● Proposed Campus Recorded July 30, 2026 · 1 Building

St. Louis Armory Data Center Proposal

Street address 3660 Market Street, St. Louis, MO 63110, St. Louis city verified address Exact, at the address [1] stlpr.org

Overview, regulatory gates and specifications

Developers proposed converting the historic St. Louis Armory at 3660 Market Street in Midtown St. Louis, Missouri, into a data center facility. [1] Filings on the record specify 1 planned or operational building. [1] TerraWatt plans to build a 120 megawatt data center in the old Famous Barr warehouse on Market Street as part of a planned technology district. [1]

1. Land & Parcel
Parcel located
2. Local Zoning
Not yet on file
3. Tax & EDA Deal
Not yet on file
4. Utility Grid Queue
Not yet on file
5. Air & Water Permits
Not yet on file
What happens next: Next public milestones include utility queue filings, state environmental permits and local site plan review.
Electricity Demand
Not disclosed
No MW figure in public filings yet

U.S. EIA residential equivalence (~830 homes per MW) will compute automatically once a permit or filing states facility megawatts.

Utility interconnection queue filings monitored.

Cooling & Water
Not disclosed
Daily water volume not stated in public filings

U.S. EPA household water equivalence (300 gal/day per home) requires a disclosed daily or annual water figure.

No local property tax abatement amount disclosed in public filings.

Site & Buildings [1]
1 building
agency filing

Assessor parcel acreage and building square footage are added when municipal or county filings are published.

Location: 3660 Market Street, St. Louis, MO 63110.

Taxes & Permanent Jobs
Not disclosed
Tax and job figures not yet on file

State and local tax abatement agreements and permanent job commitments are recorded when filed.

No local property tax abatement amount disclosed in public filings.

Key specifications on the record

Power capacity
Not disclosed
Water usage
Not disclosed
Land area
Not disclosed
Buildings
1 building operator page
[1] stlpr.org
Backup generators
Not disclosed
Capital investment
$8.3 million developer figure
[4] stltoday.com
Who leads it
Midtown Redevelopment as stated by the source
Not disclosed
Who would use it, Jobs once it runs, Tax each year

Who is connected to this project

Connected government officials, corporate entities, utilities and local rules on the public record.

David Lambiaso

TerraWatt partner

DID Recorded statement at STLPR (September 17, 2026) [1]
SAID David Lambiaso, partner in TerraWatt, filed a suit against the city's Board of Adjustment over renewable energy requirements and community benefits agreement approval conditions. (September 17, 2026) [1]

Steve Smith

City Foundry STL developer

DID Recorded statement at www.facebook.com (September 15, 2026)
SAID Steve Smith, City Foundry STL developer, proposed keeping the planned data center while preserving the Armory as an entertainment venue instead of converting it to corporate offices (September 15, 2026) facebook.com (opens in a new tab)

Builder, Shell LLC & Utilities

BUILDER
Operator / Developer: Midtown Redevelopment
UTILITIES
Electric utility: Not disclosed

Citizen privacy standard: Elected officials, corporate applicants and utility executives are named in full. Private residents who speak at public comment are cited as Resident First L. unless they hold public office or speak on behalf of an organization.

Technical specification and permit ledger

Disclosed engineering ceilings, reported actuals and primary regulatory basis for St. Louis Armory Data Center Proposal.

Field / Parameter Disclosed Ceiling Reported Actual Basis & Primary Source
Electrical Capacity (MW)
Site Footprint (Acres)
Data Hall Buildings 1 building agency filing [1] stlpr.org
Cooling & Water System
Backup Diesel / Gas Generators
Tax Abatement & Annual Revenue

Blank cell: not disclosed by any source on file.

Still not public, and where it would show up

The record adds each the day a source gives it. Why these documents.

  • Water use A state water right filing or a water supply agreement.
  • Who would use it A lease announcement or a tenant named in a filing.
  • Power the campus would draw A utility or public service commission docket, an interconnection filing, or an air permit for an on site plant.
  • Jobs and tax An incentive agreement, a county's economic development filing or a fiscal note.

Hearings and statements on the record

August 28, 2026 St. Louis, MO St. Louis Board of Aldermen Board Bill 49 Data Center Regulations Vote St. Louis Board of Aldermen 2 clips

On August 28, 2026, the St. Louis Board of Aldermen voted unanimously to advance Board Bill 49, establishing the city's first comprehensive zoning, conditional use, water disclosure, and noise regulations for data centers.

  1. FOX 2 St. Louis Broadcast Report Broadcast Report transcribed from local broadcast report
    "It establishes size classifications for data centers. Restrictions on where they can be built. Noise, regulations and water use its guidelines. The measure also requires new data centers with loads exceeding 5 megawatts to give 100% of their electricity from renewable energy sources. The bill is sponsored by first ward alderwoman and schweitzer. This is all about"
  2. Resident public comment Resident Public Comment transcribed from local broadcast report
    "Lot of concerns about the proliferation of data centers and the amount of energy that they use and will continue to use and the effect. On our on our climate, on environment, on our ability to exist in this world. So I think it's really important that we in the local level act to protect the people we represent. Even if that means fighting against some pretty powerful interests."

Timeline on the record

Chronological regulatory, corporate and permitting events on the record, newest first.

  1. (source date; the content gives no date of its own)

    The project is planned at an 11 acre site in the old Famous Barr warehouse.

    [1] stlpr.org

  2. (source date; the content gives no date of its own)

    The city's renewable energy requirements require the data center to use 2.4 megawatts of renewable energy.

    [1] stlpr.org

  3. Filing (source date; the content gives no date of its own)

    The developer filed suit against the city this week; the company plans to build a data center as part of a planned technology district.

