Boulder City Eldorado Valley BLM Data Center Proposal

Street address U.S. Route 95 and Eldorado Valley Dr, Boulder City, NV 89005, Clark County assessor parcel Exact, on the parcel blm.gov (opens in a new tab)

Overview, regulatory gates and specifications

A developer withdrew a data center project in Boulder City and signaled plans to move the project to federal land. [3] Filings on the record specify 1 planned or operational building. [3] The Center for Biological Diversity and local residents successfully halted the development of the proposed data center on public land near Boulder City [23]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
zoning application

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: U.S. Route 95 and Eldorado Valley Dr, Boulder City, NV 89005.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed Reported by others: 167 MW (Las Vegas Sun (opens in a new tab)). Their figure, not the record's.
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building permitted
blm.gov (opens in a new tab)
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Switch Inc. as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Tom Gaitens

senior adviser at Humans First

DID Recorded statement at Nevada Public Radio KNPR (October 7, 2026)
SAID Tom Gaitens, senior adviser at Humans First, calls data center development an apolitical issue where everyone drinks water, uses electricity and wants their voice heard (October 7, 2026) knpr.org (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Switch Inc.
UTILITIES
Electric utility: Not disclosed

View all 5 statements on the record in Nevada →

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Boulder City Eldorado Valley BLM Data Center Proposal.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 1 building zoning application
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

May 20, 2026 Boulder City, NV Boulder City Planning Commission Denial of Eldorado Valley AI Data Center Boulder City Planning Commission 3 clips

On May 20, 2026, the Boulder City Planning Commission voted unanimously to deny an application for a controversial AI data center in Eldorado Valley after residents packed the chamber opposing desert conservation land use and Colorado River water draw.

  1. FOX5 Las Vegas Broadcast Report Broadcast Report transcribed from local broadcast report
    "Agenda that brought them there, whether or not to move plans on a controversial AI data center forward, something many residents have said they don't want. Fox five's kim passoth has been following this story. She's back with us right now with more developments from tonight. Kim yeah. Tom. At tonight's meeting, the planning commission heard all of that opposition, though the vote was not unanimous. After a presentation from the developer and much public debate, they decided to deny the developer's application. I asked you guys to really"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "To the mic during public comment, speaking to the Boulder City Planning Commission. So let's set down the hammer, because absolutely everyone has said they don't want this. We'd like you to just deny it before the meeting. Those opposed also wanted to make their voices heard, taking to the streets. I think history has taught us that a lot of corporations will always put profit over people here in this community. I want to put the people first. Even this dog was dressed in a no data center shirt. When we"
  3. FOX5 Las Vegas Broadcast Report Broadcast Report transcribed from local broadcast report
    "Light and that's not accurate. Our wind mostly blows from where the data center will be. Nobody wants to sit through a city council meeting. No one knows what's going on. The developer of the town site, solar two project, did make a presentation on their amended plans. After rounds of community feedback, but ultimately the commission shared their thoughts and voted against the developer's proposal. This is the hottest topic, one of the hottest topics in the country. On top of our lack of water. Regardless of how I"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    The Center for Biological Diversity and local residents successfully halted the development of the proposed data center on public land near Boulder City

    [23] ksut.org

  2. (source date; the content gives no date of its own)

    Skylar Opportunities LLC withdrew application for 1000 megawatt data center on 680 acres of federal land near Henderson due to city planned urban development efforts in same area

    [9] reviewjournal.com

  3. (source date; the content gives no date of its own)

    The Boulder City data center permit was approved by the Bureau of Land Management after determining a previous environmental review for a solar project was sufficient, and is now on hold after an administrative judge granted a stay

    [19] reviewjournal.com

  4. (source date; the content gives no date of its own)

    Townsite Solar 2 LLC asked BLM in 2025 to amend right of way grant to build data center instead of solar

    [8] nationofchange.org

  5. · Status: stalled or cancelled (source date; the content gives no date of its own)

    Townsite Solar 2 LLC received BLM approval in 2023 for solar power and battery storage facility on 88.5 acre parcel 25 miles southeast of Las Vegas

    [8] nationofchange.org

  6. (source date; the content gives no date of its own)

    Townsite Solar project, owned by Skylar Capital Management hedge fund based in Houston, originally applied for solar project but changed plans to data center

    [22] wyomingpublicmedia.org

  7. · In court (source date; the content gives no date of its own)

