Data Center Record.

Reported Built from one source

St. Louis Midtown Data Center

A proposed Midtown data center in St. Louis prompted residents and organizations to file a lawsuit against the project. It is reported, as reported September 17, 2026.

How much water it would use and who would use it have not been disclosed.

Last verified · 8 sources, 0 primary · A skeleton record: built from one source, not yet reviewed in depth by a person. · How to read this page

How to read this page. Every fact links to the source it rests on; a number in brackets is its place in the source list. A figure no source gives reads Not disclosed, and nothing is estimated. Where sources give different figures, each is shown with who gave it, and another source's figure never stands in for the record's own. Entries are added and never overwritten; corrections are listed under What happened.

What is known

Each figure as its source gave it. The number in brackets is its place in the source list.

Land
11 acres
third party estimate [2]
Power it would draw
300 MW
third party estimate [3]
Water
Not disclosed
Who leads it
Not disclosed
Who would use it
Not disclosed
Jobs once it runs
Not disclosed
Tax each year
Not disclosed
Where its power comes from
50% renewable energy within 5 years
as stated by the source [2]
Every field, with who said it and when (Researcher view)

Impact figures

FieldValueWho says soSourceLast verified
How much power it needs 300 MW third party estimate [3] stltoday.com September 25, 2026
How much water it would use Not disclosed
How loud it would be Not disclosed
Jobs once it runs Not disclosed
Tax it would pay each year Not disclosed

The record's fields

FieldValueWho says soSourceLast verified
Who is building it Not disclosed
Who is constructing it Not disclosed
How much land 11 acres third party estimate [2] independent.co.uk September 25, 2026
Where its power comes from 50% renewable energy within 5 years as stated by the source [2] independent.co.uk September 25, 2026
Grid connection Not disclosed
How it is cooled Not disclosed

The developer's figure is what the company said; what a permit allows is the ceiling a permit sets; measured means observed. Water is in gallons a day or a year, whichever the source stated; a tax claim given as a range shows both ends, each linked to the source that gave it.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water useA state water right filing or a water supply agreement.
  • Who would use itA lease announcement or a tenant named in a filing.
  • Who is behind itA land record, a zoning application or a company's own announcement.
  • Jobs and taxAn incentive agreement, a county's economic development filing or a fiscal note.

What happened

  1. (source date; the content gives no date of its own)

    Armory data center in Midtown is approved before new St. Louis regulations and is regulated by conditional use permit with different sound policies [4]

  2. (source date; the content gives no date of its own)

    Permit upheld by Board of Adjustment in July [2]

  3. · Status: rumored (source date; the content gives no date of its own)

    Developer David Lambiaso filed suit against the city's Board of Adjustment challenging two conditions imposed on the data center construction [1]

  4. (source date; the content gives no date of its own)

    Renewable energy must power 50% of facility in first five years, 100% within 10 years [5]

  5. (source date; the content gives no date of its own)

    Construction expected to begin August 2027 and be completed by late 2029 [5]

  6. · Status: approved (source date; the content gives no date of its own)

    Land Clearance for Redevelopment Authority approved community benefit plan for TerraWatt data center at 3728 Market Street [5]

The full St. Louis Midtown Data Center timeline, in order

2 corrections to this record

Every correction, with its reason
  1. · the draft of a reference figures row

    The record could not read this figure's source: the page answered HTTP 403, so no text of it reached the classifier, which scored card 12140 from the headline alone, and the number came from the headline; published by the bulk approve of 2026-09-25. A reference figure needs a source the record read: returned to draft, off every page, until a readable source that states it is cited (docs/batch-unread-figures-0929.md). The old and new text.

  2. · the kind of source of a history entry

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of 2026-09-23). The link did not change. The day's label corrections.

Every correction on the record is on the corrections page.

What was said

Data center noise increases cortisol, cardiovascular risk, decreases cognitive functioning especially in children, and can delay healing in hospital settings
Kasey Fowler-Finn, St. Louis University professor · September 24, 2026 · paraphrased · St Louis Public Radio local outlet

Every statement about data centers in Missouri, by speaker

4 more statements on this page

Kasey Fowler-Finn, St. Louis University professor

Data center noise is concentrated in low frequencies, making it sound like a hum that stands out from mid- to high frequency city noise

September 24, 2026, St Louis Public Radio · St Louis Public Radio local outlet · the record (Paraphrased; said in the source itself)

Kasey Fowler-Finn, St. Louis University professor

Low frequency hum from a data center can travel 800 feet or further, compared to traffic sound at 300 feet

September 24, 2026, St Louis Public Radio · St Louis Public Radio local outlet · the record (Paraphrased; said in the source itself)

Kasey Fowler-Finn, St. Louis University professor

Greatest area of impact from large data centers is 3,000 feet, about half a mile

September 24, 2026, St Louis Public Radio · St Louis Public Radio local outlet · the record (Paraphrased; said in the source itself)

St. Louis University professor

Fowler Finn says 600 foot setbacks in St. Louis regulations are woefully insufficient because most severe impacts fall within 3,000 feet

September 24, 2026, St Louis Public Radio · St Louis Public Radio local outlet · the record (Paraphrased; said in the source itself)

The site

Where in St. Louis is not in the public record. The pin marks the center of St. Louis, not a building, and the outline is St. Louis city.

