14 more on this page, one per speaker and claim; 18 statements in all
Democratic U.S. Senate nominee Dr. Annie Andrews called for a two year statewide moratorium on new data center construction in South Carolina, arguing that unchecked hyperscale development threatens household electricity rates, water supplies, and county tax bases.
Senator Darline Graham opposed calls for a data center moratorium in South Carolina and defended hyperscale artificial intelligence infrastructure as essential to U.S. national security in competition with China, while the AI industry super PAC Building the Future reserved $1.5 million in television advertising supporting his reelection.
Dr. Octavia Amaechi, Spartanburg County Commissioner of Public Works, expressed concern about the magnitude of the change in water demand projections and questions about how the projections changed and long term water use implications.
State Rep. Thomas Beach said bill by Rep. April Cromer and co sponsored by Rep. Lee Hewitt would require data centers to pay for infrastructure including electricity and water.
Southern Environmental Law Center advocated for a pause on data centers and raised concerns about a data center currently under construction on South Pine Street
Power, water, jobs and tax, summed only where a data center disclosed the figure; what each facility is for; how each is cooled. Nothing here is estimated.
Power, water, jobs and tax
Figure
Disclosed total
Disclosed
Without a figure
Basis
Power
461 MW
2
1
2 the developer's figure
Water, stated per day
0
3
Water, stated per year
0
3
Permanent jobs
0
3
Tax each year
0
3
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
Use
Records
Power
Water
Jobs
Tax each year
No stated use
3
461 MW
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 3 tracked facilities in Spartanburg are for.
How the facilities are cooled
No source on file states how any of the 3 tracked facilities in Spartanburg are cooled.
FiguresOnly what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
LicenseData CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this pageData Center Record, "Data centers in Spartanburg, Spartanburg County, South Carolina", https://datacenterrecord.org/states/sc/spartanburg-county/spartanburg, updated November 6, 2026.CSV · JSON
Data Center Record, "Data center records in Spartanburg, Spartanburg County, South Carolina", https://datacenterrecord.org/states/sc/spartanburg-county/spartanburg. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.
Researcher view · Spartanburg, Spartanburg County, South Carolina · 3 records, 0 rule rows · Census GEOID 4568290 · basis and source tier on every row · verified November 6, 2026