Data Center Record.

Laws · Nebraska

Data center laws in Nebraska

2 rules at the state level: 2 statutes. Each says what it requires in the words of its text, with the effective date the text gives and a link to the bill or order.

Last verified

Rules on the record
2
Passed
2
Statutes
2

Rules in Nebraska

  • L.B. 1010 Statute

    Adopt the Large Load Customer Regulation Act, provide for eminent domain relating to energy storage and regulation and taxation of energy storage resources, and change provisions relating to cryptocurrency mining operations and data centers

    Passed passed April 17, 2026. 109th Legislature. This status is read from the bill's own record, not written here.

    L.B. 1010 of the 109th Legislature was signed on April 17, 2026. The legislature titles it: Adopt the Large Load Customer Regulation Act, provide for eminent domain relating to energy storage and regulation and taxation of energy storage resources, and change...

    L.B. 1010 of the 109th Legislature was signed on April 17, 2026. The legislature titles it: Adopt the Large Load Customer Regulation Act, provide for eminent domain relating to energy storage and regulation and taxation of energy storage resources, and change provisions relating to cryptocurrency mining operations and data centers.

    What it requires

    The act adopts the Large Load Customer Regulation Act and requires every public power supplier to set interconnection standards for a large load customer, meaning a retail customer asking for a new or expanded interconnection where the total load at a single site would exceed twenty megawatts.

    The act adopts the Large Load Customer Regulation Act and requires every public power supplier to set interconnection standards for a large load customer, meaning a retail customer asking for a new or expanded interconnection where the total load at a single site would exceed twenty megawatts. Separately, a data center with a load of ten megawatts or more triggers a load study and notice before interconnection, an annual report to the Department of Water, Energy, and Environment and to the Legislature's Natural Resources Committee each September 30, provision for decommissioning costs, and a community benefit agreement.

    Describes the act as enacted.

    The text: nebraskalegislature.gov (opens in a new tab) primary source

    Last verified September 24, 2026.

  • L.B. 526 Statute

    Provide powers and duties for public power suppliers related to cryptocurrency mining operations

    Passed passed May 20, 2025. 109th Legislature, 1st Session. This status is read from the bill's own record, not written here.

    Approved by the Governor on 20 May 2025. It defines a cryptocurrency mining operation by the size of its electric load and lets the public power supplier that would serve one put requirements on it for the cost of the infrastructure that serves it.

    What it requires

    A cryptocurrency mining operation is any facility of one megawatt or more. A public power supplier may impose requirements on such an operation for the cost of infrastructure upgrades needed to serve it.

    Describes the act as enacted.

    The text: nebraskalegislature.gov (opens in a new tab) query feed

    Last verified September 19, 2026.

A law here is one statute, utility commission order, tariff, tax rule, moratorium or bill at the state level. What it requires is taken from the text, never summarized from coverage; a date the text does not give is left empty. Its status is one of five, defined on the laws index. The dated events beneath a law are the scorecard entries that cite it.

Bills tracked

8 bills tracked in the Nebraska legislature: 4 signed into law, 4 failed or died. A row opens its own page, with its history, each recorded vote and the legislature's own text. A resolution states a position and does not change the law.

No official summary on file for any of these 8 bills; each links to the legislature's page for the text.

8 bills tracked in Nebraska; 109th Legislature, legislature adjourned. No data center bills found as of October 26, 2026. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill. LegiScan is credited as the finder; the citation is the legislature's own page. How bills and votes are recorded.

This page as data CSV JSON
Cite this page

Data Center Record, "Data center laws in Nebraska", https://datacenterrecord.org/laws/ne. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.