Data Center Record.

Data centers in Nevada

Nevada has 13 data center sites, 0 buildings where disclosed on the record: 8 running, 4 proposed and 1 stalled or cancelled. Most are in Clark County (7) and Storey County (3), and records are in 3 of 17 counties. The largest proposal is Apple Reno Data Center in Washoe County; it is reported.

Nevada decides case by case. From the state's own rule: Nevada approved $17.6 million in tax breaks for 9 companies, including data center partners, August 10, 2026.

1 site the EPA's registry shows and no record has verified is on the map apart from the count. What not yet verified means.

How to read this page. Every count comes from the records on this page and links to where it is counted. Nothing is published until a person reads its source, and a figure no source gives reads Not disclosed; nothing is estimated. A rating changes only when a person sets it.

Projects and campuses on the record

Facility and countyStageOperatorPower (MW)Latest entry
Apple Reno Data Center Reno, Washoe CountyProposedApple20
Novva North Las Vegas data center North Las Vegas, Clark CountyProposedNovva Data Centers100
Las Vegas Data Center Expansion Las Vegas, Clark CountyProposedSwitch80 acre federally owned parcel planned for data center knpr.org (opens in a new tab) local outlet reported September 9, 2026
Rural Nevada Data Center Storey CountyProposed In courtNV Energy sued Tract in late July over arbitration requirements and power needs thisisreno.com (opens in a new tab) news outlet reported August 19, 2026
Boulder City BLM Land Data Center Boulder City, Clark CountyStalled or cancelled167The Center for Biological Diversity and local residents successfully halted the development of the proposed data center on public land near Boulder City ksut.org (opens in a new tab) local outlet reported October 6, 2026
Google Henderson data center Henderson, Clark CountyRunningGoogle
Google Storey County data center Storey CountyRunningGoogle
Novva Las Vegas data center Las Vegas, Clark CountyRunningNovva Data Centers
Vantage Reno Reno, Washoe CountyRunningVantage Data Centers
Switch Las Vegas campus Las Vegas, Clark CountyRunningSwitchSwitch acquired approximately 176 acres at Apex Industrial Park in North Las Vegas fox5vegas.com (opens in a new tab) local outlet reported September 15, 2026

A blank cell means not disclosed by any source on file. Power is the developer's figure or a permit's, each linked on the record. All 13 Nevada projects.

Every Nevada record 13 records, and 1 site not yet verified listed apart · sort by any column · blank cell: not disclosed

RecordPlaceStageOperatorMWBasisLocatedTierVerified
Apple Reno Data CenterReno, WashoeProposedApple20centroid12026-10-21
Novva North Las Vegas data centerNorth Las Vegas, ClarkProposedNovva Data Centers100not located12026-10-21
Novva Data CentersStoreyNot yet verifiedNovva Data CentersEPA registry22026-10-20
Boulder City BLM Land Data CenterBoulder City, ClarkStalled or cancelled167third party estimatecentroid12026-10-06
Google Henderson data centerHenderson, ClarkRunningGooglecentroid22026-09-17
Google Storey County data centerStoreyRunningGooglecentroid22026-09-17
Novva Las Vegas data centerLas Vegas, ClarkRunningNovva Data Centerscentroid22026-09-17
Vantage RenoReno, WashoeRunningVantage Data Centerscentroid12026-09-17
Switch Las Vegas campusLas Vegas, ClarkRunningSwitchcentroid22026-09-17
Las Vegas Data Center ExpansionLas Vegas, ClarkProposedSwitchcentroid12026-09-25
Rural Nevada Data CenterStoreyProposedcentroid42026-10-07
Novva Tahoe Reno data centerReno, WashoeRunningNovva Data Centerscentroid22026-09-17
DataBank Las Vegas data centerLas Vegas, ClarkRunningDataBankcentroid22026-09-17
Switch Tahoe Reno campusStoreyRunningSwitchcentroid12026-09-17

Tier 1: an official or company source. Tier 2: a news report resolving to the outlet's own page. Located: a site coordinate from a permit, a parcel or an address, or the county or town centroid. Verified: the last day a person read the source. A blank cell means not disclosed by any source on file.

Every Nevada county (17)

3 of 17 counties have a record. A county without one is listed, not linked, until its first published record.

CountyCensus GEOIDProjectsRulesHow it treats data centers
Clark County3200371
Storey County3202931
Washoe County3203131
Nye County3202301closed

A blank rating cell means no person has set one for the county. A county without a record is listed, not linked.

