Data centers in Hallam, Nebraska
Hallam has 2 data centers on the record: 2 proposed. Hallam has a scorecard row with no rating yet. The latest decision on the record: Hallam planning commission unanimously recommended approval for Monolith's proposed data center, September 18, 2026. Lancaster County's own decisions are on the Lancaster County page.
How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.
The 2 data centers in Hallam
Newest activity firstEach row is one site with its stage, its latest dated entry and what its sources disclose. A figure no source gives reads Not disclosed.
Monolith Data Center Expansion (Hallam)
Hallam, Lancaster County · Monolith
Latest, reported September 18, 2026: Phase 1 expansion would take about 18 months and increase production to 220,000 tons per year of carbon black omaha.com local outlet
- Land
- Not disclosed
- Power
- Not disclosed
- Water
- Not disclosed
- Tenant
- Not disclosed
Data Center near Hallam (unnamed developers)
Hallam, Lancaster County
Latest, reported August 27, 2026: Developers offered Hallam farmer Darin Schwaninger tens of thousands of dollars per acre in February 1011now.com local outlet
- Land
- Not disclosed
- Power
- Not disclosed
- Water
- Not disclosed
- Tenant
- Not disclosed
Where
Drag with one finger to move the map, pinch to zoom. Tap a pin for the data center, a county for its rules
2 data centers in Hallam: all proposed. A dashed edge means the exact site is not in the public record; every pin here marks a town or the county.
What Hallam has decided
1 body, 1 decision on the recordWhat the city has done about data centers: each body on its own row with its rating, open, case by case, restrictive or closed, never good or bad, and every vote, ordinance, moratorium or agreement behind its toggle, newest first, with its source.
Reported: the source's date; the item names no day of its own.
- Hallamcity
Hallam planning commission unanimously recommended approval for Monolith's proposed data center, reported September 18, 2026.
1 act on this row
- event
Hallam planning commission unanimously recommended approval for Monolith's proposed data center
- event
What happened
-
· Hallam
Scorecard event: Hallam planning commission unanimously recommended approval for Monolith's proposed data center omaha.com local outlet
-
· Monolith Data Center Expansion (Hallam)
Now reported: Phase 1 expansion would take about 18 months and increase production to 220,000 tons per year of carbon black omaha.com local outlet
-
· Data Center near Hallam (unnamed developers)
Now reported: Stark Power, based in Tel Aviv, Israel, acquired Sagebrush Infrastructure in June nebraskapublicmedia.org local outlet
What was said
Farmer Darin Schwaninger declined the option offer citing concerns about community division
Scott Novack, vice president of digital infrastructure for Stark, said the company is in early stages of evaluating the site and no final decision has been made
The county and nearby counties
Disclosed figures
nothing disclosed by 2 records
Power, water, jobs and tax
| Figure | Disclosed total | Disclosed | Not disclosed | Basis | |
|---|---|---|---|---|---|
| Power | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Water, stated per day | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Water, stated per year | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Permanent jobs | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records | |
| Tax each year | Not disclosed | 0 | 2 | Not disclosed by any of the 2 records |
Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.
By what the facilities are for
| Use | Records | Power | Water | Jobs | Tax each year | |
|---|---|---|---|---|---|---|
| Not disclosed | 2 | Not disclosed | Not disclosed | Not disclosed | Not disclosed | Not disclosed: power, water, jobs, tax each year |
A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.
What the facilities are for
No source on file states what any of the 2 tracked facilities in Hallam are for.
How the facilities are cooled
No source on file states how any of the 2 tracked facilities in Hallam are cooled.
Cite this page
Data Center Record, "Data centers in Hallam, Lancaster County, Nebraska", https://datacenterrecord.org/states/ne/lancaster-county/hallam, updated September 18, 2026.
Cite this page
Data Center Record, "Data center records in Hallam, Lancaster County, Nebraska", https://datacenterrecord.org/states/ne/lancaster-county/hallam. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.
The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.
The rows here are part of the Nebraska export.
For researchers
- Place id
- us/ne/lancaster-county/hallam
- Level
- city
- Census GEOID
- Not disclosed
- Rating value
- Not disclosed
- Scale word
- Not disclosed