Data Center Record.

Data centers in North Carolina

North Carolina has 10 data center sites, 0 buildings where disclosed on the record: 6 running, 3 proposed and 1 stalled or cancelled. Most are in Mecklenburg County (4) and Wake County (2), and records are in 6 of 100 counties. The largest proposal is CyrusOne Durham DUR1-DUR2 in Durham County; it is reported.

North Carolina decides case by case. From the state's own rule: North Carolina Senate Bill 730 (Ratepayer Protection Act) defines data centers as facilities with peak monthly electricity demand of 100 megawatts or greater and passed state house 69-44, August 24, 2026.

1 site the EPA's registry shows and no record has verified is on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
CyrusOne Durham DUR1-DUR2 Durham, Durham CountyProposedCyrusOne
Historic Charlotte building site data center Charlotte, Mecklenburg CountyProposed In courtThe Court Arcade was demolished this past week to make way for a three story 29,000 square foot data center wbtv.com (opens in a new tab) local outlet reported September 7, 2026
Lee County data center Lee CountyProposedA proposed 90 megawatt data center is planned near Cumnock on Lower Moncure Road with plans to drill beneath Deep River rantnc.com (opens in a new tab) local outlet reported August 18, 2026
Meta Forest City Data Center Forest City, Rutherford CountyRunningMeta
Digital Realty Charlotte Charlotte, Mecklenburg CountyRunningDigital Realty
H5 Charlotte Charlotte, Mecklenburg CountyRunningH5 Data Centers
TierPoint Charlotte Charlotte, Mecklenburg CountyRunningTierPoint
TierPoint Raleigh Raleigh, Wake CountyRunningTierPoint
Southeast Raleigh data center Raleigh, Wake CountyStalled or cancelledBeacon Partners withdrew its proposal to build a data center on Jones Sausage Road wral.com (opens in a new tab) local outlet reported August 17, 2026
Google Lenoir data center Lenoir, Caldwell CountyRunningGoogleGoogle bought more land at Lenoir data center datacenterknowledge.com (opens in a new tab) trade press reported May 30, 2024

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 10 North Carolina projects.

Every North Carolina record 10 records, and 1 site not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Inflow Data CenterDurham, DurhamNot yet verifiedEPA registry22026-10-20
Meta Forest City Data CenterForest City, RutherfordRunningMetasite22026-10-04
CyrusOne Durham DUR1-DUR2Durham, DurhamProposedCyrusOnecentroid22026-09-17
Digital Realty CharlotteCharlotte, MecklenburgRunningDigital Realtycentroid22026-09-17
H5 CharlotteCharlotte, MecklenburgRunningH5 Data Centerscentroid12026-09-17
TierPoint CharlotteCharlotte, MecklenburgRunningTierPointcentroid22026-09-17
TierPoint RaleighRaleigh, WakeRunningTierPointcentroid22026-09-17
Historic Charlotte building site data centerCharlotte, MecklenburgProposedcentroid42026-09-17
Lee County data centerLeeProposedcentroid42026-09-17
Southeast Raleigh data centerRaleigh, WakeStalled or cancelledcentroid12026-10-06
Google Lenoir data centerLenoir, CaldwellRunningGoogleEPA registry22026-10-04

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every North Carolina county (100)

6 of 100 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRulesHow it treats data centers
Mecklenburg County3711941
Wake County3718322
Caldwell County3702710
Durham County3706311
Lee County3710511case by case
Rutherford County3716110
Alamance County3700101
Avery County3701101
Brunswick County3701903
Buncombe County3702101restrictive
Carteret County3703101
Chatham County3703701restrictive
Greene County3707901
Guilford County3708102
Haywood County3708701restrictive
Henderson County3708901
Jackson County3709901restrictive
Macon County3711301restrictive
McDowell County3711101restrictive
New Hanover County3712901
Stokes County3716901
Swain County3717301restrictive
Transylvania County3717501
Union County3717901

A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.

