Boulder City Eldorado Valley BLM Data Center Proposal, in order

What happened with this project, oldest first: the stages it reached, what the county and its cities decided, and every dated step on the record. Each entry links its source.

6 events, January 1, 2023 to September 9, 2026. Also on the record, under the month each belongs to: 5 statements, 5 figures from other sources and 8 dates when source pages were read and verified. The facts, newest first: the record; the place: Nevada.

A plain date is the day it happened, as the source states it, or as the line's own sentence states it ("voted on July 6"), which is where the line sits even when it was filed later. "Reported" and a date is the day a source published a line that carries no date of its own. Those lines, and lines that describe rather than report an act, sit under their month rather than on the timeline, with what was said and the figures other sources gave. Every timeline on the site reads its lines by this one rule. How dates are read.

2023 1 event

  1. (the year its own sentence names; filed under Aug 22, 2026)

    Entry

    BLM authorized Townsite Solar 2 to use approximately 80 acres of federal land for a 19 megawatt solar generating facility and 35 megawatt battery storage system in 2023 [7]

2026 5 events

  1. (content date)

    cancelled

    A developer withdrew a data center project in Boulder City and signaled plans to move the project to federal land. blm.gov (opens in a new tab) primary source

  2. Also in August 2026: 2 figures from other sources and 1 date when a source page was read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Developer is now proposing to add a massive data center capable of demanding as much as 167 megawatts of electricity to the project [7]

    2. (source date; the content gives no date of its own)

      Figure · Las Vegas Sun

      167 MW: The data center would demand 167 megawatts, more than all of Boulder City uses on the hottest summer days and more than three times the average consumption rate throughout the year Las Vegas Sun (opens in a new tab) local outlet

    3. (source date; the content gives no date of its own)

      Figure · Las Vegas Sun

      30 to 50 percent: According to the developer, only 30-50% of the energy would come from renewable sources Las Vegas Sun (opens in a new tab) local outlet

  3. (source date; the content gives no date of its own)

    cancelled

    Townsite Data Center has planned capacity of 167 MW backup generation [11]

  4. (content date)

    stalled

    A 167 MW data center approved on BLM public land near Boulder City was put on hold after an appeal and a stay issued by the Interior Board before construction began. blm.gov (opens in a new tab) primary source

  5. (source date; the content gives no date of its own)

    cancelled

    Townsite Solar 2 LLC received BLM approval in 2023 for solar power and battery storage facility on 88.5 acre parcel 25 miles southeast of Las Vegas [8]

  6. (source date; the content gives no date of its own)

    stalled

    Townsite Solar data center project on 80 acre BLM public land in Nevada received temporary halt from Interior Board of Land Appeals stay pending environmental review and public input [22]

  7. Also in September 2026: 2 figures from other sources and 6 dates when source pages were read and verified
    1. (source date; the content gives no date of its own)

      Entry

      Planned commercial operation of Townsite Data Center in second quarter of 2028 [11]

    2. (source date; the content gives no date of its own)

      Entry

      Planned Townsite Data Center construction scheduled for first quarter of 2027 [11]

    3. (source date; the content gives no date of its own)

      Figure · alaska-native-news.com

      80 acre: Townsite Data Center is 80 acres alaska-native-news.com (opens in a new tab) local outlet

    4. (source date; the content gives no date of its own)

      Figure · enr.com

      3,000,000,000 USD: Townsite Data Center represents about $3 billion in planned capital investment enr.com (opens in a new tab) news outlet

    5. (source date; the content gives no date of its own)

      Entry

      Townsite Solar 2 LLC asked BLM in 2025 to amend right of way grant to build data center instead of solar [8]

    6. (source date; the content gives no date of its own)

      Entry

      Townsite Solar project, owned by Skylar Capital Management hedge fund based in Houston, originally applied for solar project but changed plans to data center [22]

    7. (source date; the content gives no date of its own)

      Entry

      The Boulder City data center permit was approved by the Bureau of Land Management after determining a previous environmental review for a solar project was sufficient, and is now on hold after an administrative judge granted a stay [19]

    8. (source date; the content gives no date of its own)

      Entry

      Skylar Opportunities LLC withdrew application for 1000 megawatt data center on 680 acres of federal land near Henderson due to city planned urban development efforts in same area [9]

  8. Also in October 2026: 5 statements, 1 figure from another source and 1 date when a source page was read and verified
    1. (content date; reported from elsewhere)

      Statement · Tom Gaitens, senior advisor at Humans First

      A conservative group called Humans First is conducting a 27 state bus tour advocating for local control and limiting corporate influence in data center construction KSUT Public Radio (opens in a new tab) local outlet

    2. (source date; the content gives no date of its own)

      Entry

      The Center for Biological Diversity and local residents successfully halted the development of the proposed data center on public land near Boulder City [23]

    3. (said in the source itself)

      Statement · Tom Gaitens, senior advisor at Humans First

      Tom Gaitens stated that data center development should only take place with community input and full transparency KSUT Public Radio (opens in a new tab) local outlet

    4. (said in the source itself)

      Statement · Tom Gaitens, senior adviser at Humans First

      Tom Gaitens, senior adviser at Humans First, calls data center development an apolitical issue where everyone drinks water, uses electricity and wants their voice heard Nevada Public Radio KNPR (opens in a new tab) local outlet

    5. (said in the source itself)

      Statement · Tom Gaitens, senior adviser at Humans First

      Tom Gaitens says that whether a data center is supported or rejected locally, development should only take place with community input and full transparency Nevada Public Radio KNPR (opens in a new tab) local outlet

    6. (said in the source itself)

      Statement · Tom Gaitens, senior adviser at Humans First

      Tom Gaitens says that if data centers are considered on public lands, they should be limited to locations with pre existing build outs, like decommissioned military sites, rather than new construction in open spaces Nevada Public Radio KNPR (opens in a new tab) local outlet

    7. (content date)

      Figure · Nevada Public Radio KNPR

      24 percent: Forty two percent of Republicans say data centers are mostly bad for the quality of life of people nearby, up from 24% in January Nevada Public Radio KNPR (opens in a new tab) local outlet

On the timeline: a stage change; an entry that reports an act on the day the source or its own sentence gives; and a decision, a published scorecard event on a row at or under the record's county, that reports an act. Under the months: a statement that names this record, a figure another source gave about it, matched by place and developer, an entry dated only by the day its source was published, and an entry or a decision that describes rather than reports an act. Each is on the record in its own right and keeps its own link.

For researchers
Stage
cancelled
Events on the timeline
6
Under the months
18
Stage changes
5
Decisions
0
Statements
5
Figures
5