Governor Jim Pillen said data center projects cannot be allowed to deplete natural resources
Context & source notes
Provenance: Paraphrased; said in the source itself.
Primary source: Kearney Hub (opens in a new tab).
Nebraska has 12 data center sites, 0 buildings where disclosed on the record: 5 running and 7 proposed. Most are in Lancaster County (4) and Douglas County (3), and records are in 6 of 93 counties. The largest proposal is Lincoln Data Center in Lancaster County; it is reported.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
| TierPoint Omaha Omaha, Douglas County | Running | TierPoint | ||
|---|---|---|---|---|
| Google Papillion data center Papillion, Sarpy County | Running | Google to open new data center in Sarpy County 3newsnow.com (opens in a new tab) local outlet reported October 4, 2019 |
A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 12 Nebraska projects.
| Record | Place | Stage | Operator | MW | Basis | Located | Tier | Verified |
|---|---|---|---|---|---|---|---|---|
| Lightedge Data Center | Papillion, Sarpy | Not yet verified | EPA registry | 2 | 2026-10-20 | |||
| Lincoln Data Center | Lincoln, Lancaster | Proposed | centroid | 4 | 2026-09-25 | |||
| Monolith Data Center Expansion (Hallam) | Hallam, Lancaster | Proposed | Monolith | centroid | 1 | 2026-09-18 | ||
| Google Omaha data center | Omaha, Douglas | Running | centroid | 2 | 2026-09-17 | |||
| Grand Island Data Center | Grand Island, Hall | Proposed | centroid | 4 | 2026-09-17 | |||
| H5 Omaha | Omaha, Douglas | Running | H5 Data Centers | centroid | 2 | 2026-09-17 | ||
| Meta Sarpy Data Center | Papillion, Sarpy | Running | Meta | centroid | 1 | 2026-09-17 | ||
| TierPoint Omaha | Omaha, Douglas | Running | TierPoint | centroid | 2 | 2026-09-17 | ||
| Winnebago Tribe AI Data Center | Winnebago, Thurston | Proposed | Winnebago Tribe of Nebraska | centroid | 4 | 2026-09-17 | ||
| Kearney Data Center | Kearney, Buffalo | Proposed | centroid | 4 | 2026-09-17 | |||
| Data Center near Hallam (unnamed developers) | Hallam, Lancaster | Proposed | centroid | 4 | 2026-09-17 | |||
| Google Lincoln Data Center | Lincoln, Lancaster | Proposed | centroid | 2 | 2026-09-17 | |||
| Google Papillion data center | Papillion, Sarpy | Running | EPA registry | 2 | 2026-10-04 |
Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.
| County | Census GEOID | Projects | Rules | How it treats data centers |
|---|---|---|---|---|
| Lancaster County | 31109 | 3 | ||
| Douglas County | 31055 | 0 | ||
| Sarpy County | 31153 | 0 | ||
| Buffalo County | 31019 | 0 | ||
| Hall County | 31079 | 0 | ||
| Thurston County | 31173 | 0 | ||
| Cass County | 31025 | 1 | ||
| Gage County | 31067 | 1 | ||
| Lincoln County | 31111 | 1 |
A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.
What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.
| Body | Level | Rating | In force until | Latest act | Acts | Verified |
|---|---|---|---|---|---|---|
| Nebraska | state | Nebraska ended one data center tax break. goodjobsfirst.org (opens in a new tab) news outlet Jun 5, 202615 acts on this rowEvery act on the Nebraska row
| 15 | 2026-10-01 | ||
| Kearney | city | Kearney City Council approved Tech One Crossing data center on Tuesday, September 8, 2026. omaha.com (opens in a new tab) local outlet Sep 8, 20268 acts on this rowEvery act on the Kearney row
| 8 | 2026-09-23 | ||
| Cass County | county | until August 11, 2027 | 2027-08-11 | Cass County Board of Commissioners voted 5-0 to approve a 12 month moratorium on permitting for data centers. klkntv.com (opens in a new tab) local outlet Aug 11, 20265 acts on this rowEvery act on the Cass County row
| 5 | 2026-09-23 |
| Gage County | county | until September 16, 2027 | 2027-09-16 | Gage County supervisors approved a 12 month moratorium on data center permits on Wednesday. klkntv.com (opens in a new tab) local outlet Sep 16, 20262 acts on this rowEvery act on the Gage County row
| 2 | 2026-09-17 |
| Hallam | city | not rated | Hallam planning commission unanimously recommended approval for Monolith's proposed data center. omaha.com (opens in a new tab) local outlet Reported Sep 181 act on this rowEvery act on the Hallam row
| 1 | 2026-09-18 | |
| Lancaster County | county | not rated | Lancaster County Board created 13 member task force to review data center proposal and recommend regulations to Planning Commission by end of year. starherald.com (opens in a new tab) news outlet Reported Sep 112 acts on this rowEvery act on the Lancaster County row
| 2 | 2026-09-23 | |
| Lincoln | city | not rated | City of Lincoln announced it would not pursue additional large scale data centers outside Google's site near North 35th Street and Interstate 80. journalstar.com (opens in a new tab) local outlet Reported Aug 271 act on this rowEvery act on the Lincoln row
| 1 | 2026-08-27 | |
| Lincoln County | county | not rated | Lincoln County commissioners voted down a data center moratorium. knopnews2.com (opens in a new tab) local outlet Reported Jul 131 act on this rowEvery act on the Lincoln County row
| 1 | 2026-08-27 |
Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.