76 counties with no records yet
  • Alexander County
  • Alleghany County
  • Anson County
  • Ashe County
  • Beaufort County
  • Bertie County
  • Bladen County
  • Burke County
  • Cabarrus County
  • Camden County
  • Caswell County
  • Catawba County
  • Cherokee County
  • Chowan County
  • Clay County
  • Cleveland County
  • Columbus County
  • Craven County
  • Cumberland County
  • Currituck County
  • Dare County
  • Davidson County
  • Davie County
  • Duplin County
  • Edgecombe County
  • Forsyth County
  • Franklin County
  • Gaston County
  • Gates County
  • Graham County
  • Granville County
  • Halifax County
  • Harnett County
  • Hertford County
  • Hoke County
  • Hyde County
  • Iredell County
  • Johnston County
  • Jones County
  • Lenoir County
  • Lincoln County
  • Madison County
  • Martin County
  • Mitchell County
  • Montgomery County
  • Moore County
  • Nash County
  • Northampton County
  • Onslow County
  • Orange County
  • Pamlico County
  • Pasquotank County
  • Pender County
  • Perquimans County
  • Person County
  • Pitt County
  • Polk County
  • Randolph County
  • Richmond County
  • Robeson County
  • Rockingham County
  • Rowan County
  • Sampson County
  • Scotland County
  • Stanly County
  • Surry County
  • Tyrrell County
  • Vance County
  • Warren County
  • Washington County
  • Watauga County
  • Wayne County
  • Wilkes County
  • Wilson County
  • Yadkin County
  • Yancey County

The rules in North Carolina 27 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
North Carolinastatecase by caseNorth Carolina Senate Bill 730 (Ratepayer Protection Act) defines data centers as facilities with peak monthly electricity demand of 100 megawatts or greater and passed state house 69-44. newsargus.com (opens in a new tab) local outlet Aug 24, 202610 acts on this row
Every act on the North Carolina row
  1. denial

    North Carolina Utilities Commission rejected Duke Energy permit for 255MW gas power plant in Richmond County, citing uncertain data center demand and conflict with ratepayer protection pledge.

    canarymedia.com (opens in a new tab) trade press

    Also reported by 1 source
  2. event

    Senate Bill 730 (Ratepayer Protection Act) passed the House 69-44 with support from only two Democrats and two independents formerly Democrats

    wakeweekly.com (opens in a new tab) news outlet

  3. rate rule

    Attorney General Jeff Jackson filed a proposal with the North Carolina Utilities Commission to create a separate rate class for data centers and other exceptionally large users of electricity

    nsjonline.com (opens in a new tab) local outlet

    Also reported by 1 source
  4. event

    North Carolina State Historic Preservation Office recommended a protective buffer of around 100 feet for cemeteries on the Burnette Road site

    witn.com (opens in a new tab) local outlet

  5. denial

    North Carolina Utilities Commission voted 3-1 on September 18 to deny Duke Energy Progress a certificate of public convenience and necessity for a 255 megawatt gas fired peaker turbine at the Smith Energy Complex in Richmond County.

    marcellusdrilling.com (opens in a new tab) news outlet

  6. denial

    North Carolina regulators denied Duke Energy's $584 million gas turbine proposal near Hamlet

    wral.com (opens in a new tab) local outlet

  7. moratorium

    47 local governments in North Carolina adopted moratoriums on approving new data centers as of September 9, 2026

    cardinalpine.com (opens in a new tab) local outlet

  8. event

    North Carolina Division of Air Quality issued air quality permits for backup power generation and Duke Energy generators

    wunc.org (opens in a new tab) local outlet

  9. event

    North Carolina House passed bill to crack down on data centers

    wral.com (opens in a new tab) local outlet

  10. event

    House Republican proposal stalled in Senate in June, included study to recommend new rate class

    reflector.com (opens in a new tab) local outlet

Last verified September 24, 2026.

102026-09-24
Alamance Countycountynot ratedAlamance County commissioners approved a 1 year data center moratorium. myfox8.com (opens in a new tab) news outlet Reported Aug 171 act on this row
Every act on the Alamance County row
  1. moratorium adopted

    Alamance County commissioners approved a 1 year data center moratorium

    myfox8.com (opens in a new tab) news outlet

Last verified August 17, 2026.

12026-08-17
Avery Countycountynot ratedAvery County Commissioners postponed a public hearing on a proposed moratorium on data centers, cryptocurrency mining and similar uses because the county missed advertising requirements. averyjournal.com (opens in a new tab) news outlet Oct 51 act on this row
Every act on the Avery County row
  1. moratorium

    Avery County Commissioners postponed a public hearing on a proposed moratorium on data centers, cryptocurrency mining and similar uses because the county missed advertising requirements

    averyjournal.com (opens in a new tab) news outlet

Last verified October 5, 2026.

