Data Center Record.
Census GEOID: 32003 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 1 reporting source

● Running First recorded October 21, 2026 · 1 Building

EdgeConneX Las Vegas Data Center (LAS01)

Street address 4220 S Maryland Pkwy, Las Vegas, NV 89119, Clark County verified address Exact, at the address [1] edgeconnex.com

Overview, regulatory gates and specifications

EdgeConneX Inc. lists EdgeConneX Las Vegas (EDCLAS01) at 1541 Pama Ln, Las Vegas, NV on its interconnection and facility directory. [1] Filings on the record specify disclosed capacity of 6 MW (the developer's figure), 1 planned or operational building. [1] Verified facility status from Nevada GOED Data Center Tax Abatement filings, NDEP air quality permits, or operator campus specifications. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Zoning approved
3. Tax & EDA Deal
Incentive review
4. Utility Grid Queue
Energized
5. Air & Water Permits
Not yet on file
What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.
Electricity Demand [1]
6 MW
the developer's figure

Equivalent to ~4,980 U.S. homes (U.S. EIA 830 homes/MW baseline) · 0.3% of Hoover Dam nameplate capacity (2,080 MW).

Grid interconnection and utility service tracked on file.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
operator page

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 4220 S Maryland Pkwy, Las Vegas, NV 89119.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
6 MW developer figure Equivalent to the continuous electricity demand of about 4,980 average U.S. homes based on U.S. Energy Information Administration residential consumption data. Less than 0.1 percent (0.059 percent) of New York City's summer peak demand in 2024.
[1] edgeconnex.com
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] edgeconnex.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Commissioned
Operational since 2016 (10 years)
Who leads it
EdgeConneX as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year
The math behind the comparison
  1. EdgeConneX Las Vegas Data Center (LAS01), capacity: 6 MW.
  2. New York City (NYISO Zone J) summer peak demand, actual, 2024: 10,245 MW (2024).
  3. 6 ÷ 10,245 = 0.00059 (MW over MW).

Sources:

A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: EdgeConneX
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for EdgeConneX Las Vegas Data Center (LAS01).

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW) 6 MW 6 MW the developer's figure [1] edgeconnex.com
Site Footprint (Acres)
Data Hall Buildings 1 building 1 operator page [1] edgeconnex.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

May 20, 2026 Boulder City, NV Boulder City Planning Commission Denial of Eldorado Valley AI Data Center Boulder City Planning Commission 3 clips

On May 20, 2026, the Boulder City Planning Commission voted unanimously to deny an application for a controversial AI data center in Eldorado Valley after residents packed the chamber opposing desert conservation land use and Colorado River water draw.

  1. FOX5 Las Vegas Broadcast Report Broadcast Report transcribed from local broadcast report
    "Agenda that brought them there, whether or not to move plans on a controversial AI data center forward, something many residents have said they don't want. Fox five's kim passoth has been following this story. She's back with us right now with more developments from tonight. Kim yeah. Tom. At tonight's meeting, the planning commission heard all of that opposition, though the vote was not unanimous. After a presentation from the developer and much public debate, they decided to deny the developer's application. I asked you guys to really"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "To the mic during public comment, speaking to the Boulder City Planning Commission. So let's set down the hammer, because absolutely everyone has said they don't want this. We'd like you to just deny it before the meeting. Those opposed also wanted to make their voices heard, taking to the streets. I think history has taught us that a lot of corporations will always put profit over people here in this community. I want to put the people first. Even this dog was dressed in a no data center shirt. When we"
  3. FOX5 Las Vegas Broadcast Report Broadcast Report transcribed from local broadcast report
    "Light and that's not accurate. Our wind mostly blows from where the data center will be. Nobody wants to sit through a city council meeting. No one knows what's going on. The developer of the town site, solar two project, did make a presentation on their amended plans. After rounds of community feedback, but ultimately the commission shared their thoughts and voted against the developer's proposal. This is the hottest topic, one of the hottest topics in the country. On top of our lack of water. Regardless of how I"

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

  • Read on October 26, 2026 (the day the page was read; it gives no date of its own)

    Verified facility status from Nevada GOED Data Center Tax Abatement filings, NDEP air quality permits, or operator campus specifications.

    [1] edgeconnex.com

Nearest data centers in Nevada

Verified data center records in Nevada within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Flexential Las Vegas Pollock Data Center (LAS01 / LAS03) Las Vegas, Clark County 4 mi Running Flexential 7.4 MW
Switch The CORE Campus (Las Vegas) Las Vegas, Clark County 5 mi Running Switch Inc. 500 MW
Flexential North Las Vegas Data Center (LAS02) North Las Vegas, Clark County 7 mi Running Flexential 6 MW
DataBank Las Vegas Data Center (LAS1) Las Vegas, Clark County 8 mi Running DataBank 6 MW
Google Henderson Data Center Henderson, Clark County 15 mi Running Google 150 MW
Boulder City Eldorado Valley BLM Data Center Proposal Boulder City, Clark County 19 mi Stalled or cancelled Switch Inc. 1 building

Blank cell: not disclosed by any source on file.

Common questions about EdgeConneX Las Vegas Data Center (LAS01)

Answered directly from the verified filings and local actions on this page.

Who is building EdgeConneX Las Vegas Data Center (LAS01)?

EdgeConneX is the developer. No construction contractor is named on the record yet.

How much power and water does EdgeConneX Las Vegas Data Center (LAS01) say it needs?

Power: 6 MW (the developer's figure, edgeconnex.com (opens in a new tab)). Water: not disclosed by any source on file.

Where does EdgeConneX Las Vegas Data Center (LAS01) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. EdgeConneX: Las Vegas (LAS01) Data Center Specification (opens in a new tab), EdgeConneX, news outlet

1 source on file.

Regional grid context

This site is in the Northwest Power Pool (NWPP) regional power market.

Sources and data

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "EdgeConneX Las Vegas Data Center (LAS01)", https://datacenterrecord.org/projects/edgeconnex-las-vegas-edclas01-nv, last verified October 26, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "EdgeConneX Las Vegas Data Center (LAS01)", https://datacenterrecord.org/projects/edgeconnex-las-vegas-edclas01-nv. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
36.112847, -115.136154
How the location is known
Location from the site's street address.
Location source
https://www.edgeconnex.com/locations/americas/las-vegas-nv-data-center/
Coordinate source
EdgeConneX Las Vegas (LAS01, 4220 S Maryland Pkwy) specification
How capacity was disclosed
the developer's figure
Capacity, if disclosed
6 MW, the developer's figure
Published
October 21, 2026
Last verified
October 26, 2026
Not disclosed
Location source number, Location last verified, EPA registry id, Uses, Tenancy, Cooling, How water was disclosed, How acreage was disclosed, Interconnection, Rating of the county's rows

Researcher view · EdgeConneX Las Vegas Data Center (LAS01) · 1 source, 1 entry · basis and source tier on every row · verified October 26, 2026

Download CSV JSON