Data Center Record.

Being built Built from one source

Amazon Web Services Richmond County Data Center Campus

Hamlet, Richmond County, NCDeveloper: Amazon Web ServicesCensus GEOID 37153

Stage
Being built
Power
1 GW
the developer's figure
Buildings
20 buildings
zoning application, verified October 27, 2026
Undisclosed in public filings
Land, Water

Amazon Web Services is constructing a 20 building data center campus at the Energy Way Industrial Park in Hamlet, Richmond County, North Carolina, after receiving North Carolina Department of Environmental Quality air quality permits in September 2026. It is being built; the record holds no sourced date for when it reached that stage.

How much water it would use and who would use it have not been disclosed.

Last verified · 3 sources, 0 primary · Built from one source, not yet reviewed in depth by a person. · How to read this page

  • This record: Being built, ringed
  • data center
  • Smaller pins: 25 other published records in North Carolina
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Buildings
20 buildings zoning application, verified October 27, 2026
Power it would draw
1 GW the developer's figure About 10 percent of New York City's summer peak demand in 2024.
Who leads it
Amazon Web Services as stated by the source
Undisclosed in public filings
Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. Amazon Web Services Richmond County Data Center Campus, capacity: 1,000 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 1,000 ÷ 10,245 = 0.1 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 1 GW the developer's figure deq.nc.gov (opens in a new tab) October 27, 2026
How much water it would use
How loud it would be
Jobs once it runs
Tax it would pay each year

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Amazon Web Services as stated by the source October 27, 2026
Who is constructing it
How much land
Buildings 20 buildings zoning application, verified October 27, 2026 deq.nc.gov (opens in a new tab) October 27, 2026
Where its power comes from
Grid connection
How it is cooled

How much power it needs, also reported: 255 MW, 2026 (WRAL (opens in a new tab): Duke proposed adding a turbine capable of generating about 255 megawatts of electricity by 2030) .

A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What happened

  1. · Status: permitting (content date)

    Amazon's North Carolina data center sought and received state approval for diesel generator permits amid community pushback over the use of diesel power.

    deq.nc.gov (opens in a new tab) query feed

The full Amazon Web Services Richmond County Data Center Campus timeline, in order

1 correction to this record

Every correction, with its reason

Every correction on the record is on the corrections page.

The site

The pin is the site. The shaded outline is the parcel, from the county's own parcel record.

The site map is at the top of the page.

Where
Energy Way, Hamlet, NC 28345, Hamlet, Richmond County, North Carolina [source] (opens in a new tab)
How exactly it is located
Exact, on the parcel
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
By the straight line between two exact points.

USGS NAIP aerial view of Amazon Web Services Richmond County Data Center Campus
LAT 34.88920 / LON -79.71061 Imagery: U.S. Geological Survey / USDA NAIP (Public Domain)

Comparisons

1 metric with more than one figure

Every figure on the record for the same thing, the record's own or the document's first, each with who gave it, its date and its basis.

Capacity at full buildout

2 figures, 2 sources
Show each source's words
  • 255 MW, WRAL: Duke proposed adding a turbine capable of generating about 255 megawatts of electricity by 2030

Questions about this project

7 questions answered from the record

Answered from the rows on this page.

How big is Amazon Web Services Richmond County Data Center Campus?

The record has 2 measures of its size: 1 GW (the developer's figure, deq.nc.gov (opens in a new tab)) and 20 buildings (zoning application, verified October 27, 2026, deq.nc.gov (opens in a new tab)). Its acreage is not disclosed.

Who is building Amazon Web Services Richmond County Data Center Campus?

Amazon Web Services is the developer. No construction contractor is named on the record yet.

Who will use Amazon Web Services Richmond County Data Center Campus?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Amazon Web Services Richmond County Data Center Campus say it needs?

Power: 1 GW (the developer's figure, deq.nc.gov (opens in a new tab)). Water: not disclosed by any source on file.

Where does Amazon Web Services Richmond County Data Center Campus stand today?

It is being built; the date it reached that stage is not sourced, only the day a page was read. The newest entry, September 1, 2026: Amazon's North Carolina data center sought and received state approval for diesel generator permits amid community pushback over the use of diesel power.

What has Hamlet or Richmond County decided about it?

No decision by Hamlet or Richmond County about data centers is on the record. The Richmond County page and the North Carolina scorecard list every rated row the day a person publishes one.

What is still unknown about Amazon Web Services Richmond County Data Center Campus?

Not disclosed by any source on file: how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. North Carolina approves diesel generator permits for Amazon data center - WRAL (opens in a new tab), WRAL, September 1, 2026, local outlet
  2. An Amazon data center in NC wants to use diesel power. Why there’s pushback - Raleigh News & Observer (opens in a new tab), Raleigh News & Observer, August 8, 2026, local outlet
  3. Amazon Data Center Slated for NC Town With Devastating Industrial History - sentientmedia.org (opens in a new tab), sentientmedia.org, August 4, 2026, news outlet

3 sources on file.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Amazon Web Services Richmond County Data Center Campus", https://datacenterrecord.org/projects/amazon-data-center-nc-nc, last verified October 27, 2026. CSV · JSON
Cite this page

Data Center Record, "Amazon Web Services Richmond County Data Center Campus", https://datacenterrecord.org/projects/amazon-data-center-nc-nc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Stage
Being built
Tier
built from one source
Tags
Built from one source
Coordinates
34.8892, -79.71061
How the location is known
Location from the county parcel record.
Location source
https://www.deq.nc.gov/about/divisions/air-quality
Coordinate source
NC DEQ Division of Air Quality generator permit and Richmond County Energy Way Industrial Park record
How capacity was disclosed
the developer's figure
Capacity, if disclosed
1 GW, the developer's figure
Published
September 4, 2026
Last verified
October 27, 2026
Undisclosed in public filings
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · Amazon Web Services Richmond County Data Center Campus · 3 sources, 1 entry, 0 decisions nearby · basis and source tier on every row · verified October 27, 2026

Download CSV JSON