Switch lists a data center at Reno, Nevada among the sites it operates. [1] Filings on the record specify disclosed capacity of 650 MW (the developer's figure), 3 planned or operational buildings. [2] Switch lists Switch Tahoe Reno campus at Reno, Nevada on its own page of data center locations, read September 14, 2026. [2]
Equivalent to ~539,500 U.S. homes (U.S. EIA 830 homes/MW baseline) · 31% of Hoover Dam nameplate capacity (2,080 MW).
Grid interconnection and utility service tracked on file.
U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.
No local property tax abatement amount disclosed in public filings.
Assessor parcel acreage and building square footage are added when municipal or county filings are published.
Location: 1000 Supernap Dr, Sparks, NV 89434.
State and local tax abatement agreements and permanent job commitments are recorded when filed.
No local property tax abatement amount disclosed in public filings.
Sources:
A comparison is arithmetic on two published rows and is never a new fact (how comparisons are made).
Connected government officials, corporate entities, utilities and local rules on the public record.
Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.
Disclosed engineering ceilings, reported actuals and primary regulatory basis for Switch The Citadel Campus (Tahoe Reno).
| Field / Parameter | Disclosed Ceiling | Reported Actual | Basis & Primary Source |
|---|---|---|---|
| Electrical Capacity (MW) | 650 MW | 650 MW | the developer's figure [2] switch.com |
| Site Footprint (Acres) | |||
| Data Hall Buildings | 3 buildings | 3 | operator page [2] switch.com |
| Cooling & Water System | |||
| Backup Diesel / Gas Generators | |||
| Tax Abatement & Annual Revenue |
Blank cell: not disclosed by any source on file.
The record adds each the day a source gives it. Why these documents.
Storey County Board of Commissioners and Tahoe Reno Industrial Center public record on tax abatements, water rights, and power infrastructure for Switch and Google campuses (November 21, 2019).
"regulations that are being brought out of around data centers, all they are going to do is they're going to relocate the infrastructure. They are not going to in any way reduce the demand. The market is looking for more infrastructure because there are companies that are building and extracting value from building this infrastructure and it's just a question of where you put it, not nothing more than that."
"infrastructure. They are not going to in any way reduce the demand. The market is looking for more infrastructure because there are companies that are building and extracting value from building this infrastructure and it's just a question of where you put it, not nothing more than that."
"and extracting value from building this infrastructure and it's just a question of where you put it, not nothing more than that."
Using this data in a report? Support the record.
Chronological regulatory, corporate and permitting events on the record, newest first.
· Status: running (source date; the content gives no date of its own)
Switch solar project supports green energy at Reno area data center
Read on September 14, 2026 (the day the page was read; it gives no date of its own)
Switch lists Switch Tahoe Reno campus at Reno, Nevada on its own page of data center locations, read September 14, 2026.
· City
Postal mailing address city is not a Census place in Storey County; filed at the county level per place-geoid-fixes-1016.
The campus is in the Tahoe Reno Industrial Center, unincorporated Storey County; Reno is in Washoe County, and the record had placed it at Reno's center. On the editor's word of October 16, 2026.
· City
The campus is in the Tahoe Reno Industrial Center, unincorporated Storey County; Reno is in Washoe County, and the record had placed it at Reno's center. On the editor's word of October 16, 2026.
Every correction on the record is on the corrections page.
Verified data center records in Nevada within 60 miles by straight line distance.
| Facility & Location | Distance | Stage | Operator / Tenant | Disclosed Scale |
|---|---|---|---|---|
| Switch Citadel Campus (Tahoe Reno McCarran) McCarran, Storey County | Less than 1 mi | Running | Switch | 1 building |
| PR TX 1 Storey County Data Center McCarran, Storey County | Less than 1 mi | Proposed | PR TX 1, LLC | |
| Vantage Data Centers Nevada (NV1 Campus) Storey County | Less than 1 mi | Running | Vantage Data Centers | 224 MW |
| Google Storey County Data Center (Tahoe Reno Industrial Center) Storey County | Less than 1 mi | Running | 200 MW | |
| EdgeCore Reno Data Center Campus (RN01) Storey County | Less than 1 mi | Being built | EdgeCore Digital Infrastructure | 216 MW |
| SV RNO Property Owner 1 Storey County Data Center McCarran, Storey County | Less than 1 mi | Proposed | SV RNO Property Owner 1 LLC |
Blank cell: not disclosed by any source on file.
Answered directly from the verified filings and local actions on this page.
Switch Inc. is the developer. No construction contractor is named on the record yet.
Power: 650 MW (the developer's figure, switch.com (opens in a new tab)). Water: not disclosed by any source on file.
It is running, as reported August 18, 2020. The newest entry, reported August 18, 2020: Switch solar project supports green energy at Reno area data center [9].
Official operator or facility campus page verified in 50 state website discovery pass.
9 sources on file.
This site is in the Northwest Power Pool (NWPP) regional power market.
Every number on this page comes from a named source. Click any source to open the document in a new tab.
If a link has moved or a document has changed, let us know and we will update the record and log the change.
Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.
Data Center Record. Switch The Citadel Campus (Tahoe Reno). Last verified October 26, 2026. https://datacenterrecord.org/projects/switch-tahoe-reno-campus-nv. Accessed November 22, 2026.
Every row on this page is available to download with its source, its basis and the date it was last verified.
Download this page's records (CSV) JSON
Licensed CC BY-NC 4.0. Say where it came from and do not sell it or use it to train a commercial model without a license.
Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.
Data Center Record takes no money from data center developers, operators, utilities or trade groups. That rule does not change for licensing.
Data Center Record is an independent project and takes no money from data center developers, operators, utilities or trade groups. Reader support keeps the record free to read, with no ads and no paywall.
Last verified , first recorded . Every correction is logged on the corrections page and under What happened. Report a correction · Send a tip about Switch The Citadel Campus (Tahoe Reno)
Data Center Record, "Switch The Citadel Campus (Tahoe Reno)", https://datacenterrecord.org/projects/switch-tahoe-reno-campus-nv. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.
The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.