12026-10-05
BrevardcityrestrictiveBrevard adopted permanent zoning regulations governing data center development instead of a temporary moratorium. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Brevard row
  1. moratorium adopted

    Brevard adopted permanent zoning regulations governing data center development instead of a temporary moratorium

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Brunswick Countycountynot ratedNo dated act on this row yet.2026-08-24
Buncombe Countycountyrestrictive until September 15, 20272027-09-15Buncombe County and Asheville adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Buncombe County row
  1. moratorium adopted

    Buncombe County and Asheville adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Carycitynot ratedCary approved an 18 month moratorium on data centers. abc11.com (opens in a new tab) local outlet Reported Aug 282 acts on this row
Every act on the Cary row
  1. moratorium adopted

    Cary approved an 18 month moratorium on data centers

    abc11.com (opens in a new tab) local outlet

  2. moratorium adopted

    Cary, NC adopted a data center pause or moratorium

    govtech.com (opens in a new tab) national outlet

Last verified August 28, 2026.

22026-08-28
Charlottecityrestrictive until February 1, 20272027-02-01Charlotte Water imposed a 150 day moratorium on new data center applications in June while officials study infrastructure capacity and environmental concerns. yahoo.com (opens in a new tab) national outlet Sep 4, 20264 acts on this row
Every act on the Charlotte row
  1. moratorium

    Charlotte City Council held a public hearing on October 14, 2026 ahead of an October 26 vote to extend the city's 150 day data center moratorium by up to 11 months

    bisnow.com (opens in a new tab) trade press

  2. moratorium adopted

    Charlotte enacted its 150 day moratorium in June 2026 following local outcry against data centers

    bisnow.com (opens in a new tab) trade press

  3. moratorium adopted

    Charlotte Water imposed a 150 day moratorium on new data center applications in June while officials study infrastructure capacity and environmental concerns

    yahoo.com (opens in a new tab) national outlet

  4. event

    Data center zoning decision was made off I-85 in Charlotte area

    charlotteobserver.com (opens in a new tab) local outlet

Last verified October 14, 2026.

42026-10-14
Chatham CountycountyrestrictiveChatham County enacted a moratorium on new data centers in February 2026. law360.com (opens in a new tab) news outlet Sep 18, 20263 acts on this row
Every act on the Chatham County row
  1. moratorium rejected

    A state judge rejected the one year moratorium on new data center projects

    law360.com (opens in a new tab) trade press

  2. moratorium adopted

    Chatham County enacted a one year moratorium on new data center projects in February

    law360.com (opens in a new tab) trade press

  3. moratorium

    Superior Court Judge John Morris awarded summary judgment to Eco TIP West, ruling the developer has vested property rights in its data center project despite the county moratorium enacted in February 2026.

    law360.com (opens in a new tab) news outlet

Last verified September 18, 2026.

32026-09-18
Durham Countycountynot ratedDurham County voted for a pause on data centers. govtech.com (opens in a new tab) national outlet Reported Aug 252 acts on this row
Every act on the Durham County row
  1. moratorium

    Durham County voted for a pause on data centers

    govtech.com (opens in a new tab) national outlet

    Also reported by 1 source
  2. moratorium adopted

    Durham County adopted a 9 month pause on data centers

    wral.com (opens in a new tab) local outlet

Last verified August 26, 2026.

22026-08-26
Greene Countycountynot ratedNo dated act on this row yet.2026-09-18
Greensborocitynot ratedNo dated act on this row yet.2026-08-18
Guilford Countycountynot ratedStaff recommended a text amendment to define county rules surrounding data centers and establish standards and regulations. yahoo.com (opens in a new tab) national outlet Reported Sep 172 acts on this row
Every act on the Guilford County row
  1. event

    Staff recommended a text amendment to define county rules surrounding data centers and establish standards and regulations

    yahoo.com (opens in a new tab) national outlet

  2. hearing

    County staff gave commissioners an overview of data center development covering land use, infrastructure, utilities, economic development and policy options on September 17, 2026

    yahoo.com (opens in a new tab) national outlet

Last verified September 17, 2026.

22026-09-17
Haywood Countycountyrestrictive until September 15, 20272027-09-15Haywood County and Canton adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Haywood County row
  1. moratorium adopted

    Haywood County and Canton adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Hendersonvillecityrestrictive until September 15, 20272027-09-15Hendersonville adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Hendersonville row
  1. moratorium adopted

    Hendersonville adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Jackson Countycountyrestrictive until September 15, 20272027-09-15Jackson County adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Jackson County row
  1. moratorium adopted

    Jackson County adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Lee Countycountycase by caseLee County commissioners signed off on changes to permit data centers in light industrial zones. thecooldown.com (opens in a new tab) national outlet Aug 27, 20266 acts on this row
Every act on the Lee County row
  1. moratorium