  • This record: Proposed, ringed
  • data center
  • Dashed edge: the exact site is not in the public record
  • Smaller pins: 17 other published records in Missouri
Details
  • this record's location, ringed
  • parcel outline, from the county parcel record
  • city limits, U.S. Census Bureau, on a town level record
  • county boundary

The other pins are the published projects in the same state, each in its stage color. The imagery beneath is the USGS national orthoimagery, public domain, shown so the land around the site can be read.

Where
St. Louis, St. Louis city, Missouri
How exactly it is located
Town level, the center of the city
The parcel
No parcel outline in the public record
Nearest homes
Not computed for a record placed at a place center
Nearest records
Nearest records are not computed for a record placed at the center of its town.

Questions about this project

5 questions answered from the record

Answered from the rows on this page.

How big is St. Louis Midtown Data Center?

The record has 2 measures of its size: 300 MW (third party estimate, source) and 11 acres (third party estimate, source). Each figure names who gave it and links to the source.

Who is building St. Louis Midtown Data Center?

Not disclosed. No source on file names the developer. The sources read for this record are listed under Sources.

How much power and water does St. Louis Midtown Data Center say it needs?

Power: 300 MW (third party estimate, source). Water: not disclosed by any source on file.

Where does St. Louis Midtown Data Center stand today?

It is reported, as reported September 17, 2026. The newest entry, reported September 24, 2026: Armory data center in Midtown is approved before new St. Louis regulations and is regulated by conditional use permit with different sound policies [4].

What has St. Louis or St. Louis city decided about it?

No decision by St. Louis or St. Louis city about data centers is on the record. The St. Louis city page and the Missouri scorecard list every rated row the day a person publishes one.

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Developer behind controversial data center near Armory sues St. Louis, St Louis Public Radio, September 17, 2026, local outlet
  2. Data center developer sues city after requiring company to supply renewable energy on site - The Independent, The Independent, September 17, 2026, local outlet
  3. 'Pay to play'? Donation adds new controversy to Ferguson data center vote, St Louis Post-Dispatch, September 22, 2026, local outlet
  4. How data center noise is different from regular noise pollution, according to a St. Louis scientist, St Louis Public Radio, September 24, 2026, local outlet
  5. St. Louis OKs plan for Midtown data center estimated to generate $445M in tax revenue over 10 years, St Louis Public Radio, September 15, 2026, local outlet
  6. Data centers across the region move forward, St Louis Post-Dispatch, September 16, 2026, local outlet
  7. Midtown data center wins key approval from St. Louis Board of Public Service, www.stlmag.com, April 21, 2026, local outlet
  8. Residents, organizations file lawsuit against proposed Midtown data center - KMOV, KMOV, August 29, 2026, local outlet

8 sources on file.

Cite this record

Data Center Record, "St. Louis Midtown Data Center", https://datacenterrecord.org/projects/st-louis-midtown-data-center-mo, last verified September 25, 2026.

Last verified , first recorded . Every correction is logged on the corrections page and under What happened.

Cite this page

Data Center Record, "St. Louis Midtown Data Center", https://datacenterrecord.org/projects/st-louis-midtown-data-center-mo. Data: Data Center Record, datacenterrecord.org, CC BY 4.0.

The structured rows are CC BY 4.0. Link to this page; that is what turns a reuse into a citation. Prose stays under copyright.

Report a change
For researchers
Slug
st-louis-midtown-data-center-mo
Status value
rumored
Stage
Proposed
Tier
skeleton
Tags
skeleton
Place id
us/mo/st-louis-city/st-louis
Coordinates
38.6357896, -90.2451124
Location precision
city
Location source
City centroid (St. Louis), U.S. Census Bureau TIGERweb, public domain, placed at city level
Coordinate source
tigerweb city centroid
Location source number
Not disclosed
Location last verified
September 17, 2026
EPA registry id
Not disclosed
Use type values
not_disclosed
Tenancy value
not_disclosed
Cooling type value
not_disclosed
Capacity basis
third_party_estimate
Water basis
not_disclosed, gallons_per_day
Acreage basis
third_party_estimate
Interconnection value
not_disclosed
Capacity, if disclosed
300 MW, third party estimate
Rating of the county's rows
Not disclosed
Published
2026-09-05
Last verified
2026-09-25