No official summary on file for any of these 8 measures; each row links to the legislature's page for the text.
LB1010 Signed
Provide powers and duties for public power districts related to cryptocurrency mining operations
L.B. 526 Signed
Provide a property tax exemption and a sales and use tax exemption relating to data centers
LB1080 Signed
Provide tax incentives for large data center projects
LB1118 Signed
L.B. 468 Died at adjournment
Adopt the Large Load Customer Regulation Act
L.B. 1064 Died at adjournment
L.B. 1111 Died at adjournment
L.B. 1131 Died at adjournment
8 bills tracked, 4 signed · LegiScan, CC BY 4.0
| Number | Session | Status | Date | Title |
|---|---|---|---|---|
| LB1010 | 109th Legislature | Signed | 2026-04-17 | Adopt the Large Load Customer Regulation Act, provide for eminent domain relating to energy storage and regulation and taxation of energy storage resources, and change provisions relating to cryptocurrency mining operations and data centers |
| L.B. 1064 | 109th Legislature | Died at adjournment | 2026-04-17 | Adopt the Large Load Customer Regulation Act |
| L.B. 1111 | 109th Legislature | Died at adjournment | 2026-04-17 | Require an annual data center load report to the Nebraska Power Review Board, provide powers and duties for public power suppliers, allow and require regulation of data centers, and change provisions relating to regulation of cryptocurrency mining operations |
| L.B. 1131 | 109th Legislature | Died at adjournment | 2026-04-17 | Adopt the Domestic Violence and Human Trafficking Service Providers Tax Credit Act and eliminate personal property tax and sales and use tax exemptions relating to data centers |
| L.B. 468 | 109th Legislature | Died at adjournment | 2026-04-17 | Change provisions relating to inheritance taxes, change certain fee and tax provisions, and eliminate a sales tax exemption relating to data centers |
| L.B. 526 | 109th Legislature | Signed | 2025-05-21 | Provide powers and duties for public power districts related to cryptocurrency mining operations |
| LB1080 | 102nd Legislature | Signed | 2012-04-11 | Provide a property tax exemption and a sales and use tax exemption relating to data centers |
| LB1118 | 102nd Legislature | Signed | 2012-03-07 | Provide tax incentives for large data center projects |
8 bills tracked in Nebraska; 109th Legislature, legislature adjourned; last checked October 26, 2026. The last check found no bill not already tracked; the 8 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)
Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.
| Member | Party | Position |
|---|---|---|
| Bacon | R | Yea |
| Flood | R | Yea |
| Smith (NE) | R | Yea |
A blank party cell means the clerk's roll gives none.
| Member | Party | Position |
|---|---|---|
| Fischer (R-NE) | R | Yea |
| Ricketts (R-NE) | R | Yea |
A blank party cell means the clerk's roll gives none.
Positions as the clerk records them. How bills and votes are recorded.
Scorecard eventNebraska
MoratoriumNebraska
Governor Jim Pillen signed an executive order formalizing a pause on data center development
Scorecard eventHallam
Hallam planning commission unanimously recommended approval for Monolith's proposed data center
Now reportedMonolith Data Center Expansion (Hallam)
Moratorium adoptedGage County
Gage County supervisors approved a 12 month moratorium on data center permits on Wednesday
Scorecard eventLancaster County
Governor Jim Pillen said billion dollar data center companies are well positioned to pay their own way
Scott Novack, vice president of digital infrastructure for Stark, said the company is in early stages of evaluating the site and no final decision has been made
Every Nebraska statement, by speaker (49)
Governor Jim Pillen said data center projects cannot be allowed to deplete natural resources
Provenance: Paraphrased; said in the source itself.