13 counties with no records yet
  • Carson City
  • Churchill County
  • Douglas County
  • Elko County
  • Esmeralda County
  • Eureka County
  • Humboldt County
  • Lander County
  • Lincoln County
  • Lyon County
  • Mineral County
  • Pershing County
  • White Pine County

The rules in Nevada 5 rows · rating rests only on a binding act in force

What the state and its counties and cities have decided. Each row is rated by what it has decided, open, case by case, restrictive or closed, never by whether that is good or bad.

BodyLevelRatingIn force untilLatest actActsVerified
Nevadastatecase by caseNevada approved $17.6 million in tax breaks for 9 companies, including data center partners. 8newsnow.com (opens in a new tab) local outlet Aug 10, 202632 acts on this row
Every act on the Nevada row
  1. moratorium

    Nevada interim committee advanced bill to pause data centers statewide and eliminate all tax breaks

    reviewjournal.com (opens in a new tab) local outlet

  2. litigation

    Interior Board of Land Appeals Administrative Judge David Gunter granted a stay that prevented construction while consolidated appeals from Boulder City and environmental groups were processed.

    reviewjournal.com (opens in a new tab) local outlet

  3. event

    Governor Joe Lombardo signed an executive order requiring data center companies to pay to fund K-12 education instead of receiving a tax break they had for a decade, effective on or after September 19, 2026

    ktnv.com (opens in a new tab) local outlet

  4. event

    Nevada Governor Joe Lombardo announced tighter conditions for data centers seeking state tax abatements, including requirements concerning taxes, energy costs and the impact of projects on water, infrastructure and communities.

    newsweek.com (opens in a new tab) national outlet

  5. event

    Governor Lombardo issued executive order on Friday requiring new data center tax break applicants to pay into a Local School Support Tax

    thecentersquare.com (opens in a new tab) national outlet

  6. event

    Gov. Joe Lombardo signed executive order on September 18 directing Governor's Office of Economic Development to draft community support commitment by November 6 with elimination of local school tax exemptions for data center developers.

    reviewjournal.com (opens in a new tab) local outlet

    Also reported by 2 sources
  7. event

    Governor Joe Lombardo signed Executive Order 2026-005 on September 18, 2026 establishing the Nevada Standard for Responsible Data Center Development.

    gov.nv.gov (opens in a new tab) primary source

    Also reported by 10 sources
  8. event

    2025 Legislature expanded GOED Board authority to deny applications, approve for lesser amount, or impose conditions

    elkodaily.com (opens in a new tab) news outlet

  9. event

    Nevada Gov. Joe Lombardo signed an executive order on Friday, September 19, 2026 aimed at placing guardrails on data centers, stating that developers should shoulder the costs to electrical grids and water systems in the communities that host them

    knpr.org (opens in a new tab) local outlet

    Also reported by 1 source
  10. filing

    Rep. Dina Titus introduced the Public Lands Accountability Act on September 18, 2026, in response to the Trump administration's approval of a data center in Boulder City

    reviewjournal.com (opens in a new tab) local outlet

  11. event

    Data center applications seeking partial tax abatement cannot go before the GOED Board unless the developer agrees to pay the Local School Support Tax in full and executes a binding Community Support Commitment.

    kolotv.com (opens in a new tab) local outlet

  12. event

    The 2015 Nevada legislation establishing data center tax abatements passed with wide bipartisan support and was signed by Republican Governor Brian Sandoval

    nevadacurrent.com (opens in a new tab) local outlet

  13. event

    Nevada governor took steps Friday to curtail tax breaks and place other guardrails on data centers.

    law360.com (opens in a new tab) news outlet

  14. approval

    Public Utilities Commission of Nevada approved permits for two behind the meter gas plants to power data centers until NV Energy can permanently supply the campuses.

    rtoinsider.com (opens in a new tab) trade press

    Also reported by 2 sources
  15. event

    Clark County Education Association unveiled an eight point plan to reshape data center tax incentives.

    knpr.org (opens in a new tab) local outlet

  16. event

    Clark County Education Association unveiled plan to end abatement of local schools support tax for data centers

    nevadacurrent.com (opens in a new tab) local outlet

  17. moratorium

    Interim revenue committee of lawmakers voted to draft a bill to pause data centers across Nevada and repeal tax abatements

    reviewjournal.com (opens in a new tab) local outlet

  18. event

    Nevada Senate Bill from 2015 sponsored by Aaron Ford created data center tax break program

