Energy Storage Solutions Edgecombe County AI Data Center
Kingsboro, Edgecombe County, NCDeveloper: Energy Storage SolutionsCensus GEOID 37065
- Stage
- Proposed
- Undisclosed in public filings
- Land, Water
Energy Storage Solutions proposed a 900 megawatt AI data center campus on 122 acres of county owned land at the Kingsboro Industrial Park in Edgecombe County, North Carolina. It is proposed, since July 14, 2026.
How much water it would use and who would use it have not been disclosed.
Tap a pin for the data center, the parcel for its record
- This record: Proposed, ringed
- data center
- Smaller pins: 25 other published records in North Carolina
Details
- this record's location, ringed
- parcel outline, from the county parcel record
- city limits, U.S. Census Bureau, on a town level record
- county boundary
The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.
How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.
What is known
Each figure as its source gave it. The number in brackets is its place in the source list.
- Buildings
- 4 buildings zoning application, verified October 27, 2026
- Power it would draw
- 900 MW the developer's figure About 9 percent of New York City's summer peak demand in 2024.
- Who leads it
- Energy Storage Solutions as stated by the source
- Undisclosed in public filings
- Land, Water, Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
- Energy Storage Solutions Edgecombe County AI Data Center, capacity: 900 MW.
- New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
- 900 ÷ 10,245 = 0.09 (MW over MW).
Sources:
- Energy Storage Solutions (opens in a new tab)
- NYISO, 2025 Load and Capacity Data Report (Gold Book) (opens in a new tab), Table I-4a, Baseline Summer Non-Coincident Peak Demand, Historical and Forecast, page 26, Zone J, 2024 row (2024)
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Every field, with who said it and when (Researcher view)
Impact figures
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| How much power it needs | 900 MW | the developer's figure | edgecombecountync.gov (opens in a new tab) | October 27, 2026 |
| How much water it would use | ||||
| How loud it would be | ||||
| Jobs once it runs | ||||
| Tax it would pay each year |
The record's fields
| Field | Value | Who says so | Source | Last verified |
|---|---|---|---|---|
| Who is building it | Energy Storage Solutions | as stated by the source | October 27, 2026 | |
| Who is constructing it | ||||
| How much land | ||||
| Buildings | 4 buildings | zoning application, verified October 27, 2026 | edgecombecountync.gov (opens in a new tab) | October 27, 2026 |
| Where its power comes from | ||||
| Grid connection | ||||
| How it is cooled |
A blank value cell means not disclosed by any source on file; a blank basis cell means the source gave the figure without saying on what basis.
The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.
Still not public, and where it would show up
The record adds each the day a source gives it. Why these documents.
- Water use A state water right filing or a water supply agreement.
- Who would use it A lease announcement or a tenant named in a filing.
- Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.
What happened
-
· Status: proposed (content date)
Energy Storage Solutions proposed a 900 megawatt AI data center on 122 acres of county owned land in Kingsboro, Edgecombe County, facing resident opposition.
The full Energy Storage Solutions Edgecombe County AI Data Center timeline, in order
The site
The pin is the site. The shaded outline is the parcel, from the county's own parcel record.
- Where
- Kingsboro Industrial Park, Rocky Mount, NC 27801, Kingsboro, Edgecombe County, North Carolina [source] (opens in a new tab)
- How exactly it is located
- Exact, on the parcel
- The parcel
- No parcel outline in the public record
- Nearest homes
- Not computed for a record placed at a place center
- Nearest records
- Southeast Raleigh data center, 52 mi
- TierPoint Raleigh, 52 mi
- American Tower Raleigh Data Center (RA1), 60 mi
- Flexential Raleigh (RAL01, RAL02, and RAL03), 65 mi
- Inflow Data Center, 66 mi
Keep going
Questions about this project
5 questions answered from the record
How big is Energy Storage Solutions Edgecombe County AI Data Center?
-
The record has 2 measures of its size: 900 MW (the developer's figure, edgecombecountync.gov (opens in a new tab)) and 4 buildings (zoning application, verified October 27, 2026, edgecombecountync.gov (opens in a new tab)). Its acreage is not disclosed.
Who is building Energy Storage Solutions Edgecombe County AI Data Center?
-
Energy Storage Solutions is the developer. No construction contractor is named on the record yet.
How much power and water does Energy Storage Solutions Edgecombe County AI Data Center say it needs?
-
Power: 900 MW (the developer's figure, edgecombecountync.gov (opens in a new tab)). Water: not disclosed by any source on file.
Where does Energy Storage Solutions Edgecombe County AI Data Center stand today?
-
It is proposed, since July 14, 2026. The newest entry, July 14, 2026: Energy Storage Solutions proposed a 900 megawatt AI data center on 122 acres of county owned land in Kingsboro, Edgecombe County, facing resident opposition. [1]
What has Kingsboro or Edgecombe County decided about it?
-
No decision by Kingsboro or Edgecombe County about data centers is on the record. The Edgecombe County page and the North Carolina scorecard list every rated row the day a person publishes one.
Sources
Reporting
- AI data center boom meets rural reality in Edgecombe County - North Carolina Health News (opens in a new tab), North Carolina Health News, July 14, 2026, query feed
1 source on file.
About this data
Last verified , first recorded . Every correction is logged on the corrections page. Report a correction · Send a tip about Energy Storage Solutions Edgecombe County AI Data Center
Cite this page
Data Center Record, "Energy Storage Solutions Edgecombe County AI Data Center", https://datacenterrecord.org/projects/energy-storage-solutions-edgecombe-county-ai-data-center-kingsboro-nc. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
For researchers
- Stage
- Proposed
- Tier
- built from one source
- Tags
- Built from one source
- Coordinates
- 35.9182, -77.6745
- How the location is known
- Location from the county parcel record.
- Location source
- https://www.edgecombecountync.gov/
- Coordinate source
- Edgecombe County Kingsboro Industrial Park parcel record
- How capacity was disclosed
- the developer's figure
- Capacity, if disclosed
- 900 MW, the developer's figure
- Published
- September 28, 2026
- Last verified
- October 27, 2026
- Undisclosed in public filings