    Opponents requested county enact data center moratorium and adopt changes to Unified Development Ordinance

    rantnc.com (opens in a new tab) local outlet

  2. moratorium

    Citizens opposed to a proposed data center on Lower Moncure Road requested Lee County Board of Commissioners place moratorium and UDO amendment discussions on the meeting agenda

    rantnc.com (opens in a new tab) local outlet

  3. event

    Lee County commissioners signed off on changes to permit data centers in light industrial zones

    thecooldown.com (opens in a new tab) national outlet

  4. statement

    More than 150 residents attended a Lee County Board of Commissioners meeting on August 18, 2026 to oppose a proposed data center facility on Lower Moncure Road

    rantnc.com (opens in a new tab) local outlet

  5. moratorium

    Eric Davidson, a newly appointed Republican commissioner, offered a motion to impose a 90 day moratorium on new data centers but withdrew it after County Attorney Whitney Parrish advised commissioners lacked authority to enact a moratorium without following state mandated procedures

    rantnc.com (opens in a new tab) local outlet

  6. event

    Lee County Board of Commissioners rejected a resolution urging the North Carolina General Assembly to research and enact legislation for data centers

    rantnc.com (opens in a new tab) local outlet

Last verified September 18, 2026.

62026-09-18
Macon Countycountyrestrictive until September 15, 20272027-09-15Macon County and the Town of Franklin adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Macon County row
  1. moratorium adopted

    Macon County and the Town of Franklin adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
McDowell Countycountyrestrictive until March 11, 20272027-03-11McDowell County approved six month moratorium on data center development. carolinacoastonline.com (opens in a new tab) local outlet Sep 11, 20261 act on this row
Every act on the McDowell County row
  1. moratorium adopted

    McDowell County approved six month moratorium on data center development

    carolinacoastonline.com (opens in a new tab) local outlet

Last verified September 11, 2026.

12026-09-11
New Hanover Countycountynot ratedNo dated act on this row yet.2026-09-23
NewportcityrestrictiveNewport approves a moratorium on data center development. witn.com (opens in a new tab) local outlet Sep 16, 20261 act on this row
Every act on the Newport row
  1. moratorium adopted

    Newport approves a moratorium on data center development

    witn.com (opens in a new tab) local outlet

Last verified September 16, 2026.

12026-09-16
Raleighcitynot ratedRaleigh enacted a data center moratorium just last week. bisnow.com (opens in a new tab) trade press Oct 11 act on this row
Every act on the Raleigh row
  1. moratorium adopted

    Raleigh enacted a data center moratorium just last week

    bisnow.com (opens in a new tab) trade press

Last verified October 1, 2026.

12026-10-01
Shallottecitycase by caseShallotte adopted unified development ordinance amendment in January limiting data center uses to Heavy Industrial zoning district. newsargus.com (opens in a new tab) local outlet Aug 24, 20261 act on this row
Every act on the Shallotte row
  1. ordinance

    Shallotte adopted unified development ordinance amendment in January limiting data center uses to Heavy Industrial zoning district

    newsargus.com (opens in a new tab) local outlet

Last verified August 24, 2026.

12026-08-24
Southportcityclosed until December 11, 20272027-12-11Southport Board of Aldermen unanimously approved a 15 month moratorium on new data center approvals. wwaytv3.com (opens in a new tab) local outlet Sep 11, 20261 act on this row
Every act on the Southport row
  1. moratorium adopted

    Southport Board of Aldermen unanimously approved a 15 month moratorium on new data center approvals

    wwaytv3.com (opens in a new tab) local outlet

Last verified September 11, 2026.

12026-09-11
Stokes Countycountynot ratedStokes County commissioners voted 3-2 to move forward with a rezoning proposal for a hyperscale data center. wxii12.com (opens in a new tab) local outlet Reported Sep 172 acts on this row
Every act on the Stokes County row
  1. event

    Stokes County commissioners voted 3-2 to move forward with a rezoning proposal for a hyperscale data center

    wxii12.com (opens in a new tab) local outlet

  2. approval

    Stokes County commissioners voted three to two on September 14 to approve rezoning for Walnut Cove area data center proposed by Engineered Land Solutions

    thestokesnews.com (opens in a new tab) news outlet

Last verified September 17, 2026.

22026-09-17
Swain Countycountyrestrictive until September 15, 20272027-09-15Swain County adopted a one year moratorium on data center development. wlos.com (opens in a new tab) local outlet Sep 15, 20261 act on this row
Every act on the Swain County row
  1. moratorium adopted

    Swain County adopted a one year moratorium on data center development

    wlos.com (opens in a new tab) local outlet

Last verified September 15, 2026.