    2news.com (opens in a new tab) local outlet

  19. ordinance

    Lyon County Commission voted 5-0 directing staff to return with updates and revisions on data center ordinance specific to residential setbacks, building specifications and provisions on water and cooling systems

    nnbw.com (opens in a new tab) local outlet

  20. event

    State Sen. Nicole Cannizzaro requested a 2027 bill draft to regulate data centers, including requirements for operators to cover infrastructure costs, prohibition of NDAs, union labor requirements, environmental reviews, and closed loop water systems.

    ktnv.com (opens in a new tab) local outlet

  21. litigation

    Interior Board of Land Appeals halted a 167 MW data center approval on September 1, 2026

    enr.com (opens in a new tab) news outlet

    Also reported by 1 source
  22. groundbreaking

    Core Upgrades Project breaks ground with ceremony at Jean Airport in September 2026

    lasvegassun.com (opens in a new tab) local outlet

  23. litigation

    Boulder City appeals to the Department of Interior Board of Land Appeals, which should overturn the BLM's decision

    lasvegassun.com (opens in a new tab) local outlet

  24. event

    BLM concluded that the new project was substantially the same as the original project and elected not to require a new environmental review

    lasvegassun.com (opens in a new tab) local outlet

  25. approval

    Nevada approved $17.6 million in tax breaks for 9 companies, including data center partners.

    8newsnow.com (opens in a new tab) local outlet

  26. moratorium

    Nevada lawmakers moved to draft legislation for a potential moratorium on new data center development during a legislative revenue committee meeting in late August

    news3lv.com (opens in a new tab) local outlet

  27. approval

    BLM approved the Townsite Data Center in June without preparing a new environmental assessment, reusing 2023 review of a 19 MW solar project

    enr.com (opens in a new tab) news outlet

  28. event

    In 2025, the Nevada Legislature expanded the GOED Board's authority to deny an application, approve it for a lesser amount, or impose conditions on its approval

    fox5vegas.com (opens in a new tab) local outlet

  29. event

    Southern Nevada Water Authority banned evaporative cooling for the region's data centers in 2023.

    carsonnow.org (opens in a new tab) local outlet

  30. moratorium adopted

    Southern Nevada Water Authority imposed an evaporative cooling moratorium beginning with a board vote in 2021

    ktnv.com (opens in a new tab) local outlet

  31. event

    Nevada Legislature established renewable portfolio standard in 2019 requiring 50 percent renewable energy by 2030

    nevadacurrent.com (opens in a new tab) local outlet

  32. event

    Abatement legislation passed in 2015 required Governor's Office of Economic Development to grant tax abatements for data centers meeting statutory employment, wage and investment thresholds without protections for energy and water use.

    rgj.com (opens in a new tab) news outlet

Last verified September 27, 2026.

322026-09-27
Boulder Citycitynot ratedCitizens initiative filed asking Boulder City to require voter approval before any future data center approval within city limits. nationofchange.org (opens in a new tab) national outlet Reported Sep 92 acts on this row
Every act on the Boulder City row
  1. filing

    Citizens initiative filed asking Boulder City to require voter approval before any future data center approval within city limits

    nationofchange.org (opens in a new tab) national outlet

  2. denial

    Boulder City Planning Commission voted in May 2026 against allowing data centers under city land use rules

    nationofchange.org (opens in a new tab) national outlet

Last verified September 23, 2026.

22026-09-23
Nye CountycountyclosedNye County has banned the development of data centers. nevadacurrent.com (opens in a new tab) local outlet Sep 18, 20262 acts on this row
Every act on the Nye County row
  1. event

    Nye County has banned the development of data centers

    nevadacurrent.com (opens in a new tab) local outlet

  2. moratorium adopted

    Nye County commissioners approved land use code change banning data centers in Pahrump area

    fox5vegas.com (opens in a new tab) local outlet

Last verified September 18, 2026.

22026-09-18
Renocityrestrictive until August 31, 20272027-08-31Reno extended the moratorium through August 2027 and determined to adopt new regulations at that time. nnbw.com (opens in a new tab) local outlet Sep 7, 20262 acts on this row
Every act on the Reno row
  1. moratorium extended

    Reno extended the moratorium through August 2027 and determined to adopt new regulations at that time

    nnbw.com (opens in a new tab) local outlet

  2. moratorium adopted

    Reno City Council approved a 30 day moratorium on accepting and processing new data center applications in June with 6-1 vote

    nnbw.com (opens in a new tab) local outlet

Last verified September 7, 2026.