Primary source: Kearney Hub (opens in a new tab).
Governor Jim Pillen called for creation of a task force to study the impact of data centers on natural resources, land, water and electricity
Provenance: Paraphrased; said in the source itself.
Primary source: Kearney Hub (opens in a new tab).
Micaela Wuehler, Lincoln County Commissioner, appointed to 19 member Nebraska Data Center Task Force
Provenance: Paraphrased; content date; reported from elsewhere.
Primary source: Omaha World-Herald (opens in a new tab).
County Commissioner Sean Flowerday said land must be zoned industrial for data center permit and as of now that is not possible in Lancaster County
Provenance: Paraphrased; said in the source itself.
Primary source: nebraskapublicmedia.org (opens in a new tab).
Ken Winston said developers should disclose projected electrical demand, water usage, and greenhouse gas emissions before approval
Provenance: Paraphrased; said in the source itself.
Primary source: WOWT (opens in a new tab).
Ken Winston said data centers need regulation and pausing builds can buy communities time to develop standards
Provenance: Paraphrased; said in the source itself.
Primary source: WOWT (opens in a new tab).
Nebraska Sierra Club meeting addressed benefits and drawbacks of AI data centers, calling for regulations to ensure sustainability
Provenance: Paraphrased; said in the source itself.
Primary source: WOWT (opens in a new tab).
During a question about AI data centers, Backemeyer stressed the need for greater transparency and said local communities should have more say in decisions surrounding new developments, including tax breaks and other incentives.
Provenance: Paraphrased; said in the source itself.
Primary source: couriernebraska.com (opens in a new tab).
Matt Schulte, Republican candidate for Lancaster County Commissioner District 3, previously proposed a data center moratorium but later agreed a moratorium might not be necessary.
Provenance: Paraphrased; said in the source itself.
Primary source: Nebraska Public Media (opens in a new tab).
Governor Jim Pillen said he generally opposes moratoriums, preferring that decisions be made on a case by case basis for individual communities and projects.
Provenance: Paraphrased; said in the source itself.
Primary source: klin.com (opens in a new tab).
Governor Jim Pillen said Nebraska needs to protect water supplies, protect ratepayers, and should not give data center tax credits.
Provenance: Paraphrased; said in the source itself.
Primary source: klin.com (opens in a new tab).
Rex Adams, Gage County Supervisor, said as soon as the board gets regulations in place, the better off they are and should not drag it out.
Provenance: Paraphrased; said in the source itself.
Primary source: omaha.com (opens in a new tab).
Lancaster County Commissioner Christa Yoakum stated that Lancaster County has very little land zoned industrial and would not have enough property in one place for a data center under current zoning.
Provenance: Paraphrased; content date; reported from elsewhere.
Primary source: KLKN-TV (opens in a new tab).
Sierra Club Nebraska is concerned about potential long term consequences of data center water use and lack of oversight.
Provenance: Paraphrased; said in the source itself.
Primary source: wowt.com (opens in a new tab).
County zoning regulations do not define data centers
Provenance: Paraphrased; said in the source itself.
Primary source: Omaha World-Herald (opens in a new tab).
Bold Alliance proposed local legislation to regulate data centers
Provenance: Paraphrased; said in the source itself.
Primary source: Omaha World-Herald (opens in a new tab).
Mayor Jonathan Nikkila said the city is trying to get ahead of data center development with great laws and high standards
Provenance: Paraphrased; said in the source itself.
Primary source: KLKN-TV (opens in a new tab).
Dan Osborn said he doesn't want the U.S. to lose out to China on data centers and is therefore against a data center moratorium.
Provenance: Paraphrased; said in the source itself.
Primary source: c-span.org (opens in a new tab).
Walz suggested a committee of experts on power and natural resource consumption advise data center projects coming to Nebraska communities.
Provenance: Paraphrased; said in the source itself.
Primary source: Columbus Telegram (opens in a new tab).
Walz expressed opposition to state government dictating data center allowances and said communities should build their own economic development plans.
Provenance: Paraphrased; said in the source itself.
Primary source: Columbus Telegram (opens in a new tab).
Walz referenced Lincoln Premium Poultry opening in Fremont in 2018 and the community adjusting plans, suggesting she wants data center decisions handled similarly with local input.