12026-09-15
Waxhawcitynot ratedTown of Waxhaw unanimously approved a 12 month moratorium on data centers. wbtv.com (opens in a new tab) local outlet Reported Aug 121 act on this row
Every act on the Waxhaw row
  1. moratorium adopted

    Town of Waxhaw unanimously approved a 12 month moratorium on data centers

    wbtv.com (opens in a new tab) local outlet

Last verified August 12, 2026.

12026-08-12

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

North Carolina laws and the full scorecard

Bills and laws in North Carolina

none signed into law yet, 2 bills tracked

2 bills tracked in the North Carolina legislature, none signed into law yet, grouped by where each stands. A row opens its own page; the North Carolina laws page has what each law requires.

No official summary on file for any of these 2 measures; each row links to the legislature's page for the text.

In committee 2

2 bills tracked, 0 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
S. 1026 2025-2026 Session In committee 2026-05-05 Power Bill Protection/Large Load Tariff
H. 1180 2025-2026 Session In committee 2026-05-04 Data Center Amendments

2 bills tracked in North Carolina; 2025-2026 Session, legislature in session; last checked October 26, 2026. The last check found no bill not already tracked; the 2 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. North Carolina's members: 14 yea, 0 nay. How each member voted

MemberPartyPosition
AdamsDYea
Davis (NC)DYea
EdwardsRYea
FousheeDYea
FoxxRYea
HarriganRYea
Harris (NC)RYea
HudsonRYea
KnottRYea
McDowellRYea
Moore (NC)RYea
MurphyRYea
RossDYea
RouzerRYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. North Carolina's members: 2 yea, 0 nay. How each member voted

MemberPartyPosition
Budd (R-NC)RYea
Tillis (R-NC)RYea

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

  1. Moratorium adoptedRaleigh

    Raleigh enacted a data center moratorium just last week

The full North Carolina timeline, year by year

What was said

Governor Josh Stein said the Duke Energy data centre tariff agreement needs more work on transparency and terms ensuring data centres pay for all infrastructure upgrades needed to power them.
Josh Stein, North Carolina governor · October 14, 2026 · paraphrased · WFDD (opens in a new tab) local outlet · also reported by 1 more source
Sam Altman, OpenAI CEO, compared rejecting AI to rejecting electricity, calling AI adoption essential for economic growth.
Sam Altman, OpenAI CEO · September 3, 2026 · paraphrased · ETV Bharat (opens in a new tab) news outlet

Every North Carolina statement, by speaker (74)

70 more on this page, one per speaker and claim; 74 statements in all
"A single hyperscale data center can consume resources needed for 100,000 households. Rising cost of water and electricity are the most significant concerns voters have expressed."
Mona Singh, Policy advocate, <UNKNOWN> Cardinal & Pine article Cardinal & Pine (opens in a new tab) local outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Cardinal & Pine article.

Primary source: Cardinal & Pine (opens in a new tab).

"Hyperscale data centers and fossil fuel infrastructure require large quantities of water to cool the facilities, putting a strain on aquatic life and our drinking water sources. This year's drought and low water levels highlight the vulnerability of water quantity."
Nicole Eastman, Yadkin Riverkeeper, Yadkin Riverkeepers Rowan County commission meeting Salisbury Post (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Rowan County commission meeting.

Primary source: Salisbury Post (opens in a new tab).

North Carolina Attorney General Jeff Jackson said Duke Energy's data centre tariff agreement is a massive step forward in ensuring data centres pay their fair share.

Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: WFDD (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Also reported by: WUNC News (opens in a new tab) local outlet .

John Szoka, CEO of Conservative Energy Network and former member of the North Carolina House of Representatives, said data centers represent enormous private investment, substantial new tax base, construction and skilled trade jobs, and that North Carolina became strong for business by looking forward

The North State Journal (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The North State Journal (opens in a new tab).

President Donald Trump said communities should want data center investments when they are placed in appropriate locations and their impacts including power, sound and water are properly addressed, and that developers should provide or finance additional electricity infrastructure rather than shifting costs to existing ratepayers

Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: The North State Journal (opens in a new tab).

Archived copy: Wayback Machine (opens in a new tab).

Murphy said he also supports development of data centers, saying they are needed to keep the United States a global leader in the development of artificial intelligence.

Republican candidate for U.S. House (District 3), North Carolina reflector.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: reflector.com (opens in a new tab).