22026-09-07
Storey Countycountynot ratedNevada Public Utilities Commission approved two temporary natural gas fired power projects totaling 362 MW in Storey County for data centers. news.constructconnect.com (opens in a new tab) news outlet Reported Sep 211 act on this row
Every act on the Storey County row
  1. approval

    Nevada Public Utilities Commission approved two temporary natural gas fired power projects totaling 362 MW in Storey County for data centers

    news.constructconnect.com (opens in a new tab) news outlet

Last verified September 21, 2026.

12026-09-21

Reported: the source's date; the item names no day of its own. A month with no day: the source names the month and not the day. A rating rests only on a binding act in force; "not rated" means no person has set one. A blank cell means the record holds nothing for it.

Nevada laws and the full scorecard

Bills and laws in Nevada

2 signed into law, 2 bills tracked

2 bills tracked in the Nevada legislature, 2 of them signed into law, grouped by where each stands. A row opens its own page; the Nevada laws page has what each law requires.

No official summary on file for 1 of these 2 measures; each row links to the legislature's page for the text.

Signed into law 2

2 bills tracked, 2 signed · LegiScan, CC BY 4.0

NumberSessionStatusDateTitle
S.B. 547 80th Legislature (2019) Signed 2019-06-13 Revises provisions relating to providers of new electric resources. (BDR 58-913)
S.B. 170 78th Legislature (2015) Signed 2015-06-09 Provides for a partial abatement of certain taxes for new or expanding data centers and related businesses in this State. (BDR 32-765)

2 bills tracked in Nevada; 36th Special Session (2025), legislature adjourned; last checked October 26, 2026. The last check found no bill not already tracked; the 2 tracked bills stand. Search terms: data center, data centre, large load, hyperscale, computing facility, server farm, high load factor (indirect), energy intensive facility (indirect), large electric load (indirect), digital asset mining (indirect), cryptocurrency mining (indirect), qualified technology facility (indirect), colocation (indirect), moratorium (with another term), sales tax exemption (with another term). The search on LegiScan. (opens in a new tab)

Bill data from LegiScan (opens in a new tab), licensed CC BY 4.0 (opens in a new tab). The record chooses the bills, writes each stage in its own words and cites the legislature's own page for every bill.

How this state's members voted

H.R. 9340, Ratepayer Protection Act: U.S. House of Representatives, roll call 312, September 16, 2026. On Motion to Suspend the Rules and Pass, as Amended. Passed, 417 to 3. Nevada's members: 4 yea, 0 nay. How each member voted

MemberPartyPosition
Amodei (NV)RYea
HorsfordDYea
Lee (NV)DYea
TitusDYea

A blank party cell means the clerk's roll gives none.

H.R. 9340, Ratepayer Protection Act: U.S. Senate, roll call 254, September 30, 2026. On Cloture on the Motion to Proceed H.R. 9340. Cloture on the Motion to Proceed Rejected, 57 to 43. Nevada's members: 0 yea, 2 nay. How each member voted

MemberPartyPosition
Cortez Masto (D-NV)DNay
Rosen (D-NV)DNay

A blank party cell means the clerk's roll gives none.

Positions as the clerk records them. How bills and votes are recorded.

What happened

The full Nevada timeline, year by year

What was said

WAVR Technologies targeting 2028 for consumer ready version of atmospheric water harvesting technology.
Rich Sloan, CEO of WAVR Technologies · October 2, 2026 · paraphrased · KSNV (opens in a new tab) local outlet
Rep. Dina Titus pushing Public Lands Accountability Act to ensure data center projects on public lands adhere to NEPA
Dina Titus, U.S. Representative · September 29, 2026 · paraphrased · Nevada Public Radio KNPR (opens in a new tab) local outlet

Every Nevada statement, by speaker (71)

67 more on this page, one per speaker and claim; 71 statements in all

Ronnie Najarro, AFP NV State Director, praised Governor Lombardo's executive order reforming the state's data center tax abatement program, which requires companies receiving incentives to cover their own power costs, meet local water standards, and stop diverting revenue from Nevada's schools

Americans for Prosperity Nevada State Director americansforprosperity.org (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: americansforprosperity.org (opens in a new tab).