Provenance: Paraphrased; said in the source itself.
Primary source: Columbus Telegram (opens in a new tab).
Lynne Walz said state government should not tell communities what they can and cannot allow in their areas and those decisions should be local.
Provenance: Paraphrased; said in the source itself.
Primary source: Columbus Telegram (opens in a new tab).
Trump called data centers the Golden Goose in a Truth Social post
Provenance: Paraphrased; said in the source itself.
Primary source: KFXL (opens in a new tab).
Archived copy: Wayback Machine (opens in a new tab).
President Trump wrote on Truth Social that rejecting data centers would make communities backwards and poor, and urged to let data reign
Provenance: Paraphrased; said in the source itself.
Primary source: KFXL (opens in a new tab).
Archived copy: Wayback Machine (opens in a new tab).
Hyperscale data center projects can span thousands of acres
Provenance: Paraphrased; said in the source itself.
Primary source: KMTV 3 News Now (opens in a new tab).
Farmer Darin Schwaninger declined the option offer citing concerns about community division
Provenance: Paraphrased; said in the source itself.
Primary source: 1011now.com (opens in a new tab).
Senator Danielle Conrad criticized Pillen's announcement that he would deny tax incentives for data centers, as a 'performative' attempt to suspend state law and tax policy through an executive order.
Provenance: Paraphrased; said in the source itself.
Primary source: Nebraska Public Media (opens in a new tab).
Janet Bock, a candidate for District 30, said data centers are a top issue for people in her district, which includes Gage County and part of Lancaster County. She said people are concerned about environmental effects and property value deterioration, and thinks the moratorium should be longer than the eight months approved by the Gage County Board.
Provenance: Paraphrased; said in the source itself.
Primary source: Nebraska Public Media (opens in a new tab).
Data centers are necessary for staying ahead in the AI race and national defense
Provenance: Paraphrased; said in the source itself.
Primary source: Nebraska Governor's Office (.gov) (opens in a new tab).
Archived copy: Wayback Machine (opens in a new tab).
Governor Pillen said the task force will help evaluate the impact of data centers on Nebraska's water resources, power grids and local infrastructure
Provenance: Paraphrased; said in the source itself.
Primary source: Nebraska Governor's Office (.gov) (opens in a new tab).
Archived copy: Wayback Machine (opens in a new tab).
Governor Pillen said the task force will ensure county officials have necessary tools, zoning guidelines and policy frameworks to manage data center growth effectively
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Gov. Jim Pillen announced 17 members to the state's new Data Center Task Force
Provenance: Paraphrased; said in the source itself.
Primary source: nebraskapublicmedia.org (opens in a new tab).
Task force membership includes 17 officials including executives from Berkshire Hathaway Energy, Tenaska, OPPD, NPPD, Lincoln Electric System, and county commissioners from multiple jurisdictions
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Pillen stated task force must balance economic development with protecting state resources including land, electricity and water
Provenance: Paraphrased; said in the source itself.
Primary source: KETV (opens in a new tab).
Residents voiced concerns about water, electricity, and quality of life impacts from data centers
Provenance: Paraphrased; said in the source itself.
Primary source: KMTV 3 News Now (opens in a new tab).
Jayden Speed, founder of Cass County Data Center Watch, raised concerns about water and electricity usage
Provenance: Paraphrased; said in the source itself.
Primary source: KMTV 3 News Now (opens in a new tab).
Lisa Hild, a resident, expressed concern that a data center would change her family farm's quality of life
Provenance: Paraphrased; said in the source itself.
Primary source: KMTV 3 News Now (opens in a new tab).
Eric Klein testified that added tax revenue from data centers could lower property tax rates for everyone in the county
Provenance: Paraphrased; said in the source itself.
Primary source: KMTV 3 News Now (opens in a new tab).
Pete Sepp, National Taxpayers Union President, said Nebraska executive order constitutes effective moratorium on data centers
Provenance: Paraphrased; said in the source itself.
Primary source: National Taxpayers Union (opens in a new tab).
Maureen Larsen, Director of Economic Development, said the state wants to be supportive of data center projects when in Nebraska's best interest while guarding against out of state entities extracting resources
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Sen. Mike Jacobson indicated willingness to introduce a bill to remove data centers from the Imagine Nebraska Act
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Gov. Pillen said data centers should not receive tax incentives and the state should attract givers not takers
Position note: Follows July 2026 statements describing Nebraska as appealing for data centers due to low electricity rates, accompanying an executive order suspending state tax incentives for large scale facilities.