Chuck Hubbard, Democratic Congressional candidate, said a two year moratorium could help ensure environmentally safe data center development and that data centers put forever chemicals in waterways, raise electric bills, and produce noise pollution

Ashe Post & Times (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Ashe Post & Times (opens in a new tab).

Munashe Magarira, senior attorney at the Southern Environmental Law Center, said Duke's build out plan calls for a 'staggering amount' of new, polluting gas plants, with the collective maximum output of 12 gas plants approximately 9,850 megawatts.

journalnow.com (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: journalnow.com (opens in a new tab).

Michael Whatley and his family hold between $246,000 and $690,000 in energy investments with companies fueling data center growth

Fox News article Fox News (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Fox News (opens in a new tab).

Whatley and his family have holdings between $149,000 and $410,000 in Duke Energy

Fox News article Fox News (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Fox News (opens in a new tab).

Whatley reported $361,000 from CAPCVentures LLC for consulting services in 2025

Fox News article Fox News (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Fox News (opens in a new tab).

Republican commissioners William Brawley, Tommy Tucker, and Donald van der Vaart rejected the project because Duke Energy failed to demonstrate how it would adhere to the Ratepayer Protection Pledge

Tommy Tucker, and Donald van der Vaart, North Carolina Utilities Commissioners foreignpolicyjournal.com (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: foreignpolicyjournal.com (opens in a new tab).

Will Scott, Environmental Defense Fund North Carolina policy director, said commission approval of fossil fuel Duke proposals have been foregone conclusion but this rejection was surprising.

Canary Media (opens in a new tab) trade press
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Canary Media (opens in a new tab).

Gov. Josh Stein calling on state utility regulators to codify data center energy promises made by Duke Energy to ensure data centers do not result in higher electricity bills for North Carolina families.

North Carolina Governor thegazette.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: thegazette.com (opens in a new tab).

Harold Weinbrecht, Cary mayor, stated the moratorium will allow staff time to conduct a technical study, engage with community, and develop ordinance addressing data centers

mayor of Cary WUNC News (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WUNC News (opens in a new tab).

Jane Harrison, Raleigh Mayor Pro Tem, wants city to alert residents and council when large data center proposals come before board

WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

Sarika Bansal, Cary councilwoman, stated the moratorium will give the town time to understand how data center development could affect residents, infrastructure and local resources

WUNC News (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WUNC News (opens in a new tab).

Lori Bush, Cary Mayor Pro Tem, cited high electricity demand, cooling related water use, noise from cooling equipment and backup generators, and large building footprints as potential impacts from data centers

Mayor Pro Tem, Cary Town Council WUNC News (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WUNC News (opens in a new tab).

Anderson Clayton, North Carolina Democratic Party Chair, stated Michael Whatley has investments in Duke Energy and companies pushing for data centers, and that Duke Energy is pushing for higher utility prices.

Cardinal & Pine (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Cardinal & Pine (opens in a new tab).

Janet Cowell, Raleigh Mayor, calls for careful approach and pause to have conversation and lower temperature on data center issue

WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

North Carolina Democrats held a press conference calling on U.S. Senate candidate Michael Whatley to sell his investments in data center companies

Anderson Clayton and Natalie Murdock, North Carolina Democratic Party Yahoo (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Yahoo (opens in a new tab).

Duke Energy seeks to raise utility rates in North Carolina by around $15 per month by summer 2028

Anderson Clayton, North Carolina Democratic Party Chair Cardinal & Pine (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Cardinal & Pine (opens in a new tab).

Jeff Jackson, North Carolina Attorney General, urges Utilities Commission to create new rate class for Duke Energy data center customers

journalnow.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: journalnow.com (opens in a new tab).

Also reported by: NC Newsline (opens in a new tab) local outlet , RTO Insider (opens in a new tab) trade press .

Said again: September 17, 2026 ( RTO Insider (opens in a new tab) trade press ).

Jackson proposed that Duke Energy make energy load forecasts every 90 days instead of every six months

North Carolina Attorney General NC Newsline (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NC Newsline (opens in a new tab).

Also reported by: journalnow.com (opens in a new tab) local outlet , The North State Journal (opens in a new tab) local outlet .

Said again: September 19, 2026 ( The North State Journal (opens in a new tab) local outlet ).

Jeff Jackson, NC Attorney General, calls on state regulators to establish distinct utility rate class for Duke Energy data centers to prevent costs shifting to residential customers

North Carolina Attorney General WECT (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WECT (opens in a new tab).