    [1] stlpr.org

  4. · Status: proposed (source date; the content gives no date of its own)

    TerraWatt plans to build a 120 megawatt data center in the old Famous Barr warehouse on Market Street as part of a planned technology district.

    [1] stlpr.org

  5. (source date; the content gives no date of its own)

    The developer agreed to have renewable energy account for half of the 120 megawatt facility's energy load within five years of operations and 100 percent within 10 years

    [4] stltoday.com

  6. (source date; the content gives no date of its own)

    TerraWatt is expected to start construction by June 2027 and have the office portion be occupied by the end of 2028

    [4] stltoday.com

  7. · Status: being built (source date; the content gives no date of its own)

    TerraWatt is proposing to transform the old Famous Barr warehouse into a $4.1 billion data center, with the adjacent Armory site to be used as office space

    [4] stltoday.com

  8. · Status: approved (content date)

    A data center near the Armory in St. Louis was allowed to move forward by the St. Louis board under new rules in July 2026.

    [1] stlpr.org

Every event in order

6 corrections to this record

Every correction, with its reason
  1. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

  2. · Source tier

    The source was labeled with the Google News search that found it; it now carries its outlet's tier (the record's rules of September 23, 2026). The link did not change.

Every correction on the record is on the corrections page.

Nearest data centers in Missouri

Verified data center records in Missouri within 60 miles by straight line distance.

Facility & Location Distance Stage Operator / Tenant Disclosed Scale
St. Louis Midtown Chouteau Data Center Proposal St. Louis, St. Louis city Less than 1 mi Proposed Midtown Technology Partners 2 buildings
TierPoint St. Louis Downtown (2300 Locust Street) St. Louis, St. Louis city 1 mi Running TierPoint 1 building
H5 Data Centers St. Louis St. Louis, St. Louis city 2 mi Running H5 Data Centers 8 MW
Netrality and Digital Realty 210 North Tucker Carrier Hotel St. Louis, St. Louis city 2 mi Running Netrality Data Centers / Digital Realty 22 MW
TierPoint St. Louis Downtown Data Center (Olive) St. Louis, St. Louis city 2 mi Running TierPoint 10 MW
710 North Tucker Carrier Hotel (Globe Building St. Louis) St. Louis, St. Louis city 2 mi Running Hostirian 10 MW

Blank cell: not disclosed by any source on file.

Common questions about St. Louis Armory Data Center Proposal

Answered directly from the verified filings and local actions on this page.

Who is building St. Louis Armory Data Center Proposal?

Midtown Redevelopment is the developer. No construction contractor is named on the record yet.

How much power and water does St. Louis Armory Data Center Proposal say it needs?

Power: not disclosed by any source on file. Water: not disclosed by any source on file.

Where does St. Louis Armory Data Center Proposal stand today?

Sources

Primary documents first: filings, minutes, dockets and official pages. Then reporting. The numbers are the ones the entries above cite.

Reporting

  1. Developer behind controversial data center near Armory sues St. Louis - STLPR (opens in a new tab), STLPR, September 17, 2026, local outlet
  2. Armory Data Center Deal Advances in St. Louis - stl.news (opens in a new tab), stl.news, September 15, 2026, local outlet
  3. St. Louis board allows data center near Armory to move forward with new rules - STLPR (opens in a new tab), STLPR, July 30, 2026, local outlet
  4. St. Louis could get $8.3 million from Armory data center by spring - STLtoday.com (opens in a new tab), STLtoday.com, September 14, 2026, local outlet

4 sources on file.

Regional grid context

This site is in the SERC Midwest (SRMW) regional power market.

Sources and data

Sources on this page

Every number on this page comes from a named source. Click any source to open the document in a new tab.

Cite this page

Every record on this page carries its sources and the date it was last verified. When you cite it in a story, a study or a public filing, link to this page and give the date you accessed it.

Get this data

Every row on this page is available to download with its source, its basis and the date it was last verified.

Use this data in your work

Free to use and republish with attribution for reporting, research, teaching and public filings under CC BY-NC 4.0. Commercial, enterprise, financial or AI training use needs a commercial license.

About this data

Last verified
Next check Feeds every four hours, pages daily.
Figures Each figure as its source gave it, with its basis; another source's figure never stands in for the record's own, and nothing is estimated.
License Data CC BY-NC 4.0 (opens in a new tab); free for personal, academic, civic and newsroom reporting with attribution. Using this data in a report? Support the record. Commercial use needs a license. Prose stays under copyright.
Cite this page Data Center Record, "St. Louis Armory Data Center Proposal", https://datacenterrecord.org/projects/st-louis-armory-data-center-mo, last verified November 6, 2026. CSV · JSON
Using this data in a report? Support the record. Commercial use needs a license.
Cite this page

Data Center Record, "St. Louis Armory Data Center Proposal", https://datacenterrecord.org/projects/st-louis-armory-data-center-mo. Data: Data Center Record, datacenterrecord.org, CC BY-NC 4.0.

The structured rows are CC BY-NC 4.0. Link to this page; that is what turns a reuse into a citation. Commercial use needs a license. Prose stays under copyright.

Report a change
For researchers
Stage
Proposed
Tier
built from one source
Tags
Built from one source
Coordinates
38.6318, -90.2375
How the location is known
Location from the site's street address.
Location source
https://www.stlouis-mo.gov/
Coordinate source
City of St. Louis Armory parcel
Location last verified
September 17, 2026
Published
September 5, 2026
Last verified
November 6, 2026
Not disclosed
Location source number, EPA registry id, Uses, Tenancy, Cooling, How capacity was disclosed, How water was disclosed, How acreage was disclosed, Interconnection, Capacity, if disclosed, Rating of the county's rows