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Gov. Jim Pillen said Nebraska is appealing because of available land, low electrical rates and abundant water, but has also provided tax incentives to data centers
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
The executive order will create a task force to propose safeguards to protect the state's natural resources from data center use
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
Gov. Pillen said the executive order will suspend state tax incentives for large scale data centers
Provenance: Paraphrased; said in the source itself.
Primary source: KOLN | Nebraska Local News, Weather, Sports | Lincoln, NE (opens in a new tab).
As of March 2026, Google had built three data centers in Nebraska, including one in Omaha and one in Papillion.
Provenance: Paraphrased; content date; reported from elsewhere.
Primary source: wowt.com (opens in a new tab).
On the November 3, 2026 ballot in Nebraska: Governor (4), U.S. Senate (5), U.S. House, District 1 (4), U.S. House, District 2 (3), U.S. House, District 3 (5); 3 of 21 candidates with a statement on data centers on the record. Every candidate.
5 sites are serving load, 3 of them in Douglas County.
12 projects are on the record in Nebraska: 7 reported, 5 running and 1 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers
answered from the rows aboveRecords are in 6 counties: Lancaster County (4), Douglas County (3), Sarpy County (2), Buffalo County (1), Hall County (1) and Thurston County (1). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers
answered from the rows aboveNot disclosed. None of the 12 records on file for Nebraska states a power figure. Resources: the questions people ask about data centers
answered from the rows aboveNot disclosed. None of the 12 records on file for Nebraska states a water figure. Resources: the questions people ask about data centers
answered from the rows above6 developers are named on the record: Google (3 records), H5 Data Centers, Meta, Monolith, TierPoint and Winnebago Tribe of Nebraska. 4 records name no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers
answered from the rows above7 county and city rows are on the record, 3 of them rated: Kearney is rated case by case: Kearney City Council approved Tech One Crossing data center on Tuesday, September 8, 2026, source (opens in a new tab), Cass County is rated restrictive: Cass County Board of Commissioners voted 5-0 to approve a 12 month moratorium on permitting for data centers, August 11, 2026, source (opens in a new tab) and Gage County is rated restrictive: Gage County supervisors approved a 12 month moratorium on data center permits on Wednesday, September 16, 2026, source (opens in a new tab). The state's own row is rated case by case, with 15 dated acts listed under the scorecard. Resources: the questions people ask about data centers
answered from the rows above7 records are not yet running. Lancaster County: Lincoln Data Center (reported), Monolith Data Center Expansion (Hallam) (reported), Data Center near Hallam (unnamed developers) (reported) and Google Lincoln Data Center (reported); Buffalo County: Kearney Data Center (reported); Hall County: Grand Island Data Center (reported); and Thurston County: Winnebago Tribe AI Data Center (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers
answered from the rows above4 state laws are on the record: LB1010 (signed, April 17, 2026, source (opens in a new tab)), L.B. 526 (signed, May 21, 2025, source (opens in a new tab)) and LB1080 (signed, April 11, 2012, source (opens in a new tab)) and 1 more under Laws. The state's own scorecard row carries 15 dated acts, the newest reported October 1, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers
answered from the rows abovesummed only where a record disclosed the figure
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 12 | ||
| Water, stated per day | 0 | 12 | ||
| Water, stated per year | 0 | 12 | ||
| Permanent jobs | 0 | 12 | ||
| Tax each year | 0 | 12 |
A blank cell means no record in Nebraska disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.
| Figure | Disclosed total | Disclosed | Without a figure | Basis |
|---|---|---|---|---|
| Power | 0 | 12 | ||
| Water, stated per day | 0 | 12 | ||
| Water, stated per year | 0 | 12 | ||
| Permanent jobs | 0 | 12 | ||
| Tax each year | 0 | 12 |
A blank total means no record disclosed the figure; the count without one says how many.
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
The disclosed totals are in the table above.
No source on file states what any of the 12 tracked facilities in Nebraska are for. 1 site not yet verified is named apart and is not in that number.
| Use | Records | Power | Water | Jobs | Tax each year |
|---|---|---|---|---|---|
| No stated use | 12 |
A blank cell means no record with that use disclosed the figure.
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
No source on file states how any of the 12 tracked facilities in Nebraska are cooled. 1 site not yet verified is named apart and is not in that number.
Report a correction · Send a tip about Nebraska