Data Center Record.

SERC Virginia and Carolina South (SRVC-S)

Data Center Record tracks 46 facilities across North Carolina and South Carolina in the SERC Virginia and Carolina South (SRVC-S) regional power market.

Modeled wholesale electricity price effect and regional load

2024 to 2025 wholesale price effect
7.5 percent (+$3.01 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
2028 projected wholesale price effect
14.7 percent (+$4.94 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
Data center share of regional electricity load (2025)
5.9 percent, modeled data center load share, Dallas Fed WP 2606r1, third party estimate.
Fixed cost share of retail electricity bill
68.4 percent (s = 0.684), retail pass through parameter, Dallas Fed WP 2606r1, third party estimate.

States in SERC Virginia and Carolina South

Tracked facilities in SERC Virginia and Carolina South (46)

Facility State Place Stage Stated power
300 Jones Road Data Center SC Spartanburg, Spartanburg County proposed
Aiken 5 MW Data Center SC Aiken, Aiken County running 5 MW
Amazon Web Services Richmond County Data Center Campus NC Hamlet, Richmond County being built 1 GW
Amentum / DC Blox Savannah River AI Data Center SC Aiken, Aiken County approved 1 GW
American Tower Raleigh Data Center (RA1) NC Raleigh, Wake County running 2 MW
Apple Maiden Data Center NC Maiden, Catawba County running 150 MW
Cherokee County Data Center SC Gaffney, Cherokee County approved
CyrusOne Durham DUR1 and DUR2 NC Durham, Durham County running 12 MW
Dacentec Lenoir Data Center NC Lenoir, Caldwell County running 5 MW
DartPoints Charleston Data Center (CHS1) SC Ladson, Charleston County running 4 MW
DartPoints Columbia Data Center (CAE1) SC Columbia, Richland County running 4 MW
DartPoints Greenville Data Center (GSP1) SC Greenville, Greenville County running 4 MW
DartPoints Spartanburg Data Center (SPA1) SC Spartanburg, Spartanburg County running 4 MW
DC BLOX Greenville Data Center (GSP1) SC Greenville, Greenville County running 9 MW
DC BLOX Myrtle Beach Cable Landing Station (MYR1) SC Myrtle Beach, Horry County running 15 MW
DC74 Data Centers Charlotte (CLT1) NC Charlotte, Mecklenburg County running 5 MW
DC74 Data Centers Charlotte South (CLT4) NC Charlotte, Mecklenburg County running 5 MW
Digital Realty Charlotte NC Charlotte, Mecklenburg County running 6 MW
Eagle Rock Partners Colleton County Data Center SC Walterboro, Colleton County proposed 1 GW
Energy Storage Solutions Edgecombe County AI Data Center NC Edgecombe County proposed 900 MW
Flexential Charlotte North (CLT4 and CLT5) NC Charlotte, Mecklenburg County running 12 MW
Flexential Charlotte South (CLT1, CLT2, and CLT3) NC Charlotte, Mecklenburg County running 9 MW
Flexential Raleigh (RAL01, RAL02, and RAL03) NC Morrisville, Wake County running 11 MW
Google Berkeley County data center SC Moncks Corner, Berkeley County running 200 MW
Google Dorchester County data center SC Ridgeville, Dorchester County being built 150 MW
Google Lenoir data center NC Lenoir, Caldwell County running 150 MW
H5 Charlotte NC Charlotte, Mecklenburg County running 12 MW
Hilton Head Area Data Centers SC Bluffton, Beaufort County proposed
Historic Charlotte building site data center NC Charlotte, Mecklenburg County proposed
Inflow Data Center NC Durham, Durham County running 4 MW
IWS Anderson Data Center Project Phase 2 SC Anderson, Anderson County running 15 MW
CyrusOne Lee County Data Center NC Sanford, Lee County approved
Meta Aiken Data Center SC Aiken, Aiken County running 150 MW
Meta Forest City Data Center NC Forest City, Rutherford County running 150 MW
Microsoft Mega Park Person County NC Woodsdale Township, Person County approved
DartPoints Asheville Data Center (AVL1) NC Asheville, Buncombe County running 6 MW
NorthMark Spartanburg County Data Center SC Spartanburg, Spartanburg County being built 457 MW
Project Liberty Marion County Data Center SC Marion, Marion County approved
QTS York County SC Rock Hill, York County being built 300 MW
Segra Kannapolis Data Center NC Kannapolis, Cabarrus County running 4 MW
Southeast Raleigh data center NC Raleigh, Wake County cancelled
T5 Data Centers Charlotte (Kings Mountain) NC Kings Mountain, Cleveland County running 28 MW
TierPoint Charlotte NC Charlotte, Mecklenburg County running 10 MW
TierPoint Research Triangle Park (RTP) NC Durham, Durham County running 14 MW
TierPoint Raleigh NC Raleigh, Wake County running 5 MW
Sce&g Irmo Data Center SC Irmo, Lexington County not yet verified