Jackson requested that Duke Energy pause new natural gas plant development to allow stakeholders to evaluate load forecast

North Carolina Attorney General NC Newsline (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NC Newsline (opens in a new tab).

Jackson proposed that Duke Energy submit regular reports about agreements with large energy users that differ from standard templates

North Carolina Attorney General NC Newsline (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NC Newsline (opens in a new tab).

Jackson proposed that Duke Energy make public the template contract it uses with data centers and other large energy users

North Carolina Attorney General NC Newsline (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: NC Newsline (opens in a new tab).

Also reported by: The North State Journal (opens in a new tab) local outlet .

Said again: September 19, 2026 ( The North State Journal (opens in a new tab) local outlet ).

Demis Hassabis stated achieving human level AI would unleash ten times the impact of the Industrial Revolution.

Google DeepMind ETV Bharat (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ETV Bharat (opens in a new tab).

Jensen Huang stated every country needs AI data center infrastructure as foundational as water, roads, electricity and internet.

Nvidia CEO ETV Bharat (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ETV Bharat (opens in a new tab).

Jensen Huang, Nvidia CEO, at G20 Innovation Ministerial said work that takes ten years could take one year, and year long projects could finish within a month.

ETV Bharat (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ETV Bharat (opens in a new tab).

Michael Whatley, RNC Chair and U.S. Senate nominee in North Carolina, said data center opposition is not organic and is ginned up

Republican National Committee Chair and U.S. Senate nominee in North Carolina MS NOW (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: MS NOW (opens in a new tab).

Chemours claims 2P50 could nearly eliminate water use for cooling

WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

Coalition of 17 environmental organizations urging EPA not to approve 2P50 and other new PFAS uses

Natural Resources Defense Council and Earthjustice WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

Chemours developing Opteon 2P50, a fluorinated fluid for cooling data center servers

WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

Opteon 2P50 chemical awaiting federal EPA approval and not yet commercially available in United States

Chemours WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

Commissioner Todd Yates stated data centers cannot be stopped

Davidson County Commissioner WXII (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WXII (opens in a new tab).

PFAS from Fayetteville Works contaminated drinking water for hundreds of thousands of people in Cape Fear region

WRAL WRAL (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WRAL (opens in a new tab).

"Treating the generators as separate projects understates the facility's overall pollution impact and helps the companies avoid stricter regulatory standards that would apply if emissions were considered together"
Jasmine Washington, Staff Attorney, Southern Environmental Law Center Southern Environmental Law Center public statement Southern Environmental Law Center (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Southern Environmental Law Center public statement.

Primary source: Southern Environmental Law Center (opens in a new tab).

"One of the wealthiest companies in the world can and should do better than trying to evade critical air quality protections for a whopping 649 diesel-fired generators that belch deadly soot pollution into the air North Carolinians breathe"
Caroline Cress, Senior Attorney, Southern Environmental Law Center Southern Environmental Law Center public statement Southern Environmental Law Center (opens in a new tab) news outlet
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Southern Environmental Law Center public statement.

Primary source: Southern Environmental Law Center (opens in a new tab).

Jon Sanders, director of the John Locke Foundation's Center for Food, Power, and Life, said I'm doubtful local moratoriums will have much practical effect because the market has already narrowed the universe of places where a data center can realistically locate

director, John Locke Foundation Center for Food, Power, and Life Carolina Journal (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Carolina Journal (opens in a new tab).

Republican state Reps. David Willis and Jeff McNeely said residents asking questions about energy, water, noise, and who benefits from the projects deserve answers but argued that blocking data centers through moratoriums is the wrong answer

Republican state representative; Jeff McNeely, Republican state representative Carolina Journal (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Carolina Journal (opens in a new tab).

Gary Salamido, president and CEO of the North Carolina Chamber, said Capital flows where it is wanted and stays where it's welcome, so moratoriums certainly send a message

president and CEO, North Carolina Chamber Carolina Journal (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Carolina Journal (opens in a new tab).

Rania Masri, co director of the North Carolina Environmental Justice Network, said in support of the moratoriums in June: We are being told that AI data centers are inevitable , that communities must sacrifice their water, land, and health, and their economic future for Big Tech's greed

co-director, North Carolina Environmental Justice Network Carolina Journal (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Carolina Journal (opens in a new tab).

Governor Josh Stein and Attorney General Jeff Jackson issued a joint call for Duke Energy to make its federal Ratepayer Protection Pledge legally binding through a state agreement with the Utilities Commission.

North Carolina Attorney General WCCB Charlotte (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: WCCB Charlotte (opens in a new tab).