Alexander Marks, Nevada State Education Association, stated that dedicating some revenue to public education does not make bad policy good policy, opposing the order's approach

ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

John Vellardita, Clark County Education Association Executive Director, called the executive order a very important first step and noted that every dollar to K-12 education is meaningful

ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

Clark County Education Association represents 18,000 teachers and released an 8 point plan regarding data center requirements including water protection, power grid protection, workforce development, and reviewing property tax abatement

ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

Khara Boender, Data Center Coalition Director of Government Affairs for the West, said the group thanks Governor Lombardo for his leadership but has concerns that some policies create additional hurdles to data center development in Nevada

FOX5 Vegas (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: FOX5 Vegas (opens in a new tab).

Aaron Ford said he wants guardrails and separate conversations on AI and data centers, including possible age restrictions, content restrictions, and parental controls

Nevada Attorney General and Democratic gubernatorial candidate KUNR Public Radio (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KUNR Public Radio (opens in a new tab).

Aaron Ford, Democratic gubernatorial candidate, said local communities should not be forced to have data centers if they don't want them and that local say is paramount

Nevada Attorney General and Democratic gubernatorial candidate KUNR Public Radio (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KUNR Public Radio (opens in a new tab).

Google's Nevada Clean Energy Fund investment will support the Residential Energy Upgrade Program, bringing free weatherization and energy efficiency improvements to households in data center communities.

blog.google (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: blog.google (opens in a new tab).

Google announced a $10 million Energy Impact Fund to support energy innovation and affordability in Nevada, with $5 million to the Nevada Clean Energy Fund.

blog.google (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: blog.google (opens in a new tab).

Lombardo's campaign did not give a direct yes or no answer but said that the state already has strong measures in place to shield ratepayers from any increases associated with data centers.

Republican candidate for Governor, Nevada thenevadaindependent.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: thenevadaindependent.com (opens in a new tab).

Many data center companies declined or were unresponsive to media requests for facility tours and interviews about their operations

Channel 13 News ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

Desert Research Institute published a paper on data centers in Nevada that was cited in news reporting

Channel 13 News ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

There is no single authoritative agency that tracks data center information in Nevada or monitors their impact to the environment and community

Channel 13 News ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

Local communities express concerns that data centers demand large quantities of land and resources but public access and transparency about their operations is very limited

Channel 13 News ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

Channel 13 conducted a weeklong series on data centers in Southern Nevada starting September 11, 2026 to explore industry impacts and community concerns

Channel 13 News ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

New or expanding data centers receive a 75 percent abatement on personal property tax and pay a reduced sales and use tax rate of 2 percent for 10 to 20 years

Clark County Education Association News From The States (opens in a new tab) national outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: News From The States (opens in a new tab).

Nevada experiencing data center boom with massive power demand

Geneva Zoltek, climate reporter ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

CCEA said Nevada current incentive model does not provide enough public benefit in exchange for tax breaks offered to data center projects

Clark County Education Association KSNV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSNV (opens in a new tab).

Clark County Education Association on Tuesday unveiled eight point plan for data center development based on accountability, transparency and community partnership

KSNV (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KSNV (opens in a new tab).

Joe Lombardo, Republican incumbent Nevada Governor, states average data center consumes less water than 25 to 50 homes and does not raise resident utility rates, and calls data centers the new gold rush

incumbent Republican Nevada Governor kolotv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kolotv.com (opens in a new tab).

Ford plans to audit data centers to verify they are upholding promises on water usage, electricity, and labor

Democratic gubernatorial candidate KTVN (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KTVN (opens in a new tab).

Aaron Ford, Democratic candidate for Nevada Governor, says he will put brakes on tax giveaways to data centers, require them to use own water and green energy, and audit state tax abatements to ensure compliance

kolotv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kolotv.com (opens in a new tab).

Aaron Ford, Nevada Democratic candidate for governor, calls for pausing all data center tax abatements going forward

Democratic gubernatorial candidate KTVN (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: KTVN (opens in a new tab).

Lombardo campaign ad claims Aaron Ford sponsored bill that gave tax breaks to data centers with no restrictions on water or power consumption

kolotv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kolotv.com (opens in a new tab).

President Trump praised data centers as essential for community wealth and lowering taxes, warning communities opposing them risk poverty, crime and squalor

kolotv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kolotv.com (opens in a new tab).