A blank cell means no source states a figure.

All 23 regional markets in Dallas Fed WP 2606r1

Region States Tracked records (CC BY-NC 4.0) 2024 to 2025 wholesale price effect 2028 projected wholesale price effect
Northwest Power Pool (NWPP) WA, OR, ID, MT, NV, UT 105 15.4 percent (+$5.68 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 25.9 percent (+$7.77 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Virginia and Carolina North (SRVC-N) VA, NC 55 15.0 percent (+$5.22 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 27.6 percent (+$9.76 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC California (CAMX) CA 69 8.6 percent (+$3.70 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 17.2 percent (+$6.96 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
MRO West (MROW) IA, MN, ND, NE, SD 76 12.1 percent (+$3.45 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 15.7 percent (+$4.59 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
ERCOT All (ERCT) TX 67 12.6 percent (+$3.15 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 28.0 percent (+$6.10 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Virginia and Carolina South (SRVC-S) NC, SC 46 7.5 percent (+$3.01 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 14.7 percent (+$4.94 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC Southwest (AZNM) AZ, NM 41 8.6 percent (+$2.93 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 14.7 percent (+$4.32 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
WECC Rockies (RMPA) CO, WY 42 7.7 percent (+$2.51 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 12.2 percent (+$3.76 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC NYC and Westchester (NYCW) NY 13 5.2 percent (+$2.46 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 6.0 percent (+$2.63 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC Long Island (NYLI) NY 4 4.5 percent (+$2.40 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 5.3 percent (+$2.62 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC West (RFCW) IN, OH, PA, WV, IL 134 6.7 percent (+$2.29 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 15.7 percent (+$5.11 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC Upstate New York (NYUP) NY 15 5.3 percent (+$2.14 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.7 percent (+$3.34 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Tennessee Valley (SRTV) KY, TN 27 5.8 percent (+$2.03 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.7 percent (+$2.91 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SPP North (SPNO) KS, NE, MO 8 6.5 percent (+$1.87 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.2 percent (+$2.54 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC East (RFCE) DC, DE, MD, NJ, PA 127 5.1 percent (+$1.81 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 13.3 percent (+$4.61 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC South (SRSO) AL, GA 51 4.2 percent (+$1.47 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 5.3 percent (+$1.73 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Midwest (SRMW) IL, MO 28 4.7 percent (+$1.46 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 7.0 percent (+$2.28 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
MRO East (MROE) WI, MI 22 4.0 percent (+$1.39 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 7.9 percent (+$2.60 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
NPCC New England (NEWE) CT, MA, ME, NH, RI, VT 34 2.4 percent (+$1.28 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 3.1 percent (+$1.71 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
RFC Michigan (RFCM) MI 25 3.8 percent (+$1.27 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 8.8 percent (+$2.89 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SPP South (SPSO) OK, AR, LA, TX 16 3.1 percent (+$0.99 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 3.5 percent (+$1.12 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
SERC Mississippi Valley (SRMV) AR, LA, MS 26 3.0 percent (+$0.93 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 4.7 percent (+$1.48 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.
FRCC All (FRCC) FL 33 1.0 percent (+$0.42 per MWh, 2024 to 2025), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate. 0.8 percent (+$0.34 per MWh, 2028 projected), modeled wholesale price effect, Dallas Fed WP 2606r1, third party estimate.

Wholesale price effects are third party estimates from Dallas Fed WP 2606r1 (opens in a new tab) (March 2026, revised October 2026). Tracked record counts are Data Center Record rows licensed under CC BY-NC 4.0.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

What researchers have found

These studies measure different things. Some model wholesale market prices. Some measure what households actually paid. Some model what would happen under a policy change. The record shows each one as the authors stated it and does not rank them.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.