Google operates its Berkeley County hyperscale data center campus at 1025 Cane Bay Boulevard in Moncks Corner, Berkeley County, South Carolina. [2] Filings on the record specify disclosed capacity of 200 MW (the developer's figure), 4 planned or operational buildings. [1] Google lists Google Berkeley County data center at Berkeley County, South Carolina on its own page of data center locations, read September 14, 2026. [1]
Equivalent to ~166,000 U.S. homes (U.S. EIA 830 homes/MW baseline) · 9.6% of Hoover Dam nameplate capacity (2,080 MW).
Grid interconnection and utility service tracked on file.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 1025 Cane Bay Boulevard, Moncks Corner, SC 29461.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Sources:
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Google Berkeley County data center.
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 200 MW | 200 MW | the developer's figure [1] datacenters.google |
| Site Footprint (Acres) | |||
| Data Hall Buildings | 4 buildings | 4 | operator page [1] datacenters.google |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Chronological regulatory, corporate and permitting events on the record, newest first.
(source date; the content gives no date of its own)
Google is investing $9 billion in three South Carolina AI data centre campuses through 2027
[12] techbuzz.ai, also Post and Courier (opens in a new tab) public registry
(source date; the content gives no date of its own)
· Status: running (source date; the content gives no date of its own)
Google data center expansion in South Carolina to become one of company's largest facilities
Read on September 14, 2026 (the day the page was read; it gives no date of its own)
Google lists Google Berkeley County data center at Berkeley County, South Carolina on its own page of data center locations, read September 14, 2026.
The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.
The source was labeled with the Google News search that found it; it now carries its outlet's tier: video is tier 5 (the editor, September 23, 2026). The link did not change.
The note "(Entry dated by the video's upload date; see the correction.)" appended by the date correction of September 8, 2026 belongs in this log, not in the event sentence; the date basis of the row already says the date is the source's. The sentence is restored to the event only (September 13, 2026).
Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.
Date basis recorded (September 8, 2026, /methodology#dates): the row's date is the video's upload date, the source's own date, because the content gives no date of its own.
Dated by the video's upload date (ABC News 4, October 13, 2025), which is the source date; the content gives no other date.
Every correction on the record is on the corrections page.
Verified data center records in South Carolina within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| DartPoints Charleston Data Center (CHS1) Ladson, Charleston County | 17 mi | Running | DartPoints | 4 MW |
| Google Dorchester County data center Ridgeville, Dorchester County | 32 mi | Being built | 150 MW | |
| Eagle Rock Partners Colleton County Data Center Walterboro, Colleton County | 42 mi | Proposed | Eagle Rock Partners | 1 GW |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Google is the developer. No construction contractor is named on the record yet.
Power: 200 MW (the developer's figure, datacenters.google (opens in a new tab)). Water: not disclosed by any source on file.
It is running, as reported February 16, 2019. The newest entry, reported October 13, 2025: Google is investing $9 billion in three South Carolina AI data centre campuses through 2027 [12].
Official operator or facility campus page verified in 50 state website discovery pass.
13 sources on file.
This site is in the SERC Virginia and Carolina South (SRVC-S) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Google Berkeley County data center. Last verified October 27, 2026. https://datacenterrecord.org/projects/google-berkeley-county-data-center-sc. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Google Berkeley County data center
Data Center Record, "Google Berkeley County data center", https://datacenterrecord.org/projects/google-berkeley-county-data-center-sc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.