Nicole Cannizzaro, Nevada Democratic AG candidate, released plan on data centers requiring operators cover infrastructure costs, ban cost shifting to ratepayers, ban nondisclosure agreements, require local input on siting, require environmental reviews, require transparency on power and water consumption, and ensure behind the meter facilities get PUC oversight

Nevada Democratic Attorney General candidate kolotv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: kolotv.com (opens in a new tab).

Data centers have emerged as an issue in Nevada's 2026 attorney general race, with residents in Boulder City, Henderson, Pahrump, and Reno calling for moratoriums or stronger rules.

Rebecca Gill, UNLV associate professor ktnv.com (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: ktnv.com (opens in a new tab).

On August 19, 2026, Democrat Attorney General Aaron Ford said he will pause new data center tax breaks as governor

Nevada Attorney General Mesa Valleys Progress (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: Mesa Valleys Progress (opens in a new tab).

Also reported by: Nevada Current (opens in a new tab) local outlet .

Said again: September 18, 2026 ( Nevada Current (opens in a new tab) local outlet ).

Aaron Ford said on August 19, 2026, that he will pause new data center tax breaks as governor to ensure Nevadans get their money's worth

Nevada Attorney General and Democratic gubernatorial candidate The Ely Times (opens in a new tab) news outlet
Context & source notes

Provenance: Paraphrased; content date; reported from elsewhere.

Primary source: The Ely Times (opens in a new tab).

"The facility would use a closed-loop cooling system that does not consume water on a daily basis beyond restrooms and kitchenettes."
Steven Roberts, Vice President of Construction Development, Switch Clark County Commission hearing KOLO 8 News Now (opens in a new tab) local outlet project record
Context & source notes

Provenance: Quoted; content date; reported from elsewhere.

Setting: Clark County Commission hearing.

Primary source: KOLO 8 News Now (opens in a new tab).

Sean McKenna, executive director of the Division of Hydrologic Sciences at the Desert Research Institute, stated that Nevada has potential but faces challenges balancing data center expansion with other stakeholder priorities

Sierra Nevada Ally (opens in a new tab) local outlet
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: Sierra Nevada Ally (opens in a new tab).

DataBank CEO Raul K. Martynek said the purchase aligns with DataBank's strategy of owning the largest edge data center footprint in the United States.

EdgeIR (opens in a new tab) news outlet project record
Context & source notes

Provenance: Paraphrased; said in the source itself.

Primary source: EdgeIR (opens in a new tab).

On the November 3, 2026 ballot in Nevada: Governor (4), U.S. House, District 1 (4), U.S. House, District 2 (3), U.S. House, District 3 (3), U.S. House, District 4 (4); 3 of 18 candidates with a statement on data centers on the record. Every candidate.

Already running in Nevada

8 sites are serving load, 4 of them in Clark County.

See the 8 running sites
  1. DataBank Las Vegas data center Las Vegas, Clark County Running · Operational since 2023 (3 years)
  2. Google Henderson data center Henderson, Clark County Running · Operational since 2020 (6 years)
  3. Google Storey County data center Storey County Running · Operational since 2020 (6 years)
  4. Novva Las Vegas data center Las Vegas, Clark County Running
  5. Novva Tahoe Reno data center Reno, Washoe County Running · Operational since 2023 (3 years)
  6. Switch Las Vegas campus Las Vegas, Clark County Running · Operational since 2000 (26 years)
  7. Switch Tahoe Reno campus Storey County Running · Operational since 2017 (9 years)
  8. Vantage Reno Reno, Washoe County Running

Questions about Nevada data centers

How many data center projects are on the record in Nevada?

13 projects are on the record in Nevada: 4 reported, 8 running, 1 cancelled and 1 not yet verified. Each is listed under Projects with its status history and sources. Resources: the questions people ask about data centers

answered from the rows above

Where in Nevada are they?

Records are in 3 counties: Clark County (7), Storey County (3) and Washoe County (3). The county table lists every county with its count, zero included. Resources: the questions people ask about data centers

answered from the rows above

How much power is disclosed for data centers in Nevada?

167 MW is disclosed across 1 of 13 records: Boulder City BLM Land Data Center (167 MW, third party estimate, source (opens in a new tab)). The other 12 records have not disclosed capacity. Resources: the questions people ask about data centers

answered from the rows above

How much water do data centers in Nevada say they will use?

Not disclosed. None of the 13 records on file for Nevada states a water figure. Resources: the questions people ask about data centers

answered from the rows above

Who is building data centers in Nevada?