Foushee has said she thinks the decisions are best left to local leaders in communities where data centers are proposed, and she opposes a planned facility near Apex.

Democratic candidate for U.S. House (District 4), North Carolina wunc.org (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: wunc.org (opens in a new tab).

On the November 3, 2026 ballot in North Carolina: U.S. Senate (4), U.S. House, District 1 (3), U.S. House, District 2 (3), U.S. House, District 3 (3), U.S. House, District 4 (3), U.S. House, District 5 (3), U.S. House, District 6 (2), U.S. House, District 7 (3), U.S. House, District 8 (3), U.S. House, District 9 (2), U.S. House, District 10 (3), U.S. House, District 11 (3), U.S. House, District 12 (2), U.S. House, District 13 (3), U.S. House, District 14 (2); 5 of 42 candidates with a statement on data centers on the record. Every candidate.

Already running in North Carolina

6 sites are serving load, 3 of them in Mecklenburg County.

See the 6 running sites
  1. Digital Realty Charlotte Charlotte, Mecklenburg County Running · Operational since 2016 (10 years)
  2. Google Lenoir data center Lenoir, Caldwell County Running · Operational since 2008 (18 years)
  3. H5 Charlotte Charlotte, Mecklenburg County Running
  4. Meta Forest City Data Center Forest City, Rutherford County Running · Operational since 2012 (14 years)
  5. TierPoint Charlotte Charlotte, Mecklenburg County Running
  6. TierPoint Raleigh Raleigh, Wake County Running

Questions about North Carolina data centers

How many data center projects are on the record in North Carolina?

10 projects are on the record in North Carolina: 3 reported, 6 running, 1 cancelled and 1 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in North Carolina are they?

Records are in 6 counties: Mecklenburg County (4), Wake County (2), Caldwell County (1), Durham County (1), Lee County (1) and Rutherford County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in North Carolina?

Not disclosed. None of the 10 records on file for North Carolina states a power figure. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in North Carolina say they will use?

Not disclosed. None of the 10 records on file for North Carolina states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in North Carolina?

6 developers are named on the record: TierPoint (2 records), CyrusOne, Digital Realty, Google, H5 Data Centers and Meta. 3 records name no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in North Carolina have rules about data centers?

26 county and city rows are on the record, 14 of them rated: Brevard is rated restrictive: Brevard adopted permanent zoning regulations governing data center development instead of a temporary moratorium, September 15, 2026, source (opens in a new tab), Buncombe County is rated restrictive: Buncombe County and Asheville adopted a one year moratorium on data center development, September 15, 2026, source (opens in a new tab) and Charlotte is rated restrictive: Charlotte Water imposed a 150 day moratorium on new data center applications in June while officials study infrastructure capacity and environmental concerns, September 4, 2026, source (opens in a new tab). The state's own row is rated case by case, with 10 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in North Carolina, by county?

3 records are not yet running. Durham County: CyrusOne Durham DUR1-DUR2 (reported); Lee County: Lee County data center (reported); and Mecklenburg County: Historic Charlotte building site data center (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of North Carolina itself decided?

No bill on data centers has been signed into law in North Carolina yet. 2 bills are tracked under Laws: 2 in committee. The state's own scorecard row carries 10 dated acts, the newest reported September 21, 2026. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

nothing disclosed by 10 records

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power010
Water, stated per day010
Water, stated per year010
Permanent jobs010
Tax each year010

A blank cell means no record in North Carolina disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power010
Water, stated per day010
Water, stated per year010
Permanent jobs010
Tax each year010

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 10 tracked facilities in North Carolina are for. 1 site not yet verified is named apart and is not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use10

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

No source on file states how any of the 10 tracked facilities in North Carolina are cooled. 1 site not yet verified is named apart and is not in that number.

Sources read for North Carolina

17 sources

17 sources are read for North Carolina:

Public broadcaster
WUNC
Utility commission dockets
North Carolina Utilities Commission
Economic development
North Carolina Department of Commerce
Search feeds
14 news searches
Every feed, with its kind and tier

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in North Carolina", https://datacenterrecord.org/states/nc, updated October 20, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in North Carolina", https://datacenterrecord.org/states/nc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
NC
Rating of the state's own row
Case by case
Count by status
reported 3, running 6, cancelled 1, not yet verified 1
Located records
2 located, 8 at a centroid, 0 without coordinates

Researcher view · North Carolina · 10 data center sites, 0 buildings where disclosed, 27 rule rows, 2 bills · basis and source tier on every row · verified October 20, 2026

Download CSV JSON GeoJSON