    Townsite Solar data center project on 80 acre BLM public land in Nevada received temporary halt from Interior Board of Land Appeals stay pending environmental review and public input

    [22] wyomingpublicmedia.org

  8. (source date; the content gives no date of its own)

    Planned commercial operation of Townsite Data Center in second quarter of 2028

    [11] enr.com

6 earlier entries
  1. (source date; the content gives no date of its own)

    Planned Townsite Data Center construction scheduled for first quarter of 2027

    [11] enr.com

  2. · cancelled (source date; the content gives no date of its own)

    Townsite Data Center has planned capacity of 167 MW backup generation

    [11] enr.com

  3. · stalled (content date)

    A 167 MW data center approved on BLM public land near Boulder City was put on hold after an appeal and a stay issued by the Interior Board before construction began.

    blm.gov (opens in a new tab) primary source

  4. (source date; the content gives no date of its own)

    Developer is now proposing to add a massive data center capable of demanding as much as 167 megawatts of electricity to the project

    [7] lasvegassun.com

  5. (source date; the content gives no date of its own)

    BLM authorized Townsite Solar 2 to use approximately 80 acres of federal land for a 19 megawatt solar generating facility and 35 megawatt battery storage system in 2023

    [7] lasvegassun.com

  6. · cancelled (content date)

    A developer withdrew a data center project in Boulder City and signaled plans to move the project to federal land.

    blm.gov (opens in a new tab) primary source

Every event in order

20 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  3. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  4. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  5. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  6. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  7. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  8. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  9. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  10. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  11. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  12. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  13. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  14. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  15. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

See all 17 corrections for this record (2 more) →

Every correction on the record is on the corrections page.

Nearest data centers in Nevada

Verified data center records in Nevada within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Google Henderson Data Center Henderson, Clark County 8 mi Running Google 150 MW
Flexential Las Vegas Pollock Data Center (LAS01 / LAS03) Las Vegas, Clark County 16 mi Running Flexential 7.4 MW
Switch The CORE Campus (Las Vegas) Las Vegas, Clark County 19 mi Running Switch Inc. 500 MW
EdgeConneX Las Vegas Data Center (LAS01) Las Vegas, Clark County 19 mi Running EdgeConneX 6 MW
DataBank Las Vegas Data Center (LAS1) Las Vegas, Clark County 21 mi Running DataBank 6 MW
Flexential North Las Vegas Data Center (LAS02) North Las Vegas, Clark County 25 mi Running Flexential 6 MW

Blank cell: not disclosed by any source on file.

Comparisons

2 metrics with more than one figure

Every figure on the record for the same thing, each with who gave it, its date and its basis.

Capacity at full buildout

1 figure, 1 source
Show each source's words
  • 167 MW, Las Vegas Sun: The data center would demand 167 megawatts, more than all of Boulder City uses on the hottest summer days and more than three times the average consumption rate throughout the year

Project footprint

1 figure, 1 source
Show each source's words
  • 80 acre, alaska-native-news.com: Townsite Data Center is 80 acres

Common questions about Boulder City Eldorado Valley BLM Data Center Proposal

Answered directly from the verified filings and local actions on this page.

Who is building Boulder City Eldorado Valley BLM Data Center Proposal?

Switch Inc. is the developer. No construction contractor is named on the record yet.

Who will use Boulder City Eldorado Valley BLM Data Center Proposal?

Not disclosed. No source on file names a tenant, says whether the site is single or multi tenant, or states what it is for. The record keeps the use as not disclosed until one does; see Who it serves.

How much power and water does Boulder City Eldorado Valley BLM Data Center Proposal say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Boulder City Eldorado Valley BLM Data Center Proposal stand today?
What is still unknown about Boulder City Eldorado Valley BLM Data Center Proposal?

