Data Center Record.
Census GEOID: 32029 Location Precision: verified address Jump to Entity & Permit Table Commercial & Bulk Data (CC BY-NC 4.0)

Last verified: · 2 primary and local sources

● Running Announced October 21, 2026 · 1 Building · Switch

Switch Citadel Campus (Tahoe Reno McCarran)

Street address 1 Superloop Cir, McCarran, NV 89434, Storey County verified address Exact, at the address [1] echo.epa.gov

Overview, regulatory gates and specifications

Switch operates Switch Citadel Campus Tahoe Reno McCarran through legal entity Switch, Ltd. at 1 Superloop Cir McCarran NV 89434 in McCarran, Storey County, NV. Primary environmental regulator records (U.S. Environmental Protection Agency and Nevada Division of Environmental Protection) and operator facility specifications confirm commercial colocation operations at the site. [1] Filings on the record specify 1 planned or operational building. [2] On the regulatory record, state permit status is Nevada NDEP Class II Air Quality Operating Permit (NAICS 518210, 1 Superloop Cir, McCarran). [1]

Verified Site & Permit Summary
Verified address
1 Superloop Cir, McCarran, NV 89434, Storey County verified address
Operator / developer
Switch
Permit / registry ID
Nevada NDEP Class II Air Quality Operating Permit (NAICS 518210, 1 Superloop Cir, McCarran) [1]

How much power it needs, how much water it would use and who would use it have not been disclosed.

What happens next: Facility is operational; air permit compliance, water reporting and utility filings are monitored.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[2] switch.com
Backup generators
Not disclosed
Capital investment
Not disclosed
Who leads it
Switch attributed via corporate HQ or property filing
[2] switch.com
Permitted legal entity
Switch, Ltd. what a permit allows
[1] echo.epa.gov
State permit status
Nevada NDEP Class II Air Quality Operating Permit (NAICS 518210, 1 Superloop Cir, McCarran) the state's permit register, as of November 6, 2026
[1] echo.epa.gov
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Switch · Applicant / Shell LLC: Switch, Ltd.
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for Switch Citadel Campus (Tahoe Reno McCarran).

Field / Parameter Permitted / Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 1 building 1 Site filing [2] switch.com
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

What was decided

Acts of Storey County and McCarran about data centers, on the record with their source. A rule about the area is not a decision about this record.

DateWhoDecisionSource
Storey County Nevada Public Utilities Commission approved two temporary natural gas fired power projects totaling 362 MW in Storey County for data centers news.constructconnect.com (opens in a new tab)

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

No dated entry is on the record yet.

Every event in order

Nearest data centers in Nevada

Verified data center records in Nevada within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
Switch The Citadel Campus (Tahoe Reno) Storey County Less than 1 mi Running Switch Inc. 650 MW
Vantage Data Centers Nevada (NV1 Campus) Storey County Less than 1 mi Running Vantage Data Centers 224 MW
Google Storey County Data Center (Tahoe Reno Industrial Center) Storey County Less than 1 mi Running Google 200 MW
PR TX 1 Storey County Data Center McCarran, Storey County Less than 1 mi Proposed PR TX 1, LLC
SV RNO Property Owner 1 Storey County Data Center McCarran, Storey County Less than 1 mi Proposed SV RNO Property Owner 1 LLC
Novva Data Centers Tahoe Reno Campus Storey County Less than 1 mi Running Novva Data Centers 60 MW

Blank cell: not disclosed by any source on file.

Common questions about Switch Citadel Campus (Tahoe Reno McCarran)

Answered directly from the verified filings and local actions on this page.

Who is building Switch Citadel Campus (Tahoe Reno McCarran)?

Switch is the developer, switch.com (opens in a new tab). No construction contractor is named on the record yet.

How much power and water does Switch Citadel Campus (Tahoe Reno McCarran) say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does Switch Citadel Campus (Tahoe Reno McCarran) stand today?

It is running; the date it reached that stage is not sourced, only the day a page was read. No dated entry is on the record yet.

What has McCarran or Storey County decided about it?

Storey County: Nevada Public Utilities Commission approved two temporary natural gas fired power projects totaling 362 MW in Storey County for data centers (reported September 21, 2026, news.constructconnect.com (opens in a new tab)). 1 event is on the county's rows; a rule about the area is not a decision about this record.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Primary documents

  1. US EPA ECHO and Nevada NDEP Bureau of Air Pollution Control Permit Record (1 Superloop Cir, McCarran, NV) (opens in a new tab), U.S. Environmental Protection Agency and Nevada Division of Environmental Protection, November 6, 2026
  2. Switch The Citadel Campus Specifications (1 Superloop Cir, Tahoe Reno Industrial Center, McCarran) (opens in a new tab), Switch, November 6, 2026

2 sources on file.

Regional grid context

This site is in the Northwest Power Pool (NWPP) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "Switch Citadel Campus (Tahoe Reno McCarran)", https://datacenterrecord.org/projects/switch-tahoe-reno-mccarran-nv, last verified October 21, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "Switch Citadel Campus (Tahoe Reno McCarran)", https://datacenterrecord.org/projects/switch-tahoe-reno-mccarran-nv. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Running
Tier
built from one source
Tags
Built from one source
Coordinates
39.5415, -119.4715
How the location is known
Location from the site's street address.
Coordinate source
US EPA ECHO FRS and municipal parcel records
Location last verified
October 21, 2026
Published
October 21, 2026
Last verified
October 21, 2026
Not disclosed
Location source, Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows

Researcher view · Switch Citadel Campus (Tahoe Reno McCarran) · 2 sources, 0 entries, 1 decision nearby · basis and source tier on every row · verified October 21, 2026

Download CSV JSON