6 developers are named on the record: Novva Data Centers (4 records), Switch (3 records), Google (2 records), Apple, DataBank and Vantage Data Centers. 1 record names no developer; each name above opens the record, where the developer's source is listed. Resources: the questions people ask about data centers

answered from the rows above

Which counties and cities in Nevada have rules about data centers?

4 county and city rows are on the record, 2 of them rated: Nye County is rated closed: Nye County has banned the development of data centers, September 18, 2026, source (opens in a new tab), Reno is rated restrictive: Reno extended the moratorium through August 2027 and determined to adopt new regulations at that time, September 7, 2026, source (opens in a new tab) and Boulder City has no rating yet: Citizens initiative filed asking Boulder City to require voter approval before any future data center approval within city limits (reported September 9, 2026, source (opens in a new tab)). The state's own row is rated case by case, with 32 dated acts listed under the scorecard. Resources: the questions people ask about data centers

answered from the rows above

What is proposed or being built near me in Nevada, by county?

4 records are not yet running. Clark County: Novva North Las Vegas data center (reported) and Las Vegas Data Center Expansion (reported); Storey County: Rural Nevada Data Center (reported); and Washoe County: Apple Reno Data Center (reported). A county name opens its page with the map and every record there. Resources: the questions people ask about data centers

answered from the rows above

What has the state of Nevada itself decided?

2 state laws are on the record: S.B. 547 (signed, June 13, 2019, source (opens in a new tab)) and S.B. 170 (signed, June 9, 2015, source (opens in a new tab)). The state's own scorecard row carries 32 dated acts, the newest reported September 24, 2026; the laws page has what each law requires in the words of its text. Resources: the questions people ask about data centers

answered from the rows above

Disclosed figures

167 MW power

summed only where a record disclosed the figure

FigureDisclosed totalDisclosedWithout a figureBasis
Power167 MW1121 third party estimate
Water, stated per day013
Water, stated per year013
Permanent jobs013
Tax each year013

A blank cell means no record in Nevada disclosed the figure. Third party figures on the same metrics are listed apart below; a figure a project disclosed about itself is never mixed with them.

FigureDisclosed totalDisclosedWithout a figureBasis
Power167 MW1121 third party estimate
Water, stated per day013
Water, stated per year013
Permanent jobs013
Tax each year013

A blank total means no record disclosed the figure; the count without one says how many.

Summed only where a record disclosed the figure; a record with no figure adds nothing and is counted as not disclosed. Water is summed per day and per year separately, as the sources stated it, and never converted. A tax claim given as a range is summed at both ends.

The disclosed totals are in the table above.

No source on file states what any of the 13 tracked facilities in Nevada are for. 1 site not yet verified is named apart and is not in that number.

What each use disclosed

UseRecordsPowerWaterJobsTax each year
No stated use13167 MW

A blank cell means no record with that use disclosed the figure.

A record that lists several uses counts once under each. Each cell is the sum over the records with that use, disclosed rows only.

MethodFacilitiesShare of facilities
Closed loop liquid18%
No stated cooling type1292%

13 facilities in Nevada. 1 site not yet verified is named apart and is not counted here. A facility carries one cooling method; nothing here is estimated.

Sources read for Nevada

15 sources

15 sources are read for Nevada:

Newspapers
Las Vegas Review-Journal
Public broadcaster
Nevada Public Radio KNPR
Utility commission dockets
Public Utilities Commission of Nevada
Economic development
Nevada Governors Office of Economic Development
Search feeds
11 news searches
Every feed, with its kind and tier

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Only what a source states, with its basis. Nothing is estimated, and a figure no source gives reads not disclosed.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Commercial, enterprise, financial or AI training use needs a commercial license. Prose stays under copyright.
Cite this page Data Center Record, "Data centers in Nevada", https://datacenterrecord.org/states/nv, updated October 21, 2026. CSV · JSON · GeoJSON
Cite this page

Data Center Record, "Data center records in Nevada", https://datacenterrecord.org/states/nv. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
State code
NV
Rating of the state's own row
Case by case
Count by status
reported 4, running 8, cancelled 1, not yet verified 1
Located records
0 located, 12 at a centroid, 1 without coordinates

Researcher view · Nevada · 13 data center sites, 0 buildings where disclosed, 5 rule rows, 2 bills · basis and source tier on every row · verified October 21, 2026