla Lane in Colorado Springs, El Paso County, Colorado (EPA FRS ID 110072219777). [1] Novva Data Centers lists Novva Colorado Springs data center at Colorado Springs, Colorado on its own page of data center locations, read September 14, 2026. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Energized
5. Air & Water Permits
EPA air permit on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
36 MW
the developer's figure

Equivalent to ~29,880 U.S. homes (U.S. EIA 830 homes/MW baseline) · 1.7% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
2 buildings
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 650 Sybilla Lane, Colorado Springs, CO 80921.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
36 MW developer figure Equivalent to the continuous electricity demand of about 29,900 average U.S. homes based on U.S. Energy Information Administration residential consumption data. About 0.4 percent of New York City's summer peak demand in 2024.
[1] echo.epa.gov
Water usage
Not disclosed
Land area
Not disclosed
Buildings
2 buildings permitted
[1] echo.epa.gov
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2023 (3 years)
Who leads it
Novva Data Centers as stated by the source
Official project website
novva.com (opens in a new tab) verified October 28, 2026
novva.com (opens in a new tab)
Archived promotional websites
novva.com (opens in a new tab) [Wayback snapshot] (opens in a new tab) preserved in Internet Archive
tracked domains
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Novva Data Centers Colorado Springs Campus, capacity: 36 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 36 ÷ 10,245 = 0.0035 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Novva Data Centers
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Novva Data Centers Colorado Springs Campus.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 36 MW 36 MW the developer's figure [1] echo.epa.gov
Site Footprint (Acres)
Data Hall Buildings 2 buildings 2 operator page [1] echo.epa.gov
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

July 24, 2026 Colorado Springs, CO Proposed data center in Colorado Springs meets public opposition Colorado Springs Planning Commission 2 clips

9NEWS report on Colorado Springs Planning Commission and community proceedings in Colorado Springs, CO: Proposed data center in Colorado Springs meets public opposition (July 24, 2026).

  1. 9NEWS Broadcast Report Broadcast Report transcribed from local broadcast report
    "It's not based in fact or science. This isn't just about data centers. This is about the kids. This is about cops. This is about trails, open space and parks. And this is about roads. Colorado Springs Planning Commission signed off on the data center project last night. It is not a done deal though. If enough residents appeal the decision, Colorado Springs City Council will have to weigh in."
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "And this is about roads. Colorado Springs Planning Commission signed off on the data center project last night. It is not a done deal though. If enough residents appeal the decision, Colorado Springs City Council will have to weigh in."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on September 14, 2026 (the day the page was read; it gives no date of its own)

    Novva Data Centers lists Novva Colorado Springs data center at Colorado Springs, Colorado on its own page of data center locations, read September 14, 2026.

    [1] echo.epa.gov

Nearest data centers in Colorado

Verified data center records in Colorado within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
QTS Colorado Springs Data Center Colorado Springs, El Paso County 4 mi Running QTS Data Centers 16 MW
Raeden Project Taurus Data Center Campus Colorado Springs, El Paso County 15 mi Proposed Raeden 2 buildings
T5 Colorado Springs Data Center Colorado Springs, El Paso County 16 mi Running T5 Data Centers 16 MW
Parker Highfield Parkway Data Center Campus Parker, Douglas County 38 mi Proposed Compark / Highfield Data Center Developer 2 buildings
OneNeck IT Solutions Englewood Data Center Douglas County 38 mi Running OneNeck IT Solutions 6 MW
Flexential Englewood Compark Data Center (DEN02) Parker, Douglas County 38 mi Running Flexential 14 MW

Blank cell: not disclosed by any source on file.

Common questions about Novva Data Centers Colorado Springs Campus

Answered directly from the verified filings and local actions on this page.

Who is building Novva Data Centers Colorado Springs Campus?

Novva Data Centers is the developer. No construction contractor is named on the record yet.

How much power and water does Novva Data Centers Colorado Springs Campus say it needs?

Power: 36 MW (the developer's figure, echo.epa.gov (opens in a new tab)). Water: not disclosed by any source on file.

Where does Novva Data Centers Colorado Springs Campus stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Tracked project domains

Promotional domains, campaign sites, and municipal portals preserved through the Internet Archive.

Primary documents

  1. EPA ECHO detailed facility report: Novva Colorado, Data Center Co Springs (opens in a new tab), U.S. Environmental Protection Agency

1 source on file.

Regional grid context

This site is in the WECC Rockies (RMPA) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Novva Data Centers Colorado Springs Campus", https://datacenterrecord.org/projects/novva-colorado-springs-data-center-co, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Novva Data Centers Colorado Springs Campus", https://datacenterrecord.org/projects/novva-colorado-springs-data-center-co. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.01283, -104.81429
How the location is known
Location from the site's street address.
Location source
https://www.novva.com/
Coordinate source
EPA FRS / El Paso County Assessor
Location source number
[1]
Location last verified
October 4, 2026
EPA registry id
110072219777
How capacity was disclosed
the developer's figure
Capacity, if disclosed
36 MW, the developer's figure
Published
September 14, 2026
Last verified
November 6, 2026
Not disclosed