Not disclosed by any source on file: how much power it needs, how much water it would use, how loud it would be, jobs once it runs, tax it would pay each year, who is constructing it, how much land, where its power comes from, grid connection, how it is cooled. No missing primary document is listed for this record yet; What the record lacks is where one appears when a person names it.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Developer Pulls Out of Hyperscale Data Center in Nevada - GovTech (opens in a new tab), GovTech, September 24, 2026, national outlet
  2. Contested Data Center Project on BLM Land in Nevada Put on Hold - RTO Insider (opens in a new tab), RTO Insider, September 2, 2026, trade press
  3. Developer withdraws Boulder City data center, signals move to federal land - Nevada Current (opens in a new tab), Nevada Current, July 7, 2026, local outlet
  4. Boulder City Council seeks to stop data center on BLM land - Nevada Current (opens in a new tab), Nevada Current, July 15, 2026, local outlet
  5. Expletives, fear and anger: A data center fight turns nasty in Boulder City - The Nevada Independent (opens in a new tab), The Nevada Independent, July 16, 2026, news outlet
  6. The Federal Government Just Greenlit the First AI Data Center on Public Land - Outside Magazine (opens in a new tab), Outside Magazine, July 30, 2026, social media
  7. BLM's data center approval is a betrayal of local governance - Las Vegas Sun (opens in a new tab), Las Vegas Sun, August 22, 2026, local outlet
  8. Federal panel halts first AI data center approved on US public land - NationofChange (opens in a new tab), NationofChange, September 9, 2026, national outlet
  9. Developer pulls out of hyperscale data center, natural gas plant proposed on BLM land in Henderson - Las Vegas Review Journal (opens in a new tab), Las Vegas Review-Journal, September 24, 2026, local outlet
  10. Judge halts data center development on federal land in Boulder City - KSNV (opens in a new tab), KSNV, September 1, 2026, local outlet
  11. Federal Board Halts 167-MW Nevada Data Center Approval - Engineering News-Record (opens in a new tab), Engineering News-Record, September 3, 2026, news outlet
  12. Judge halts data center construction on public land - Nevada Current (opens in a new tab), Nevada Current, September 1, 2026, local outlet
11 more sources
  1. Judge orders pause on Boulder City data center - The Nevada Independent (opens in a new tab), The Nevada Independent, September 1, 2026, local outlet
  2. First AI Data Center Approved on Federal Public Land Hits a Major Roadblock - Outdoor Life (opens in a new tab), Outdoor Life, September 3, 2026, news outlet
  3. Federal panel halts first data center planned for US public land - NationofChange (opens in a new tab), NationofChange, September 2, 2026, national outlet
  4. Environmental groups win stay in fight over data center near Boulder City - Las Vegas Sun (opens in a new tab), Las Vegas Sun, September 1, 2026, local outlet
  5. Interior Board Stays BLM Data Center Approval In Nevada - Law360 (opens in a new tab), Law360, September 1, 2026, news outlet
  6. Trump Administration Green Lights First-Ever Public Land Data Center in Nevada - Field & Stream (opens in a new tab), Field & Stream, August 10, 2026, news outlet
  7. Boulder City data center fight sparks push for tougher federal review (opens in a new tab), Las Vegas Review-Journal, September 18, 2026, local outlet
  8. Appeal Halts Public Lands Data Center in Nevada Before Construction Begins - CleanTechnica (opens in a new tab), CleanTechnica, September 1, 2026, news outlet
  9. This Nevada city is appealing a federally-approved data center it tried to reject - upr.org (opens in a new tab), upr.org, August 4, 2026, local outlet
  10. In Nevada, a data center planned on public land is temporarily halted - wyomingpublicmedia.org (opens in a new tab), wyomingpublicmedia.org, September 9, 2026, local outlet
  11. Conservative group calls for transparency, local input on data centers - KSUT Public Radio (opens in a new tab), KSUT Public Radio, October 6, 2026, local outlet

23 sources on file.

Regional grid context

This site is in the Northwest Power Pool (NWPP) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Boulder City Eldorado Valley BLM Data Center Proposal", https://datacenterrecord.org/projects/boulder-city-blm-land-data-center-nv, last verified October 26, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Boulder City Eldorado Valley BLM Data Center Proposal", https://datacenterrecord.org/projects/boulder-city-blm-land-data-center-nv. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Stalled or cancelled
Tier
built from one source
Tags
Built from one source
Coordinates
35.8752, -114.9545
How the location is known
Location from the county parcel record.
Location source
https://www.blm.gov/office/las-vegas-field-office
Coordinate source
BLM Las Vegas Field Office Eldorado Valley right of way and Interior Board of Land Appeals docket
Location last verified
September 16, 2026
Published
September 5, 2026
Last verified
October 26, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Boulder City Eldorado Valley BLM Data Center Proposal · 23 sources, 14 entries · basis and source tier on every row · verified October 26, 2026